Delayed projects in Raigarh

1,042 MahaRERA projects in Raigarh are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 11 of 21.

ProjectLocalityPromisedRevisedDelivery
Shree Sai Srushti ParadiseArun Ramesh TamboliNeralJun 2023Jun 20233 yrs 5 mo late
Sunrise PlazaSymphony HomesVadghar (Ct)Jun 2023Jun 20233 yrs 5 mo late
Savitri VillaRavindra Sadashiv MahadikVadghar (Ct)Jun 2023Jun 20233 yrs 5 mo late
ShivkrishnaNimesh Gulabchand Chheda (HUF)GoregaonJun 2023Jun 20233 yrs 5 mo late
Swastik ResidencyRamanuj Sidhariram SharmaPalidevadJun 2023Jun 20233 yrs 5 mo late
The OnyxKashinath Shantaram PatilWahalJun 2023Jun 20233 yrs 5 mo late
TulipLiving Stone DevelopersUlaweJun 2023Jun 20233 yrs 5 mo late
United GardenUnited BuildersVichumbeJun 2023Jun 20253 yrs 5 mo late
VaikunthDivyesh NakraniUlaweJun 2023Jun 20243 yrs 5 mo late
Vaishnavi ResidencyRk Group Of InfraVadghar (Ct)Jun 2023Jun 20253 yrs 5 mo late
VakratundSantosh Dattu PatilKamotheJun 2023Jun 20233 yrs 5 mo late
Eshaanya Phase 2Ashwyn PatkarDhamniJul 2023Jul 20233 yrs 4 mo late
Hiland EmeraldMerchant ConstructionPen (M Cl)Jul 2023Jul 20233 yrs 4 mo late
Shalom ElegantJacob Verghese GeorgeUlaweJul 2023Dec 20253 yrs 4 mo late
Aspire GreenShriram Homebuild Developers LLPKhopoliJul 2023Jul 20233 yrs 4 mo late
Mahadevalay ApartmentShree DevelopersUlaweJul 2023Jul 20243 yrs 4 mo late
Megh DarshanDipali Darshan BaikarAmbepurJul 2023Jul 20243 yrs 4 mo late
Sai KutirGuru Sai BuildconVadghar (Ct)Jul 2023Jul 20233 yrs 4 mo late
Sarang IrisRcd ConstructionsPanvelJul 2023Jul 20233 yrs 4 mo late
Shree MoreshwarAshreet EnterprisesVadghar (Ct)Aug 2023Aug 20233 yrs 3 mo late
Satyam Co-Op Housing Society LtdVastu InfraKalamboliAug 2023Aug 20233 yrs 3 mo late
IndraGreenbricks Infradevelopers Pvt.ltd.KhambAug 2023Aug 20233 yrs 3 mo late
Shiv Krupa ResidencyTrimurti DevelopersPanvelAug 2023Aug 20243 yrs 3 mo late
Sushma ParkReena Roshan ShethWahalAug 2023Aug 20233 yrs 3 mo late
Saurabh Residency Wing DAshiana Builders and DevelopersUkrulSep 2023Jun 20263 yrs 2 mo late
Shree Krushnai-IShree Siddhivinayak EnterprisesAjivaliSep 2023Sep 20243 yrs 2 mo late
Balaji SaiPrakash Shankar KoliUlaweSep 2023Sep 20233 yrs 2 mo late
Elite ResidencyBuildcity DevelopersUlaweSep 2023Sep 20243 yrs 2 mo late
Falak CityFalak ConstructionGoregaonSep 2023Mar 20263 yrs 2 mo late
Ganga Shankar HeightsVikrant Anil TurekarVadghar (Ct)Sep 2023Sep 20263 yrs 2 mo late
Icon GalaxyIcon EnterprisesVadghar (Ct)Sep 2023Sep 20233 yrs 2 mo late
Kuber DwarkanathPaloma EnterprisesUlaweSep 2023Sep 20243 yrs 2 mo late
Kuber Nayan VillaKusum Ramesh MundhekarUlaweSep 2023Sep 20233 yrs 2 mo late
Om Sai ResidencyYuvraj Kisan OwalekarUlaweSep 2023Sep 20233 yrs 2 mo late
P R VillaManjula Pandurang MhatreWahalSep 2023Sep 20233 yrs 2 mo late
Sai KrupaSeema Kundan PatilWahalSep 2023Sep 20233 yrs 2 mo late
Sd Infra HomesSd Infra Builders And DevelopersVadghar (Ct)Sep 2023Sep 20243 yrs 2 mo late
Shivam ApartmentMaa Shitaladevi RealtyWahalSep 2023Sep 20233 yrs 2 mo late
Shree Vighnaharta ApartmentOm Anantaya DevelopersUlaweSep 2023Sep 20233 yrs 2 mo late
Sudarshan HeightsSameer Dattatray MasurkarKhopoliSep 2023Dec 20253 yrs 2 mo late
Shree GaneshSai DevelopersWahalSep 2023Sep 20233 yrs 2 mo late
Sky HeritageChandan Kailashchand TakBokadviraOct 2023Sep 20243 yrs 1 mo late
Seth Hari NiwasSameer Haribhau MhatreWahalOct 2023Jun 20253 yrs 1 mo late
Tathagat Chs LtdTathagat Chs LtdKalamboliOct 2023Oct 20233 yrs 1 mo late
SwaraEnvision InfraChinchvali GoheOct 2023Oct 20233 yrs 1 mo late
Winstar HeritageMaqsood Moinuddin SayedUlaweOct 2023Oct 20233 yrs 1 mo late
Cielo ApartmentCielo HeightsUranOct 2023Oct 20233 yrs 1 mo late
Padmavati ResidencySachin Ramdas PatilKarjatNov 2023Nov 20233 yrs late
Shanti KunjSanjay Bapurao DeshmukhKhalapurNov 2023Nov 20233 yrs late
Ananta SkyGh GroupKarjatNov 2023Nov 20233 yrs late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology