7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects453
Registrations491some projects hold several
Completion still due279166 past their date
Median extension4 months55% of registrations extended
Regulatory cases34on 16 projects

7 in 10 registrations run late here

491 MahaRERA registrations in Bhiwandi and the places within it

3 completed90 not yet due189 extended, not yet due163 past even the latest date46 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Bhiwandi

453 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Nazir HeightsA M ConstructionsDue Jan 2027, extended 4 mo——
Imperial TowerUmar ConstructionDue Dec 2028——
Shree Sadan ComplexShree BuildconDue Dec 2026—52%
Hiranandani Woodspring Bldg A-Oakwood Bldg B-Bridgewood Bldg C-GreenwoodGolden Mile Builders LLPDue May 2028, extended 4 mo—56%
Kalyan SurabhiKalyan Buildcon5 mo late—30%
Shree Laxman ApartmentShri Gajanan EnterprisesDue Apr 2027, extended 4 mo——
Varsha HeightsB K GroupsDue Apr 2028, extended 4 mo—61%
Zara HeightsSajid Abul Kalam ShaikhDue Apr 2028, extended 4 mo—79%
Amruta ParkCheroba HomesDue Apr 2027, extended 4 mo—55%
Arihant Aaradhya Phase IIArihant Superstructures LimitedDue Apr 2031, extended 4 mo—17%
Royal EnclaveOm DevelopersDue Apr 2027, extended 4 mo——
Bagh-E-Firdous TowerCaption Real EstateDue Apr 2028, extended 4 mo——
Infinity Square28-Aeon Infinity LLPDue Apr 2028, extended 4 mo—14%
Tahrim HieghtsPhoenix Enterprises5 mo late——
Aai Mauli ParkHendar Laxman Mhatre11 mo late—57%
Siyara Fortune Building A Wing BShakti RealtyDue Apr 2028, extended 4 mo—23%
Krishna KunjRamesh Kasturchand Jain Tejawat2 yrs 2 mo late—30%
R K ApartmentFaiz Anis Ahmed KhanDue Apr 2028, extended 4 mo——
Vrundavan ParkShree Vastunirman DevelopersDue Dec 2027, extended 2 yrs 9 mo—63%
Kalyan AashiyanaAl Bruj Developers11 mo late—100%
Riddhi Siddhi ParkShree Ganesh DevelopersDue Jan 2030, extended 4 mo—34%
Arfa GardenQuba Homes LLPDue Apr 2027, extended 4 mo—77%
Royal ParkPens Builders & Developers LLPDue Apr 2030, extended 4 mo—24%
Ranghnath ApartmentMizab Ahmed Nasir Ahmed Punjabi1 yr 11 mo late——
Siyara Fortune B BuildingShakti RealtyDue Apr 2028, extended 4 mo—84%
Bhiwandi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Macrotech Developers Limited17 projects
  2. Lodha Developers Limited14 projects
  3. Arihant Enterprises7 projects
  4. Shakti Realty6 projects
  5. Infini Developers5 projects
  6. Adrika Developers Private Limited4 projects
  7. Al Araaf Infra Private Limited4 projects
  8. Siyara Realty Private Limited4 projects
  9. Kgi Realty Private Limited3 projects
  10. Maya Developer3 projects

Bhiwandi, in questions

How many projects in Bhiwandi run late?

7 in 10 MahaRERA registrations (352 of 491): their completion date was extended or has passed, data through 25 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhiwandi by Deedo. Medians on fewer than 3 deeds are not shown.

Data through25 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology