RERA projects in Nagaon
2 projects under 2 MahaRERA registrations, registered 2021–2022. 50% have a completion date extended beyond the one promised.
Locality
2RERA projects
2Registrations
0Completion still due2 past their completion date
12 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2021 | 1 |
| 2022 | 1 |
Projects in Nagaon
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Reserve Bank Employees Kaustubh CHS LTDAditya Buildcon | P51700033866 | 14 Mar 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Anandi HeightPrathmesh Developers | P51700027975 | 21 Jan 2021 | 30 Jun 2023 | 29 Jun 2024 | Extended 12 mo | 0 |
Other localities in Kalyan
- Dombivli405 projects
- Kalyandombivali (M Corp.)206 projects
- Kalyan137 projects
- Chikanghar107 projects
- Titwala89 projects
- Kalyan-Dombivali (M Corp.)85 projects
- Khoni71 projects
- Katemanevali55 projects
- Manda52 projects
- Tisgaon48 projects
- Gandhare43 projects
- Adharwadi24 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Aditya Buildcon1 project
- Prathmesh Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology