7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects453
Registrations491some projects hold several
Completion still due279166 past their date
Median extension4 months55% of registrations extended
Regulatory cases34on 16 projects

7 in 10 registrations run late here

491 MahaRERA registrations in Bhiwandi and the places within it

3 completed90 not yet due189 extended, not yet due163 past even the latest date46 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Bhiwandi

453 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Kalyan SquareKagvin VenturesDue Dec 2027—85%
DGT Sector 3AAdrika Developers Private LimitedDue Aug 2028—62%
Ameena HeightsQuba Realty LLP2 yrs 5 mo late——
Laxman ResidencyCrystal KrishrajDue Apr 2027, extended 4 mo—3%
Babu Patel Heights - Prop. Rizwan Gulam Rasool ShaikhMohd Rizwan Gulam Rasool Shaikh1 yr 2 mo late——
Upper Thane-SupremusLodha Developers LimitedDue May 2028—56%
Raghunath HeightsKhrushna Infrastructure Builders & DevelopersDue Dec 2028, extended 3 yrs—4%
Sadri PlazaShubh EnterprisesDue Apr 2027, extended 4 mo—24%
Neelkanth SadanShreeji EnterprisesDue Jul 2027—39%
Noor ResidencyAl Araaf Infra Private Limited1 yr 5 mo late——
Star HomesBhiwandi Developers2 mo late—74%
Sai Platinum ResidencyMM Landmark Realty LLPDue Feb 2027, extended 4 mo—24%
Shree Krishna KunjBhagwati Builders And Developers1 yr 6 mo late—22%
Rukmani ResidencyClay Nest DevelopersDue Apr 2028, extended 4 mo——
Shambhu Shankar ResidencyVidisha ConstructionsDue Apr 2027, extended 4 mo—79%
Alpha ResidencyAgneta ConstructionsCompleted——
Datta Srushti ComplexBhanudas Dasharath PatilDue Apr 2030, extended 4 mo—3%
Olivia BlissJai Bhawani Orchid Infra LLPDue Apr 2027, extended 4 mo——
Omkar Residency A-WingK K GroupDue Dec 2026——
Kohinoor ResidencyAbrar Haroon KhanDue Apr 2027, extended 4 mo——
Rose ResidencyKunal Ramesh KaraniyaDue Jan 2027, extended 4 mo—9%
Yunus ResidencyAl Araaf Infra Private Limited1 yr 5 mo late——
Marine HeightsQuba Realty LLPDue Jun 2028—29%
Nisar Zulekha ComplexNisar Ahmed Ramzan MominDue Jul 2027, extended 4 mo——
Giridhar ApartmentOm Enterprises1 yr 11 mo late—25%
Bhiwandi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Macrotech Developers Limited17 projects
  2. Lodha Developers Limited14 projects
  3. Arihant Enterprises7 projects
  4. Shakti Realty6 projects
  5. Infini Developers5 projects
  6. Adrika Developers Private Limited4 projects
  7. Al Araaf Infra Private Limited4 projects
  8. Siyara Realty Private Limited4 projects
  9. Kgi Realty Private Limited3 projects
  10. Maya Developer3 projects

Bhiwandi, in questions

How many projects in Bhiwandi run late?

7 in 10 MahaRERA registrations (352 of 491): their completion date was extended or has passed, data through 25 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhiwandi by Deedo. Medians on fewer than 3 deeds are not shown.

Data through25 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology