Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51900019176

NCP Commercial Tower 1 - Floor 23rd · Ward Fnorth, Mumbai City · Lodha Developers Limited

Promised for 30 Sep 2019 — that date has passed and MahaRERA does not mark the project complete.

7 years and 2 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Sep 2019, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Jan 2019View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51900019176

Is NCP Commercial Tower 1 - Floor 23rd delayed?

Yes. MahaRERA records a promised completion of 30 Sep 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51900019176.

Who is the promoter?

MahaRERA records Lodha Developers Limited as the promoter of P51900019176.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51900019176.

Answers are generated from the record.

Data through23 Nov 2026, 01:42SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology