Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 1RK, 2BHK, Shop17 units in all
- Address
- Plot no 127, Sector 25, Pushpak NewPIN 410206
- Designated bank account
- 85
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year and 8 months
The latest completion date on record passed 1 year and 4 months ago.
- Registered
- 26 Apr 2019
- Promised
- 10 Oct 2023
- Revised
- 30 Jun 2025
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000020598 | 26 Apr 2019 | 10 Oct 2023 | 30 Jun 2025 | Sameer Haribhau Mhatre | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Seth Hari Niwas | 6 | 17 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
3 of 17 units booked (18%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 25.59 sq m · 275 sq ft | 6 | 2 |
| 1RK | 18.54 sq m · 200 sq ft | 8 | 0 |
| 2BHK | 50.71 sq m · 546 sq ft | 1 | 0 |
| Shop | 13.87 sq m · 149 sq ft | 2 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
2 documents held by Deedo, 70 filings listed on MahaRERA's project page
Legal
- Declaration Form Bform B sameer mhatre.pdf · uploaded 11 Apr 2019Source
- Legal Title reportTitle certificate sameer mhatre_compressed.pdf · uploaded 11 Apr 2019Source
- Legal Title reportsameer mhatre search report_compressed.pdf · uploaded 11 Apr 2019Source
- Declaration Form BForm B Seth.pdf · uploaded 12 Oct 2023Source
- Declaration Form BAffidavit.pdf · uploaded 27 Nov 2024Source
- Declaration Form BAffidavit .pdf · uploaded 5 Mar 2025Source
Show all 72 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)IOD.pdf · uploaded 4 Apr 2019Source
- 1 Building Plan Approval (IOD)IOD.pdf · uploaded 4 Apr 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 4 Apr 2019Source
- 1 Copy of the legal title reportTitle certificate sameer mhatre_compressed.pdf · uploaded 11 Apr 2019Source
- 2 Copy of the legal title reportsameer mhatre search report_compressed.pdf · uploaded 11 Apr 2019Source
- 1 Details of encumbrancessameer mhatre encumbrance.pdf · uploaded 11 Apr 2019Source
- 1 Declaration in FORM Bform B sameer mhatre.pdf · uploaded 11 Apr 2019Source
- 1 Certificates of CA (Form 3)Form 3 - Seth Hari Niwas_compressed.pdf · uploaded 13 Apr 2019Source
- 1 Proforma of Allotment letterAgreement .pdf · uploaded 19 Apr 2019Source
- 1 Disclosure of sold/ booked inventorySETH HARI NIWAS.pdf · uploaded 24 May 2021Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 12 Oct 2023Source
- 2 Declaration in FORM BForm B Seth.pdf · uploaded 12 Oct 2023Source
- 2 Disclosure of sold/ booked inventoryCircular 29.pdf · uploaded 12 Oct 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A 2019-20.pdf · uploaded 16 Oct 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A 2020-21.pdf · uploaded 16 Oct 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 2021-22.pdf · uploaded 16 Oct 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form2A 2022-23.pdf · uploaded 16 Oct 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Seth Hari Niwas.pdf · uploaded 25 Oct 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 March 23.pdf · uploaded 30 Oct 2023Source
- 2 Certificates of CA (Form 3)Form 3 March 23_11zon.pdf · uploaded 30 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 19-20.pdf · uploaded 30 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 20-21.pdf · uploaded 30 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 21-22.pdf · uploaded 30 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 22-23.pdf · uploaded 30 Oct 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 30-09-2024_11zon.pdf · uploaded 22 Oct 2024Source
- 1 CERSAI detailsDeclaration of CERSAI.pdf · uploaded 22 Oct 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A.pdf · uploaded 22 Oct 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 22 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 23-24.pdf · uploaded 22 Oct 2024Source
- 1 Declaration in FORM BAffidavit.pdf · uploaded 27 Nov 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Seth Hari Niwas.pdf · uploaded 4 Dec 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 30-09-2024 (2)_11zon.pdf · uploaded 4 Dec 2024Source
- 3 Certificates of CA (Form 3)Form 3 Sept Quarter_11zon.pdf · uploaded 4 Dec 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sept Quarter.pdf · uploaded 4 Dec 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 23-24.pdf · uploaded 4 Dec 2024Source
- 1 Disclosure of sold/ booked inventoryCircular 29.pdf · uploaded 14 Dec 2024Source
- 1 Certificates of CA (Form 3)Form 3 - Seth Hari Niwas as on 31-12-2023.pdf · uploaded 25 Feb 2025Source
- 2 Certificates of CA (Form 3)3 Certificates of CA (Form 3).pdf · uploaded 25 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Seth Hari Niwas as on December 2023.pdf · uploaded 25 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 25 Feb 2025Source
- 1 Declaration in FORM BAffidavit .pdf · uploaded 5 Mar 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (1).pdf · uploaded 5 Mar 2025Source
- 1 Certificates of CA (Form 3)CA Certificate (2)_11zon.pdf · uploaded 5 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer’s Certificate.pdf · uploaded 5 Mar 2025Source
- 1 Disclosure of sold/ booked inventoryInventory Details.pdf · uploaded 5 Mar 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)19-20.pdf · uploaded 18 Mar 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)20-21 (2).pdf · uploaded 18 Mar 2025Source
- 1 Other – TechnicalPERT Chart- STH.pdf · uploaded 18 Mar 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2021-22.pdf · uploaded 18 Mar 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2022-23.pdf · uploaded 18 Mar 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2023-24.pdf · uploaded 18 Mar 2025Source
Technical
Technical (Architect)
- DocumentForm 1 Seth Hari Niwas.pdf · uploaded 25 Oct 2023Source
- DocumentForm 1 30-09-2024_11zon.pdf · uploaded 22 Oct 2024Source
- DocumentForm 1 Seth Hari Niwas.pdf · uploaded 4 Dec 2024Source
- DocumentForm 1 30-09-2024 (2)_11zon.pdf · uploaded 4 Dec 2024Source
- DocumentForm 1 (1).pdf · uploaded 5 Mar 2025Source
Technical (Engineer)
- DocumentForm 2 March 23.pdf · uploaded 30 Oct 2023Source
- DocumentForm 2 Sept Quarter.pdf · uploaded 4 Dec 2024Source
- DocumentForm 2 - Seth Hari Niwas as on December 2023.pdf · uploaded 25 Feb 2025Source
- Document2 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 25 Feb 2025Source
- DocumentEngineer’s Certificate.pdf · uploaded 5 Mar 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Wahal, Panvel taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot no 128
- South
- Plot no 126
- East
- Plot no 116 and 117
- West
- 9 Mtr Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Atul Patel Architects | — |
| Other | Rera Easy | — |
Source: MahaRERA project page. Contact details are not shown.