S.i. Arcade
Deedo IDDP-THN-F1Y1Completion was pushed back 4 months, to Oct 2028; no MahaRERA orders on record; 0% of its units are booked.
Nizampur, Thane 421302 · by Salman Iqbal Ahmed Momin
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Oct 2028
- This projectRegistered 12 Oct 2023, completion promised 30 Jun 2028, revised to 30 Oct 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700053076
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700053076 | 12 Oct 2023 | 30 Jun 2028 | 30 Oct 2028 | Salman Iqbal Ahmed Momin | Project page |
Documents52
2 documents held by Deedo, 50 filings listed on MahaRERA's project page
Show all 52 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)BLUEPRINT.pdf · uploaded 23 Jun 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentBLUEPRINT.pdf · uploaded 23 Jun 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT_CERTIFICATE.pdf · uploaded 23 Jun 2023Source
- 1 Declaration about Commencement CertificateDEC_COMMENCEMENT CERTIFICATE.pdf · uploaded 23 Jun 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST.pdf · uploaded 23 Jun 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSEPARATE BANK.pdf · uploaded 23 Jun 2023Source
- 1 Copy of the legal title reportTitleCertificate.pdf · uploaded 24 Jun 2023Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 24 Jun 2023Source
- 1 Deviation Report with respect to Allotment letterdeviation from model.pdf · uploaded 24 Jun 2023Source
- 1 Deviation Report with respect to model copy of Agreementdeviation from model.pdf · uploaded 24 Jun 2023Source
- 1 Declaration in FORM BFORM_B.pdf · uploaded 27 Jun 2023Source
- 1 Other – TechnicalGmail.pdf · uploaded 28 Jun 2023Source
- 1 Proforma of Agreement for saleAgreementforSale.pdf · uploaded 13 Jul 2023Source
- 1 Proforma of Allotment letterAllotmentLetter.pdf · uploaded 13 Jul 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3_CA.pdf · uploaded 15 Jul 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-3.pdf · uploaded 13 Feb 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architecht certificate.pdf · uploaded 14 Feb 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate.pdf · uploaded 14 Feb 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 14 Feb 2024Source
- Form 1Form 1 AR certificate.pdf · uploaded 14 May 2025Source
- Form 2Form 2 Eng certificate.pdf · uploaded 14 May 2025Source
- Form 3Form-3-1.pdf · uploaded 14 May 2025Source
- Form 1Architecht certificate.pdf · uploaded 15 May 2025Source
- Form 2Engineer certificate.pdf · uploaded 15 May 2025Source
- Form 3Form-3.pdf · uploaded 15 May 2025Source
- Form 1Architecht certificate.pdf · uploaded 15 May 2025Source
- Form 2Engineer certificate.pdf · uploaded 15 May 2025Source
- Form 3Form-3.pdf · uploaded 15 May 2025Source
- Form 1Engineer certificate.pdf · uploaded 15 May 2025Source
- Form 2Architecht certificate.pdf · uploaded 15 May 2025Source
- Form 3Form-3.pdf · uploaded 15 May 2025Source
- Form 1Architect Certificate-Form 1.pdf · uploaded 9 Sep 2025Source
- Form 2Enginrrt certificate-Form 2.pdf · uploaded 9 Sep 2025Source
- Form 3Singed Form 3-Q3.pdf · uploaded 9 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold inventory.pdf · uploaded 9 Sep 2025View
- Form 1Architecture Certificate-Form 1.pdf · uploaded 9 Sep 2025Source
- Form 2Engineer Certificae- Form 2.pdf · uploaded 9 Sep 2025Source
- Form 3Singed Form 3-Q4.pdf · uploaded 9 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold inventory.pdf · uploaded 9 Sep 2025View
Technical
Technical (Architect)
- DocumentArchitecht certificate.pdf · uploaded 14 Feb 2024Source
Technical (Engineer)
- DocumentEngineer certificate.pdf · uploaded 14 Feb 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel CTS NO. 4378, S.NO. 45
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK28 units in all
- Address
- S.NO. 45, CTS NO. 4378, Nizampura, NizampuraPIN 421302
- Village
- Bhiwandi (M Corp.), Bhiwandi taluka
- Land area for this project
- 773 sq m (8,320 sq ft)
- Permissible built-up area
- 2,400 sq m (25,833 sq ft)
- Sanctioned built-up area
- 2,400 sq m (25,833 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S.NO. 45, CTS NO. 4378
Boundaries
- North
- 12 Mtr DP Road
- South
- Bharmal
- East
- Khairunnisa
- West
- Zubair Khan and others 4
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking28 units
0 of 28 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 40.64 sq m · 437 sq ft | 14 | 0 |
| 2BHK | 60.86 sq m · 655 sq ft | 7 | 0 |
| 2BHK | 65.77 sq m · 708 sq ft | 7 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | M/s Shaikh Shams & Associate | — |
| Chartered accountant | M/s A T ANSARI & ASSOCIATES | — |
| Chartered accountant | Saif Ansari & Co | — |
| Engineer | M/s Space Consulting Engineers | — |
Source: MahaRERA project page. Contact details are not shown.