Bhiwandi, Thane
Deedo IDDL-THN-BHIWANDI7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects453
Registrations491some projects hold several
Completion still due279166 past their date
Median extension4 months55% of registrations extended
Regulatory cases34on 16 projects
7 in 10 registrations run late here
491 MahaRERA registrations in Bhiwandi and the places within it
3 completed90 not yet due189 extended, not yet due163 past even the latest date46 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Bhiwandi
453 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Arihant Aaradhya Phase IArihant Superstructures Limited | Due Jul 2029, extended 4 mo | — | 65% |
| Magus City Tower 1 SeleneMagus Infratech Private Limited | Completed | — | 76% |
| Swarup TowerBaba Realty | Due Dec 2026, extended 2 yrs | — | — |
| Osians Garden - Phase-IIGlacier Dwellings LLP | Due Dec 2028 | — | — |
| Sai Narayana ResidencyMM Landmark Realty LLP | Due Apr 2027, extended 4 mo | — | — |
| Seven HeightsOvais Mudabbir Bardi | Completed | — | 62% |
| Shree Sai Saburi Apartment-Building BShree Saishraddha Enterprises | 8 mo late | — | — |
| Siyara IconShakti Realty | Due Apr 2029, extended 4 mo | — | 14% |
| Upper Thane-Casa EdenLodha Developers Limited | Completed | — | 86% |
| Upper Thane IRISLodha Developers Limited | Due Jul 2028, extended 4 mo | — | — |
| Zircon HeightsIqbal Abdul Rauf Punjabi | Completed, extended 6 mo | — | — |
| Sairaj HeightsVpm Jairaj Developers | Due Jul 2027, extended 4 mo | — | 62% |
| Varhaala HeightsSarvashiva Enterprises | Due Jul 2028, extended 4 mo | — | — |
| AtlanticRiddhi Siddhi Enterprises | Due Jul 2027, extended 4 mo | — | 28% |
| Kalyan ResidencySm Life Space Private Limited | Due Dec 2028 | — | — |
| Center OneMura Realty LLP | Due Apr 2027, extended 4 mo | — | — |
| Samruddhi HeightsShree Samruddhi Corporation | Completed | — | 57% |
| Kalyan ViharHonest Developers | Due Dec 2029 | — | 42% |
| Vrindavan ResidencyAkash Developers | Completed | — | — |
| Real HeightsMohammad Shafique Mohammad Rafique Momin | Completed, extended 1 mo | — | 69% |
| Sai Krupa ApartmentVinit Subhash Mukadam | 2 yrs late | — | — |
| Pathan TowerRiyasat Ali Nizamuddin Shaikh | Due Apr 2029, extended 4 mo | — | — |
| Regal Square Ph 4 Tower 6 And 8Dev Drashti Realty Private Limited | Due Apr 2028, extended 4 mo | — | 10% |
| Mahindra Happinest Kalyan 2 ProjectMahindra Lifespace Developers limited | Due Dec 2028 | — | — |
| Ornate RiseOrnate Buildcon Developers | Due Apr 2027, extended 4 mo | — | — |
Nearby: other talukas in Thane
Most active promoters
- Macrotech Developers Limited17 projects
- Lodha Developers Limited14 projects
- Arihant Enterprises7 projects
- Shakti Realty6 projects
- Infini Developers5 projects
- Adrika Developers Private Limited4 projects
- Al Araaf Infra Private Limited4 projects
- Siyara Realty Private Limited4 projects
- Kgi Realty Private Limited3 projects
- Maya Developer3 projects
Bhiwandi, in questions
How many projects in Bhiwandi run late?
7 in 10 MahaRERA registrations (352 of 491): their completion date was extended or has passed, data through 25 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhiwandi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through25 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology