Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passed1 extensionMahaRERA status: Certificate Signed

P51900000314

New Cuffe Parade - Lodha Dioro And Elisium · Ward Fnorth, Mumbai City · Macrotech Developers Limited

Promised for 30 Jun 2019 — that date has passed and MahaRERA does not mark the project complete.

7 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Deedo holds 1 extension certificate for this registration.
  • Risk: The latest completion date on record, 30 Jun 2019, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate15 Jul 2017View
Extension certificate16 Dec 2020View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51900000314

Is New Cuffe Parade - Lodha Dioro And Elisium delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51900000314.

Who is the promoter?

MahaRERA records Macrotech Developers Limited as the promoter of P51900000314.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51900000314.

Answers are generated from the record.

Data through23 Nov 2026, 01:37SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology