Tahoora Complex
Deedo IDDP-THN-0ERMCompletion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.
Kon (Ct), Thane 421311 · by Shree Harekrishna Realtor
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 26 Feb 2024, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700055023
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700055023 | 26 Feb 2024 | 31 Dec 2026 | 30 Apr 2027 | Shree Harekrishna Realtor | Project page |
Documents96
1 document held by Deedo, 95 filings listed on MahaRERA's project page
Finance
- PAN Card1) Partnership Firm Pan.pdf · uploaded 9 Dec 2023Source
Legal
Migrated
- 1 PAN Card1) Partnership Firm Pan.pdf · uploaded 9 Dec 2023Source
- 1 Copy of the legal title report2) legal title report rera Hare Krishna.pdf · uploaded 9 Dec 2023Source
- 1 Copy of Layout Approval (in case of layout)5) Approved Layout Plan.pdf · uploaded 9 Dec 2023Source
- 1 Building Plan Approval / NA Order for plotted development5) Approved Layout Plan.pdf · uploaded 9 Dec 2023Source
Show all 96 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted development7) Commencement Certificate.pdf · uploaded 9 Dec 2023Source
- 1 Declaration about Commencement Certificate8) Format D.pdf · uploaded 9 Dec 2023Source
- 1 Declaration in FORM B9) Form B Partner.pdf · uploaded 9 Dec 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)10) Form 1 Architect Certificate.pdf · uploaded 9 Dec 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)11) Form 2 Engineers Certificate.pdf · uploaded 9 Dec 2023Source
- 1 Disclosure of Interest in Other Real Estate Organizations19)Annexure A Jessa Patel.pdf · uploaded 9 Dec 2023Source
- 2 Disclosure of Interest in Other Real Estate Organizations19) Annexure A Shamsuddin Pathan.pdf · uploaded 9 Dec 2023Source
- 1 Proforma of Allotment letter26) Model form of Allotment Letter.pdf · uploaded 9 Dec 2023Source
- 1 Deviation Report with respect to Allotment letter37) Deviation Regarding Allotment Letter.pdf · uploaded 9 Dec 2023Source
- 1 Deviation Report with respect to model copy of Agreement38) Deviation regarding agreement.pdf · uploaded 9 Dec 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 signed.pdf · uploaded 29 Dec 2023Source
- 1 a Details of encumbrances concerned to FinanceSelf Declaration Legal.pdf · uploaded 5 Feb 2024Source
- 1 b Details of encumbrances concerned to LegalSelf Declaration Legal.pdf · uploaded 5 Feb 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentPlinth Certificate.pdf · uploaded 5 Feb 2024Source
- 1 CERSAI detailsCERSAI Declaration.pdf · uploaded 5 Feb 2024Source
- 1 Proforma of Agreement for saleAFS DRAFT final.pdf · uploaded 5 Feb 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Declaration.pdf · uploaded 5 Feb 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentPage 2 building plan.pdf · uploaded 21 Feb 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 signed.pdf · uploaded 7 Mar 2025Source
- Withdrawal Update Form 110) Form 1 Architect Certificate.pdf · uploaded 21 Apr 2026Source
- Withdrawal Update Form 211) Form 2 Engineers Certificate.pdf · uploaded 21 Apr 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 Portal signed.pdf · uploaded 21 Apr 2026Source
- Form 1Form 1.pdf · uploaded 22 Apr 2026Source
- Form 2form 2.pdf · uploaded 22 Apr 2026Source
- Form 3Withdrawal Application Form3 Portal signed.pdf · uploaded 22 Apr 2026Source
- Disclosure of Sold and Booked InventoryINVENTORY Q4 23-24.pdf · uploaded 22 Apr 2026Source
- Form 1FORM 1.pdf · uploaded 22 Apr 2026Source
- Form 2FORM 2.pdf · uploaded 22 Apr 2026Source
- Form 3Form 3 Q1.pdf · uploaded 22 Apr 2026Source
- Disclosure of Sold and Booked InventoryINVENTORY Q1 24-25.pdf · uploaded 22 Apr 2026Source
- Form 1FORM 1.pdf · uploaded 22 Apr 2026Source
- Form 2FORM 2 .pdf · uploaded 22 Apr 2026Source
- Form 3form 3 Q2.pdf · uploaded 22 Apr 2026Source
- Disclosure of Sold and Booked InventoryINVENTORY Q2 24-25.pdf · uploaded 22 Apr 2026Source
- Form 1FORM 1.pdf · uploaded 22 Apr 2026Source
- Form 2FORM 2.pdf · uploaded 22 Apr 2026Source
- Form 3form 3 q3.pdf · uploaded 22 Apr 2026Source
- Disclosure of Sold and Booked InventoryINVENTORY Q3 24-25.pdf · uploaded 22 Apr 2026Source
- Form 1FORM 1.pdf · uploaded 22 Apr 2026Source
- Form 2FORM 2.pdf · uploaded 22 Apr 2026Source
- Form 3form 3 q4.pdf · uploaded 22 Apr 2026Source
- Disclosure of Sold and Booked InventoryINVENTORY Q4 24-25.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 1FORM 1 .pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 Portal signed.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 signed.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 3Q 3 Withdrawal Application Form3 signed .pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 signed.pdf · uploaded 22 Apr 2026Source
- Form 5 (FY 2024-2025)FORM 5 SHREE HARE KRISHNA REALTORS.pdf · uploaded 15 May 2026Source
- Form 5 (FY 2023-2024)Form 5 signed fy 2023-24.pdf · uploaded 26 May 2026Source
- Withdrawal Update Form 1FORM 1 FY 23-24 Q4.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 1FORM 1 FY 24-25 Q1.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 1FORM 1 FY 24-25 Q2.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 1FORM 1 FY 24-25 Q4.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 1FORM 1 FY 24-25 Q4.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 1FORM 1 FY 25-26 Q1.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 1FORM 1 FY 25-26 Q2.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 1FORM 1 FY 25-26 Q3.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 1FORM 1 FY 25-26 Q4.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 2FORM 2 FY 23-24 Q4.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 2FORM 2 FY 24-25 Q1.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 2FORM 2 FY 24-25 Q2.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 2FORM 2 FY 24-25 Q4.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 2FORM 2 FY 24-25 Q3.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 2FORM 2 FY 25-26 Q1.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 2FORM 2 FY 25-26 Q2.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 2FORM 2 FY 25-26 Q3.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 2FORM 2 FY 25-26 Q4.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 signed.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 signed.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 signed.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 signed.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 signed.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 signed.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 signed.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 signed.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3 signed.pdf · uploaded 5 Jun 2026Source
Technical
Technical (Architect)
- DocumentFORM 1 FY 25-26 Q4.pdf · uploaded 5 Jun 2026Source
Technical (Engineer)
- DocumentFORM 2 FY 25-26 Q4.pdf · uploaded 5 Jun 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 256/7
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK49 units in all
- Address
- 256/7, Bhiwandi Road, KonPIN 421311
- Village
- kon (CT), Bhiwandi taluka
- Land area for this project
- 1,420 sq m (15,285 sq ft)
- Permissible built-up area
- 2,251 sq m (24,232 sq ft)
- Sanctioned built-up area
- 2,251 sq m (24,232 sq ft)
- Designated bank account
- 212
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
256/7
Boundaries
- North
- tahoora park
- South
- dk homes
- East
- dk homes
- West
- shreeji buildcon
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking49 units
0 of 49 units booked (0%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 1 | 1BHK | 32.36 sq m · 348 sq ft | 24 | 0 |
| Building No 1 | 2BHK | 42.92 sq m · 462 sq ft | 4 | 0 |
| Building No 2 | 1BHK | 32.36 sq m · 348 sq ft | 18 | 0 |
| Building No 2 | 2BHK | 42.92 sq m · 462 sq ft | 3 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | AK Associates | — |
| Chartered accountant | Mamta Ishwarlal Watwani | — |
| Engineer | AK Associates | — |
Source: MahaRERA project page. Contact details are not shown.