Bhiwandi (M Corp.), Thane 421302 |Promoter: 28-Aeon Infinity LLP

22 Feb 2023Registered with MahaRERA
31 Dec 2027Promised completion
30 Apr 2028Revised completionPushed back 4 months
1Building
110Units registered15 booked (14%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK, 3BHK, Office space, Shop110 units in all
Address
C.T.S. No. 434P, Kaneri, Kaneri, BhiwandiPIN 421302
Designated bank account
76
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
22 Feb 2023
Promised
31 Dec 2027
Revised
30 Apr 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170004968722 Feb 202331 Dec 202730 Apr 202828-Aeon Infinity LLPProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Type -A16106

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

15 of 110 units booked (14%), as the promoter reported to MahaRERA

2BHK · 3 units3BHK · 5 unitsOffice space · 83 unitsShop · 19 units
BuildingTypeCarpet areaUnitsBooked
Type -A2BHK64.17 sq m · 691 sq ft10
Type -A2BHK65.64 sq m · 707 sq ft10
Type -A2BHK67.23 sq m · 724 sq ft10
Type -A3BHK55.32 sq m · 595 sq ft10
Type -A3BHK81.8 sq m · 880 sq ft10
Type -A3BHK82.44 sq m · 887 sq ft10
Type -A3BHK85.58 sq m · 921 sq ft10
Type -A3BHK89.49 sq m · 963 sq ft10
Show all 54 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Type -AOffice space12.66 sq m · 136 sq ft50
Type -AOffice space29.17 sq m · 314 sq ft10
Type -AOffice space29.39 sq m · 316 sq ft41
Type -AOffice space31.2 sq m · 336 sq ft10
Type -AOffice space31.22 sq m · 336 sq ft41
Type -AOffice space32.71 sq m · 352 sq ft51
Type -AOffice space32.87 sq m · 354 sq ft41
Type -AOffice space33.02 sq m · 355 sq ft10
Type -AOffice space33.05 sq m · 356 sq ft10
Type -AOffice space33.16 sq m · 357 sq ft41
Type -AOffice space33.21 sq m · 357 sq ft50
Type -AOffice space35.09 sq m · 378 sq ft10
Type -AOffice space35.48 sq m · 382 sq ft41
Type -AOffice space37.78 sq m · 407 sq ft40
Type -AOffice space37.8 sq m · 407 sq ft10
Type -AOffice space38.61 sq m · 416 sq ft41
Type -AOffice space38.63 sq m · 416 sq ft10
Type -AOffice space41.66 sq m · 448 sq ft10
Type -AOffice space42.81 sq m · 461 sq ft10
Type -AOffice space46.78 sq m · 504 sq ft11
Type -AOffice space47.25 sq m · 509 sq ft10
Type -AOffice space47.48 sq m · 511 sq ft41
Type -AOffice space49.04 sq m · 528 sq ft10
Type -AOffice space51.51 sq m · 554 sq ft41
Type -AOffice space54.68 sq m · 589 sq ft40
Type -AOffice space70.4 sq m · 758 sq ft40
Type -AOffice space72.4 sq m · 779 sq ft40
Type -AOffice space90.51 sq m · 974 sq ft40
Type -AShop14.72 sq m · 158 sq ft10
Type -AShop18.74 sq m · 202 sq ft10
Type -AShop24.1 sq m · 259 sq ft10
Type -AShop26.29 sq m · 283 sq ft10
Type -AShop28.76 sq m · 310 sq ft31
Type -AShop36.22 sq m · 390 sq ft11
Type -AShop38.66 sq m · 416 sq ft10
Type -AShop39.07 sq m · 421 sq ft11
Type -AShop39.17 sq m · 422 sq ft10
Type -AShop42.68 sq m · 459 sq ft11
Type -AShop44.75 sq m · 482 sq ft11
Type -AShop46.18 sq m · 497 sq ft10
Type -AShop47.27 sq m · 509 sq ft10
Type -AShop53.41 sq m · 575 sq ft10
Type -AShop59.92 sq m · 645 sq ft10
Type -AShop68.68 sq m · 739 sq ft10
Type -AShop74.09 sq m · 797 sq ft10
Type -BOffice space66.04 sq m · 711 sq ft40

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 104 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 16 Jan 2023Source
  • OthersFORM 5 - FY 24-25.pdf · uploaded 7 Feb 2026Source
  • OthersDECL OF SEC UNSECURED LOAN - PROFILE UPDATE.pdf · uploaded 7 Feb 2026Source
  • OthersDECL OF PROMOTER TYPE A1 NOT FOR SALE WITH REVISED CC AND PLAN.pdf · uploaded 7 Feb 2026Source

Legal

  • Declaration Form BForm B_ Promoter.pdf · uploaded 31 Jan 2023Source
  • Legal Title reportorganized (63)_11zon.pdf · uploaded 10 Feb 2023Source

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentInfinity square CC.pdf · uploaded 14 Jan 2023Source
Show all 105 documentsShow fewer documents

Migrated

  • 1 PAN CardPAN.pdf · uploaded 16 Jan 2023Source
  • 1 Copy of Layout Approval (in case of layout)Sheet-1_compressed.pdf · uploaded 16 Jan 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentSheet-2_11zon_merged_11zon.pdf · uploaded 16 Jan 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentSheet-5_11zon_merged_11zon.pdf · uploaded 16 Jan 2023Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Finance.pdf · uploaded 31 Jan 2023Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Legal.pdf · uploaded 31 Jan 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Finance.pdf · uploaded 31 Jan 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Legal.pdf · uploaded 31 Jan 2023Source
  • 1 Declaration about Commencement CertificateFORMAT D.pdf · uploaded 31 Jan 2023Source
  • 1 Declaration in FORM BForm B_ Promoter.pdf · uploaded 31 Jan 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnequre A -.pdf · uploaded 31 Jan 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 31 Jan 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report.pdf · uploaded 31 Jan 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report 1 (1)_compressed.pdf · uploaded 31 Jan 2023Source
  • 1 CERSAI detailsCERSAI_Search_Report_200259267562_For_Asset_Based_Search_02_02_2023_12_18_35_773.pdf · uploaded 2 Feb 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 (2) (1)_compressed.pdf · uploaded 2 Feb 2023Source
  • 1 Copy of the legal title reportorganized (63)_11zon.pdf · uploaded 10 Feb 2023Source
  • 1 Proforma of Allotment letterNew Allotment Letter_AEON infinity LLP_Infinity square_050123.pdf · uploaded 10 Feb 2023Source
  • 1 Proforma of Agreement for saleFinal AFS Infinity 150223.pdf · uploaded 15 Feb 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 ( MARCH 2023).pdf · uploaded 23 Nov 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 ( JUNE 2023 ).pdf · uploaded 23 Nov 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1( SEP 2023 ).pdf · uploaded 23 Nov 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2( MARCH 2023).pdf · uploaded 23 Nov 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2( JUNE 2023 ).pdf · uploaded 23 Nov 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2( SEP 2023 ).pdf · uploaded 23 Nov 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Quality Assurance-Form 2A Infinity Square -Anjum bhai.pdf · uploaded 23 Nov 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 31ST MARCH 23_compressed.pdf · uploaded 23 Nov 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 30TH JUNE 23_compressed.pdf · uploaded 23 Nov 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 30TH SEPT 23_compressed.pdf · uploaded 23 Nov 2023Source
  • 1 Disclosure of sold/ booked inventoryINVENTORY SOLD.pdf · uploaded 27 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 FINAL .pdf · uploaded 27 Nov 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)UPDATED Q1 FORM -1 ( MARCH 2023).pdf · uploaded 18 Dec 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)UPDATED Q2 FORM-1 ( JUNE 2023 ).pdf · uploaded 18 Dec 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)UPDATED Q3 FORM-1( SEP 2023 ).pdf · uploaded 18 Dec 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q4_DEC-23_FORM-1_INFINITY.pdf · uploaded 25 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4_DEC-23_FORM-2_INFINITY.pdf · uploaded 25 Jan 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FROM 3 28 AEON INFINITY LLP_11zon.pdf · uploaded 25 Jan 2024Source
  • 2 Disclosure of sold/ booked inventoryDISCLOURE OF SOLD UNSOLD INFINITY SQUARE.pdf · uploaded 12 Feb 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 07FEB2024 INFINITY SQUARE_11zon.pdf · uploaded 12 Feb 2024Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A.pdf · uploaded 12 Feb 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 23 Apr 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 23 Apr 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_11zon.pdf · uploaded 23 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)28 aeon infinity FORM 2A.pdf · uploaded 14 May 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Scan_0017.pdf · uploaded 22 Jul 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Scan_0016.pdf · uploaded 22 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 28 AEON INFINITY SEPT 24.pdf · uploaded 6 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)28 aeon infinity form 3 june 2024_11zon.pdf · uploaded 6 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 28 infinity aept-2024_11zon.pdf · uploaded 6 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SEPT 24.pdf · uploaded 6 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 28- INFINITY.pdf · uploaded 6 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)INFINITY FORM 1.pdf · uploaded 18 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 INFINITY_11zon.pdf · uploaded 18 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 INFINITY.pdf · uploaded 18 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)AEON - FORM 1 MARCH 2025.pdf · uploaded 22 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 28AEON MARCH 25_11zon.pdf · uploaded 22 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)AEON - FORM 2 MARCH 2025.pdf · uploaded 22 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)AEON - FORM 2A FY 24-25.pdf · uploaded 22 Apr 2025Source
  • Form 1form 1 28 infinity.pdf · uploaded 18 Jul 2025Source
  • Form 2form 2 28 infinity.pdf · uploaded 18 Jul 2025Source
  • Form 3from3 28 infinity_11zon.pdf · uploaded 18 Jul 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD.pdf · uploaded 18 Jul 2025Source
  • Form 1form-1 consulting engineers certificate (upto 30 th sep 2025) SEPT 25.pdf · uploaded 15 Oct 2025Source
  • Form 2Form 2 Engineer Certificate (Infinity) SEPT 25_compressed.pdf · uploaded 15 Oct 2025Source
  • Form 3FORM-3 -AEON SEPT 25 SIGNED.pdf · uploaded 15 Oct 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD DICSLCOSURE- SIGNED.pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 1FORM 1- 28AEON - DEC25 - FOR QPR.pdf · uploaded 2 Feb 2026Source
  • Withdrawal Update Form 2FORM 2- 28AEON - DEC25 - FOR QPR.pdf · uploaded 2 Feb 2026Source
  • Withdrawal Update Form 3FORM 3 - 28 AEON - DEC 2025-FOR QPR-1.pdf · uploaded 2 Feb 2026Source
  • Form 2A (FY 2024-2025)FORM 2A - FY 24-25.pdf · uploaded 6 Feb 2026Source
  • Form 5 (FY 2024-2025)FORM 5 - FY 24-25.pdf · uploaded 7 Feb 2026Source
  • Withdrawal Update Form 1Form 1 Consulting Engineers Certificate 21-05-2026.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 2Form 2 Engineers Certificate 21-05-2026.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 3Form 3 4th Qrtr final.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 1Form 1(Qter 1 April to June 2026).pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2Form 2(Qter 1 April to June 2026).pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3revised frm 3 june 2026_11zon.pdf · uploaded 20 Jul 2026Source

Technical

  • DocumentSheet-1_compressed.pdf · uploaded 16 Jan 2023Source
  • DocumentSheet-2_11zon_merged_11zon.pdf · uploaded 16 Jan 2023Source
  • DocumentSheet-5_11zon_merged_11zon.pdf · uploaded 16 Jan 2023Source
  • DocumentSHEET 2 - PARKING STATEMENT.pdf · uploaded 6 Feb 2026Source
  • DocumentSHEET 3 AND 4 - GROUND FLOOR TO 6TH FLOOR.pdf · uploaded 6 Feb 2026Source
  • DocumentSHEET 5 AND 6 - 7TH FLOOR TO 15TH FLOOR.pdf · uploaded 6 Feb 2026Source
  • DocumentANNEXURE A - 28AEON INFINITY.pdf · uploaded 6 Feb 2026Source
  • OthersFORMAT D - DECL OF CC - 28AEON.pdf · uploaded 6 Feb 2026Source
  • OthersFORM 2- 28 AEON - FOR CORRECTION.pdf · uploaded 6 Feb 2026Source
  • OthersDECL OF PROMOTER TYPE A1 NOT FOR SALE WITH REVISED CC AND PLAN.pdf · uploaded 7 Feb 2026Source
  • OthersFORM 1 - 28AEON - FOR CORRECTION - SIGEND.pdf · uploaded 7 Feb 2026Source
  • DocumentSHEET 1 - LAYOUT - HIGHLIGHTED.pdf · uploaded 1 Apr 2026Source

Technical (Architect)

  • DocumentFORM 1 28 AEON INFINITY SEPT 24.pdf · uploaded 6 Nov 2024Source
  • DocumentINFINITY FORM 1.pdf · uploaded 18 Jan 2025Source
  • DocumentAEON - FORM 1 MARCH 2025.pdf · uploaded 22 Apr 2025Source
  • DocumentForm 1(Qter 1 April to June 2026).pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentFORM 2 SEPT 24.pdf · uploaded 6 Nov 2024Source
  • DocumentFORM 2 INFINITY.pdf · uploaded 18 Jan 2025Source
  • DocumentAEON - FORM 2 MARCH 2025.pdf · uploaded 22 Apr 2025Source
  • DocumentForm 2(Qter 1 April to June 2026).pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Bhiwandi (M Corp.), Bhiwandi taluka

Survey, CTS, gat or plot numbers

C.T.S. No. 434P

Boundaries

North
9M Wide DP Road
South
HP Petrol Pump
East
24M Wide DP Road
West
CTS No - 434 P

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectLele Infratech Private Limited Mandar Jayant Lele—
Chartered accountantChetan V Sheth—
Chartered accountantMukesh Soni And Associates—
EngineerAkshay Ravindra Thakare—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology