7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects453
Registrations491some projects hold several
Completion still due279166 past their date
Median extension4 months55% of registrations extended
Regulatory cases34on 16 projects

7 in 10 registrations run late here

491 MahaRERA registrations in Bhiwandi and the places within it

3 completed90 not yet due189 extended, not yet due163 past even the latest date46 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Bhiwandi

453 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Arihant Aaradhya Phase IArihant Superstructures LimitedDue Jul 2029, extended 4 mo—65%
Magus City Tower 1 SeleneMagus Infratech Private LimitedCompleted—76%
Swarup TowerBaba RealtyDue Dec 2026, extended 2 yrs——
Osians Garden - Phase-IIGlacier Dwellings LLPDue Dec 2028——
Sai Narayana ResidencyMM Landmark Realty LLPDue Apr 2027, extended 4 mo——
Seven HeightsOvais Mudabbir BardiCompleted—62%
Shree Sai Saburi Apartment-Building BShree Saishraddha Enterprises8 mo late——
Siyara IconShakti RealtyDue Apr 2029, extended 4 mo—14%
Upper Thane-Casa EdenLodha Developers LimitedCompleted—86%
Upper Thane IRISLodha Developers LimitedDue Jul 2028, extended 4 mo——
Zircon HeightsIqbal Abdul Rauf PunjabiCompleted, extended 6 mo——
Sairaj HeightsVpm Jairaj DevelopersDue Jul 2027, extended 4 mo—62%
Varhaala HeightsSarvashiva EnterprisesDue Jul 2028, extended 4 mo——
AtlanticRiddhi Siddhi EnterprisesDue Jul 2027, extended 4 mo—28%
Kalyan ResidencySm Life Space Private LimitedDue Dec 2028——
Center OneMura Realty LLPDue Apr 2027, extended 4 mo——
Samruddhi HeightsShree Samruddhi CorporationCompleted—57%
Kalyan ViharHonest DevelopersDue Dec 2029—42%
Vrindavan ResidencyAkash DevelopersCompleted——
Real HeightsMohammad Shafique Mohammad Rafique MominCompleted, extended 1 mo—69%
Sai Krupa ApartmentVinit Subhash Mukadam2 yrs late——
Pathan TowerRiyasat Ali Nizamuddin ShaikhDue Apr 2029, extended 4 mo——
Regal Square Ph 4 Tower 6 And 8Dev Drashti Realty Private LimitedDue Apr 2028, extended 4 mo—10%
Mahindra Happinest Kalyan 2 ProjectMahindra Lifespace Developers limitedDue Dec 2028——
Ornate RiseOrnate Buildcon DevelopersDue Apr 2027, extended 4 mo——
Bhiwandi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Macrotech Developers Limited17 projects
  2. Lodha Developers Limited14 projects
  3. Arihant Enterprises7 projects
  4. Shakti Realty6 projects
  5. Infini Developers5 projects
  6. Adrika Developers Private Limited4 projects
  7. Al Araaf Infra Private Limited4 projects
  8. Siyara Realty Private Limited4 projects
  9. Kgi Realty Private Limited3 projects
  10. Maya Developer3 projects

Bhiwandi, in questions

How many projects in Bhiwandi run late?

7 in 10 MahaRERA registrations (352 of 491): their completion date was extended or has passed, data through 25 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhiwandi by Deedo. Medians on fewer than 3 deeds are not shown.

Data through25 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology