Chikanghar, Thane
Deedo IDDL-THN-CHIKANGHAR9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects113
Registrations118some projects hold several
Completion still due6355 past their date
Median extension4 months56% of registrations extended
Regulatory cases7on 4 projects
9 in 10 registrations run late here
118 MahaRERA registrations in Chikanghar
2 completed12 not yet due51 extended, not yet due53 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Chikanghar
113 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| ShivamGagan Developers & Engineers | 6 yrs 8 mo late | — | 100% |
| Athena EnclaveJai Mata Di Developers | 2 yrs 11 mo late | — | 79% |
| Manali Heights A WingMitali Construction | Completed | — | 84% |
| Mangeshi FloraOm Realty | Completed | — | 38% |
| Shivaay ResidencyRohan Krishnapalsingh Thakur | 7 yrs 5 mo late | — | 83% |
| V Ten ResidencyV Ten Realty Private Limited | Completed, extended 6 mo | — | 100% |
| Ami Darshan E WingAarohi Development Corporation | Completed | — | — |
| Atmaram Kene ResidencyMega Developers | Completed | — | 23% |
| Pluto C WingBhakti Realtora | Completed | — | 59% |
| Tycoons Square AvenueTycoons Avanti Projects LLP | Due Jun 2027, extended 6 mo | — | 75% |
| Jigar Construction VenusPraful Haribhai Senjalia | Completed | — | 99% |
| Tycoons Square Avenue III Tower CTycoons Avanti Projects LLP | 3 yrs 10 mo late | — | 47% |
| NakshatraAbhishek Consttruction Co | Completed, extended 1 yr 8 mo | — | 88% |
Nearby: other villages in Kalyan
Most active promoters
- Mangesh Dashrath Gaikar5 projects
- Stonecrafters4 projects
- Tycoons Avanti Projects Llp4 projects
- Aarohi Development Corporation2 projects
- Dinesh Laxman Sonavane2 projects
- Gayatri Builders2 projects
- Mayur Group (Rd)2 projects
- Mayur Group (Rd)2 projects
- Namdev Construction2 projects
- Shakti Realtors2 projects
Chikanghar, in questions
How many projects in Chikanghar run late?
9 in 10 MahaRERA registrations (104 of 118): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Chikanghar by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology