Lodha Patel Estate
Completion date passedBorivali, Mumbai Suburban 400102 |Promoter: Macrotech Developers Limited
Project summary
As registered with MahaRERA
- RERA registrations
- 4
- Phases
- 4
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Jul 2023
P51800014860The latest completion date on record passed 3 years and 3 months ago.
- Registered
- 8 Jan 2018
- Promised
- 31 Jul 2023
Completion promised for 30 Oct 2023
P51800014869The latest completion date on record passed 3 years ago.
- Registered
- 8 Jan 2018
- Promised
- 30 Oct 2023
Completion promised for 31 Jul 2023
P51800014891The latest completion date on record passed 3 years and 3 months ago.
- Registered
- 9 Jan 2018
- Promised
- 31 Jul 2023
Completion pushed back 1 year and 6 months
P51800016528The latest completion date on record passed 1 year and 8 months ago.
- Registered
- 21 May 2018
- Promised
- 28 Aug 2023
- Revised
- 27 Feb 2025
4 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51800014860 | 8 Jan 2018 | 31 Jul 2023 | — | Macrotech Developers Limited | Project page |
| P51800014869 | 8 Jan 2018 | 30 Oct 2023 | — | Macrotech Developers Limited | Project page |
| P51800014891 | 9 Jan 2018 | 31 Jul 2023 | — | Macrotech Developers Limited | Project page |
| P51800016528 | 21 May 2018 | 28 Aug 2023 | 27 Feb 2025 | Macrotech Developers Limited | Project page |
Documents
5 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.