Skip to content

Ayre, Thane

5 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects4
Registrations4
Completion still due40 past their date
Median extension4 months50% of registrations extended
Regulatory cases0none on MahaRERA's lists
Ayre market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Projects in Ayre

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Swami EliteBluebird Infrastructure & DevelopersPR13300026021091 Oct 202631 Jul 202831 Jul 2028Not yet due0
HorizonImperia HomesPR13300026014547 Aug 202631 Dec 202731 Dec 2027Not yet due0
Sudama ChhatraShree Balaji ConstructionPR133000250236516 Feb 202631 Mar 202931 Jul 2029Extended 4 mo0
IreneSerenity SpacesP5170008027315 May 202531 Dec 202730 Apr 2028Extended 4 mo0

Most active promoters

  1. Bluebird Infrastructure & Developers1 project
  2. Imperia Homes1 project
  3. Serenity Spaces1 project
  4. Shree Balaji Construction1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology