Delayed projects in Maharashtra

8,426 MahaRERA projects in 36 districts are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 9 of 169.

ProjectLocalityPromisedRevisedDelivery
Elegant Residency Phase IIArihant Vastushilp Propcon Private LimitedPimpri Chinchawad (M Corp.)PuneMar 2019Sep 20247 yrs 8 mo late
Gokul PalaceAmararam Cholaji ChoudhariDhanoriPuneMar 2019Mar 20197 yrs 8 mo late
Golden LeafGolden ErectorsKondhwa KhurdPuneMar 2019Apr 20247 yrs 8 mo late
Grey Stone HeightsGreystone Spaces LLPNavi Mumbai (M Corp.)ThaneMar 2019Mar 20197 yrs 8 mo late
GurumauliVijay Vitthal ChandaneKondhve DhawadePuneMar 2019Mar 20197 yrs 8 mo late
Green Nest ResidencyShah BuildtechTiwareRaigarhMar 2019Mar 20197 yrs 8 mo late
Hapus Home A12Mega SpacesPune (M Corp.)PuneMar 2019Mar 20197 yrs 8 mo late
Harsh Raj Builders And DevelopersHarsh Raj Builders And DevelopersBhiwandi (M Corp.)ThaneMar 2019Sep 20207 yrs 8 mo late
Kalpatru EnterprisesBhawarlal Mohanlal JainBhiwandi (M Corp.)ThaneMar 2019Aug 20247 yrs 8 mo late
KedarnathA V AssociatesVangani (Ct)ThaneMar 2019Mar 20257 yrs 8 mo late
Multani ApartmentShewalkar Developers LimitedNagpur (M Corp.)NagpurMar 2019Jan 20267 yrs 8 mo late
Mahalaxmi ViharAvani Realtors & DevelopersKuwarbav (Ct)RatnagiriMar 2019Mar 20197 yrs 8 mo late
Manas GreenGreenovation Projects Pvt LtdBanerPuneMar 2019Mar 20197 yrs 8 mo late
Mangal MurtiPrakash Khanderao VetalAurangabad (M Corp.)AurangabadMar 2019Mar 20197 yrs 8 mo late
Mangla NiwasNasir Mohammedsaid SayyedPanvelRaigarhMar 2019Mar 20197 yrs 8 mo late
MelonBlue Skky RealtyWagholiPuneMar 2019Mar 20197 yrs 8 mo late
NautilusKapila EnterprisesTalavali Tarf KhandalaRaigarhMar 2019Mar 20217 yrs 8 mo late
Neumec VinayakNeumec VentureAndheriMumbai SuburbanMar 2019Sep 20207 yrs 8 mo late
Nikunj ApartmentsUrmi EnterprisesMahimPalgharMar 2019Mar 20197 yrs 8 mo late
Nirmal Lifestyle-AmethystNirmal Lifestyle LtdKurlaMumbai SuburbanMar 2019Jun 20267 yrs 8 mo late
OdinaRajyog EnterpriseKurlaMumbai SuburbanMar 2019Sep 20207 yrs 8 mo late
Orion Business ParkNeminath EnterprisesThane (M Corp.)ThaneMar 2019Sep 20207 yrs 8 mo late
Osho PrakashHarjeevan Dayaram ThakkarNaupadaThaneMar 2019Mar 20197 yrs 8 mo late
Parshvi ApartmentBhoomi Builder & DeveloperMahimPalgharMar 2019Sep 20227 yrs 8 mo late
Pushkar SignaturePushkar Homes Private LimitedNagpur (M Corp.)NagpurMar 2019Dec 20247 yrs 8 mo late
Pushpalaxmi ResidencyNikhil Kisan HoleGopalwadiPuneMar 2019Mar 20197 yrs 8 mo late
Parijat TowersBetter Builders And Infrastructure Private LtdAndheriMumbai SuburbanMar 2019Jun 20237 yrs 8 mo late
Prithvi Presidio, Buiding B, Phase-1Prithvi Edifice Pvt LtdHadapsarPuneMar 2019Sep 20227 yrs 8 mo late
Rajyog PrideV R AssociateAurangabad (Cb)AurangabadMar 2019Aug 20237 yrs 8 mo late
Rapid JewelPark View DevelopersHal Kh.RaigarhMar 2019Mar 20197 yrs 8 mo late
RoyalparkBankar Dugane AssociatesVarulwadiPuneMar 2019Mar 20227 yrs 8 mo late
Ramkrishna Ecstasy IISima purushottam KumarNavi Mumbai (M Corp.)ThaneMar 2019Dec 20217 yrs 8 mo late
S R PlazaS R Builders & DevelopersTaloje PanchnadRaigarhMar 2019Mar 20197 yrs 8 mo late
Saee ResidencyM S ConstructionsSolapur (M Corp.)SolapurMar 2019Mar 20197 yrs 8 mo late
Sai SankalpJai Ambe ConstructionsUlhasnagar (M Corp.)ThaneMar 2019Sep 20207 yrs 8 mo late
Sakshi EnclaveSakshi Saurabh DantDahisarThaneMar 2019Sep 20207 yrs 8 mo late
Sanjay Balgounda PatilSanjay Balgounda PatilIchalkaranji (M Cl)KolhapurMar 2019Mar 20227 yrs 8 mo late
Shahu ResidencyShinde Jadhav Builders And DevelopersGodoli (Ct)SataraMar 2019Mar 20197 yrs 8 mo late
Shakuntala Silver BlissOswal RealtorsKurlaMumbai SuburbanMar 2019Mar 20227 yrs 8 mo late
Sheesh MallJayashree Vinod PatkarKhed (M Cl)RatnagiriMar 2019Mar 20197 yrs 8 mo late
Shilp Vastu I BuildingVipul Motilal JainKasheliThaneMar 2019Mar 20197 yrs 8 mo late
Shiv MahimaDeep EnterprisesChendhreRaigarhMar 2019Mar 20197 yrs 8 mo late
Shiv Tirth ApartmentShivam Builders And DevelopersMahimPalgharMar 2019Mar 20227 yrs 8 mo late
Shrey-SumanSachin Gajanan SuraKhed (M Cl)RatnagiriMar 2019Mar 20197 yrs 8 mo late
Sudarshan EnterprisesHaresh Kaluram TawareBhiwandi (M Corp.)ThaneMar 2019Mar 20197 yrs 8 mo late
Suyojit BaugSuyojit Infrastructure Pvt. Ltd.NashikMar 2019Dec 20237 yrs 8 mo late
Sharayu ResidencySharayu RealtorsBhiwandi (M Corp.)ThaneMar 2019Mar 20197 yrs 8 mo late
Shree ApartmetnAdik Jayaram MhatreDombivliThaneMar 2019Jun 20227 yrs 8 mo late
Shree YashwantShree DattaGuru Construction CompanyPen RuralRaigarhMar 2019Mar 20217 yrs 8 mo late
Siddhi SamruddhiSanghvi DevelopersKatrajPuneMar 2019Nov 20217 yrs 8 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology