Bhiwandi, Thane
Deedo IDDL-THN-BHIWANDI7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects453
Registrations491some projects hold several
Completion still due279166 past their date
Median extension4 months55% of registrations extended
Regulatory cases34on 16 projects
7 in 10 registrations run late here
491 MahaRERA registrations in Bhiwandi and the places within it
3 completed90 not yet due189 extended, not yet due163 past even the latest date46 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Bhiwandi
453 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Nazir HeightsA M Constructions | Due Jan 2027, extended 4 mo | — | — |
| Imperial TowerUmar Construction | Due Dec 2028 | — | — |
| Shree Sadan ComplexShree Buildcon | Due Dec 2026 | — | 52% |
| Hiranandani Woodspring Bldg A-Oakwood Bldg B-Bridgewood Bldg C-GreenwoodGolden Mile Builders LLP | Due May 2028, extended 4 mo | — | 56% |
| Kalyan SurabhiKalyan Buildcon | 5 mo late | — | 30% |
| Shree Laxman ApartmentShri Gajanan Enterprises | Due Apr 2027, extended 4 mo | — | — |
| Varsha HeightsB K Groups | Due Apr 2028, extended 4 mo | — | 61% |
| Zara HeightsSajid Abul Kalam Shaikh | Due Apr 2028, extended 4 mo | — | 79% |
| Amruta ParkCheroba Homes | Due Apr 2027, extended 4 mo | — | 55% |
| Arihant Aaradhya Phase IIArihant Superstructures Limited | Due Apr 2031, extended 4 mo | — | 17% |
| Royal EnclaveOm Developers | Due Apr 2027, extended 4 mo | — | — |
| Bagh-E-Firdous TowerCaption Real Estate | Due Apr 2028, extended 4 mo | — | — |
| Infinity Square28-Aeon Infinity LLP | Due Apr 2028, extended 4 mo | — | 14% |
| Tahrim HieghtsPhoenix Enterprises | 5 mo late | — | — |
| Aai Mauli ParkHendar Laxman Mhatre | 11 mo late | — | 57% |
| Siyara Fortune Building A Wing BShakti Realty | Due Apr 2028, extended 4 mo | — | 23% |
| Krishna KunjRamesh Kasturchand Jain Tejawat | 2 yrs 2 mo late | — | 30% |
| R K ApartmentFaiz Anis Ahmed Khan | Due Apr 2028, extended 4 mo | — | — |
| Vrundavan ParkShree Vastunirman Developers | Due Dec 2027, extended 2 yrs 9 mo | — | 63% |
| Kalyan AashiyanaAl Bruj Developers | 11 mo late | — | 100% |
| Riddhi Siddhi ParkShree Ganesh Developers | Due Jan 2030, extended 4 mo | — | 34% |
| Arfa GardenQuba Homes LLP | Due Apr 2027, extended 4 mo | — | 77% |
| Royal ParkPens Builders & Developers LLP | Due Apr 2030, extended 4 mo | — | 24% |
| Ranghnath ApartmentMizab Ahmed Nasir Ahmed Punjabi | 1 yr 11 mo late | — | — |
| Siyara Fortune B BuildingShakti Realty | Due Apr 2028, extended 4 mo | — | 84% |
Nearby: other talukas in Thane
Most active promoters
- Macrotech Developers Limited17 projects
- Lodha Developers Limited14 projects
- Arihant Enterprises7 projects
- Shakti Realty6 projects
- Infini Developers5 projects
- Adrika Developers Private Limited4 projects
- Al Araaf Infra Private Limited4 projects
- Siyara Realty Private Limited4 projects
- Kgi Realty Private Limited3 projects
- Maya Developer3 projects
Bhiwandi, in questions
How many projects in Bhiwandi run late?
7 in 10 MahaRERA registrations (352 of 491): their completion date was extended or has passed, data through 25 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhiwandi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through25 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology