Bhiwandi, Thane
Deedo IDDL-THN-BHIWANDI7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects453
Registrations491some projects hold several
Completion still due279166 past their date
Median extension4 months55% of registrations extended
Regulatory cases34on 16 projects
7 in 10 registrations run late here
491 MahaRERA registrations in Bhiwandi and the places within it
3 completed90 not yet due189 extended, not yet due163 past even the latest date46 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Bhiwandi
453 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Lodha Villa Royale TDLR 2Lodha Developers Limited | Due Dec 2027 | — | — |
| Sai Nida ApartmentPrashant Wagaji Gawande | Due Apr 2027, extended 4 mo | — | — |
| The Green SapphirreGreen World Realtors | Due Mar 2028, extended 4 mo | — | 18% |
| AyodhyaInfini Developers | Due Jul 2027, extended 4 mo | — | 29% |
| Devkrupa HeightsNilesh Satish Patil | Due Apr 2027, extended 4 mo | — | 21% |
| Samruddhi FloraSamruddhi Buildcon | Due Jan 2027 | — | 36% |
| Namo MaximaViren Kishor Jain | Due Apr 2027, extended 4 mo | — | 73% |
| Padmadisha Paradise Building Type - 3Padmadisha Paradise | Due Apr 2029, extended 4 mo | — | 29% |
| Usha ResidencyShree Budhdev Infra | Due Feb 2027, extended 4 mo | — | 80% |
| BelpatraMahadev Developers | Due Sep 2027 | — | — |
| Iflex SpacesRNV Developers Private Limited | Due Apr 2028, extended 4 mo | — | — |
| Upper Thane - Eden DLodha Developers Limited | Due Jul 2028, extended 4 mo | — | 26% |
| Dosti Greater Thane Sector 3A Cluster 1BAdrika Developers Private Limited | Due Oct 2030 | — | 26% |
| S.i. ArcadeSalman Iqbal Ahmed Momin | Due Oct 2028, extended 4 mo | — | — |
| Om Sai One ParkInfini Developers | Due Dec 2028 | — | — |
| Om SquareBuildtech Ventures Realty | Due Apr 2027, extended 4 mo | — | — |
| Munisuvrat Textile ParkMunisuvrat Commercial Parks LLP | Due Jul 2027, extended 4 mo | — | 33% |
| Upper Thane-IRIS Wing GLodha Developers Limited | Due Sep 2028, extended 4 mo | — | — |
| Upper Thane TiaraLodha Developers Limited | Due May 2028, extended 4 mo | — | 11% |
| Tirupati HeightsTirupati Builders And Developers | 1 yr 8 mo late | — | — |
| Dheeraj Heights-Phase-1Sashwat Home | Due Apr 2027, extended 4 mo | — | 93% |
| Bhumi ImperialBhumi Urban Lifespaces LLP | Due May 2027 | — | 1% |
| Dheeraj Heights- Phase-IISashwat Home | Due Apr 2027, extended 4 mo | — | 3% |
| Sai Deep ResidencyKishor Ratan Chaudhary | Due Apr 2027, extended 4 mo | — | 68% |
| Upper Thane - Eden ELodha Developers Limited | Completed | — | 49% |
Nearby: other talukas in Thane
Most active promoters
- Macrotech Developers Limited17 projects
- Lodha Developers Limited14 projects
- Arihant Enterprises7 projects
- Shakti Realty6 projects
- Infini Developers5 projects
- Adrika Developers Private Limited4 projects
- Al Araaf Infra Private Limited4 projects
- Siyara Realty Private Limited4 projects
- Kgi Realty Private Limited3 projects
- Maya Developer3 projects
Bhiwandi, in questions
How many projects in Bhiwandi run late?
7 in 10 MahaRERA registrations (352 of 491): their completion date was extended or has passed, data through 25 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhiwandi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through25 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology