9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects7
Registrations10some projects hold several
Completion still due64 past their date
Median extension4 months60% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

10 MahaRERA registrations in Wadeghar

1 not yet due5 extended, not yet due4 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Wadeghar

7 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Ritz EuropaVikas Harakchand JainDue Apr 2031, extended 4 mo——
Triveni GalleriaGolden Arc Ventures LLPDue Apr 2030, extended 4 mo——
Shankheshwar PristineShankheshwar KreatersDue Dec 2028——
Shreeji AvenueShreeji BuildconCompleted—17%
Sai Sharnam- Tybe BAnjana Sahebrao ChavanCompleted, extended 9 mo—86%
All 7 projects →
Wadeghar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Anjana Sahebrao Chavan2 projects
  2. Golden Arc Ventures LLP1 project
  3. Shankheshwar Kreaters1 project
  4. Shreeji Buildcon1 project
  5. Vikas Harakchand Jain1 project
  6. Vpa Developers1 project

Wadeghar, in questions

How many projects in Wadeghar run late?

9 in 10 MahaRERA registrations (9 of 10): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Wadeghar by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology