Shree Laxman Apartment
Deedo IDDP-THN-SE2VCompletion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 7% of its units are booked.
Kon (Ct), Thane 421311 · by Shri Gajanan Enterprises
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 1 Apr 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700050282
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700050282 | 1 Apr 2023 | 31 Dec 2026 | 30 Apr 2027 | Shri Gajanan Enterprises | Project page |
Documents120
1 document held by Deedo, 119 filings listed on MahaRERA's project page
Finance
- PAN Cardfirm pan.pdf · uploaded 31 Jan 2023Source
Legal
Migrated
- 1 PAN Cardfirm pan.pdf · uploaded 31 Jan 2023Source
- 1 Copy of the legal title reportTitle.pdf · uploaded 31 Jan 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 31 Jan 2023Source
- 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 31 Jan 2023Source
Show all 120 documentsShow fewer documents
Migrated
- 1 Declaration in FORM BPromoter Form-B.pdf · uploaded 31 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM - 1.pdf · uploaded 31 Jan 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 31 Jan 2023Source
- 1 Proforma of Allotment letterModel form of Allotment Letter.pdf · uploaded 31 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterNo Deviation.pdf · uploaded 31 Jan 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_200259184257_For_Asset_Based_Search_01_02_2023_14_10_08_547.pdf · uploaded 1 Feb 2023Source
- 1 Copy of Layout Approval (in case of layout)PLAN APPROVAL.pdf · uploaded 3 Feb 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentHPSCANNER5934 (1).pdf · uploaded 3 Feb 2023Source
- 1 a Details of encumbrances concerned to FinanceEmcumbrance Merged.pdf · uploaded 8 Mar 2023Source
- 1 b Details of encumbrances concerned to LegalEmcumbrance Merged.pdf · uploaded 8 Mar 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsMahendra disc int.pdf · uploaded 8 Mar 2023Source
- 2 Disclosure of Interest in Other Real Estate Organizationsujwala disc int.pdf · uploaded 8 Mar 2023Source
- 1 Proforma of Agreement for saleMAHARERA MARATHI FORMAT.pdf · uploaded 8 Mar 2023Source
- 1 Deviation Report with respect to model copy of Agreementdeviation.pdf · uploaded 8 Mar 2023Source
- 2 a Details of encumbrances concerned to FinanceEmcumbrance Merged.pdf · uploaded 15 Mar 2023Source
- 2 b Details of encumbrances concerned to LegalEmcumbrance Merged.pdf · uploaded 15 Mar 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about bank qry3.pdf · uploaded 21 Mar 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 31_merged QRY3.pdf · uploaded 27 Mar 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)June 2023.pdf · uploaded 3 Jun 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)September 2023.pdf · uploaded 3 Jun 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)December 2023.pdf · uploaded 3 Jun 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)March 2024.pdf · uploaded 3 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A JUNE 23.pdf · uploaded 3 Jun 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A SEP 23.pdf · uploaded 3 Jun 2024Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A DEC 23.pdf · uploaded 3 Jun 2024Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A MAR 24.pdf · uploaded 3 Jun 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)LAXMAN_FORM 1.pdf · uploaded 8 Aug 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 Aug 2024Source
- 5 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)LAXMAN_FORM 2A.pdf · uploaded 8 Aug 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 SIGNED.pdf · uploaded 2 Dec 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5_new signed.pdf · uploaded 2 Dec 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 14 Dec 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 14 Dec 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A.pdf · uploaded 14 Dec 2024Source
- 1 Disclosure of sold/ booked inventoryCIRCULAR 29 SIGN.pdf · uploaded 4 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 signed.pdf · uploaded 8 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SIGNED.pdf · uploaded 8 Jan 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SIGNED.pdf · uploaded 8 Jan 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SIGNED.pdf · uploaded 8 Jan 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 scan(Q1).pdf · uploaded 15 Feb 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SCAN (Q2).pdf · uploaded 15 Feb 2025Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Scan(Q3).pdf · uploaded 15 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_SIGNED.pdf · uploaded 19 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2_SIGNED.pdf · uploaded 19 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A_SIGNED.pdf · uploaded 24 Feb 2025Source
- 1 Disclosure of sold/ booked inventorycircular 29.pdf · uploaded 27 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 SIGN.pdf · uploaded 18 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 SIGN.pdf · uploaded 18 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A SIGN.pdf · uploaded 18 Apr 2025Source
- 1 Disclosure of sold/ booked inventorycircular 29 SIGNED.pdf · uploaded 6 May 2025Source
- Form 1June 2023.pdf · uploaded 14 Jun 2025Source
- Form 2Form 2.pdf · uploaded 14 Jun 2025Source
- Form 3Form 3 signed.pdf · uploaded 14 Jun 2025Source
- Disclosure of Sold and Booked InventoryCIRCULAR 29 SIGN 30-06-23.pdf · uploaded 14 Jun 2025Source
- Form 1September 2023.pdf · uploaded 14 Jun 2025Source
- Form 2Form 2.pdf · uploaded 14 Jun 2025Source
- Form 3FORM 3 SIGNED.pdf · uploaded 14 Jun 2025Source
- Disclosure of Sold and Booked InventoryCIRCULAR 29 SIGN 30-09-23.pdf · uploaded 14 Jun 2025Source
- Form 1December 2023.pdf · uploaded 14 Jun 2025Source
- Form 2Form 2.pdf · uploaded 14 Jun 2025Source
- Form 3FORM 3 SIGNED.pdf · uploaded 14 Jun 2025Source
- Disclosure of Sold and Booked InventoryCIRCULAR 29 SIGN 31-12-23.pdf · uploaded 14 Jun 2025Source
- Form 1March 2024.pdf · uploaded 14 Jun 2025Source
- Form 2Form 2.pdf · uploaded 14 Jun 2025Source
- Form 3FORM 3 SIGNED.pdf · uploaded 14 Jun 2025Source
- Disclosure of Sold and Booked InventoryCIRCULAR 29 SIGN 31-03-24.pdf · uploaded 14 Jun 2025Source
- Form 1FORM 1.pdf · uploaded 14 Jun 2025Source
- Form 2Form 2.pdf · uploaded 14 Jun 2025Source
- Form 3form 3 scan(Q1).pdf · uploaded 14 Jun 2025Source
- Disclosure of Sold and Booked InventoryCIRCULAR 29.pdf · uploaded 14 Jun 2025Source
- Form 1FORM-1.pdf · uploaded 14 Jun 2025Source
- Form 2FORM-2.pdf · uploaded 14 Jun 2025Source
- Form 3FORM 3 SCAN (Q2).pdf · uploaded 14 Jun 2025Source
- Disclosure of Sold and Booked InventoryCIRCULAR 29 SIGN.pdf · uploaded 14 Jun 2025Source
- Form 1FORM-1_SIGNED.pdf · uploaded 14 Jun 2025Source
- Form 2FORM-2_SIGNED.pdf · uploaded 14 Jun 2025Source
- Form 3FORM 3 Scan(Q3).pdf · uploaded 14 Jun 2025Source
- Disclosure of Sold and Booked InventoryCIRCULAR 29 SIGN.pdf · uploaded 14 Jun 2025Source
- Form 5 (FY 2023-2024)form 5_new signed.pdf · uploaded 14 Jun 2025Source
- Form 1FORM-1.pdf · uploaded 16 Jun 2025Source
- Form 2FORM-2.pdf · uploaded 16 Jun 2025Source
- Form 3FORM 3.pdf · uploaded 16 Jun 2025Source
- Disclosure of Sold and Booked InventoryCIRCULAR 29.pdf · uploaded 16 Jun 2025Source
- Form 2A (FY 2023-2024)GAJANAND FORM-2A 23-24.pdf · uploaded 14 Jul 2025Source
- Form 2A (FY 2024-2025)GAJANAND FORM-2A 24-25.pdf · uploaded 14 Jul 2025Source
- Form 2A (FY 2025-2026)GAJANAND FORM-2A 25-26.pdf · uploaded 14 Jul 2025Source
- Withdrawal Update Form 1FORM-1 GAJANANN.pdf · uploaded 21 Oct 2025Source
- Withdrawal Update Form 2FORM-2 GAJANAN.pdf · uploaded 21 Oct 2025Source
- Withdrawal Update Form 3form 3.pdf · uploaded 21 Oct 2025Source
- Withdrawal Update Form 1signFORM-1-.pdf · uploaded 5 Feb 2026Source
- Withdrawal Update Form 1signFORM-1-.pdf · uploaded 5 Feb 2026Source
- Withdrawal Update Form 2signFORM-2 GAJANAND ENT.pdf · uploaded 5 Feb 2026Source
- Withdrawal Update Form 2signFORM-2 GAJANAND ENT.pdf · uploaded 5 Feb 2026Source
- Withdrawal Update Form 3FINAL FORM 3.pdf · uploaded 5 Feb 2026Source
- Withdrawal Update Form 3FINAL FORM 3.pdf · uploaded 5 Feb 2026Source
- Form 5 (FY 2024-2025)Form 5.pdf · uploaded 5 Feb 2026Source
- Withdrawal Update Form 1FORM 1 Q4 signed.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 2FORM 2 Q4 signed.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 3form 3.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 1FORM-1.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2FORM-2.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3FORM 3 Q1 26-27.pdf · uploaded 20 Jul 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Hissa No 22, Survevy No 170
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- —15 units in all
- Address
- Survevy No 170, Hissa No 22, Survey No 170, Hissa no 22, Village Kon, Bhiwandi, Dist ThanePIN 421311
- Village
- kon (CT), Bhiwandi taluka
- Land area for this project
- 300 sq m (3,229 sq ft)
- Permissible built-up area
- 574 sq m (6,175 sq ft)
- Sanctioned built-up area
- 574 sq m (6,175 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Survevy No 170, Hissa No 22
Boundaries
- North
- Pimplas Road
- South
- Vijay Mhatres Right
- East
- 170-21
- West
- Survey No 170-19
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking15 units
15 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 15 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Miyaji & Associates | — |
| Chartered accountant | Bashmakh & Co | — |
| Chartered accountant | Karan Surendra Singh | — |
| Engineer | N A & Associates | — |
| Engineer | Shamoil Momin | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kon (Ct)
- Aai Mauli Park Building BRERA P51700081073
- Sai Darshan D WingRERA PR1330002501864
- Millat ArcadeRERA P51700080861
- Kalyan EliteRERA P51700080574
- Kalyan VatikaRERA P51700079636
- Magus City Tower 2 LunarRERA P51700077802
- The LivinRERA P51700055755
- Tahoora ComplexRERA P51700055023
All 34 projects in Kon (Ct) · Compare Shree Laxman Apartment with another project