Skip to content
Residential / Group Housing · 2 buildings · 16 unitsRERA PR1330002602109

Swami Elite

Deedo IDDP-THN-WNRA

It is due for completion in Jul 2028, with no extension on record; no MahaRERA orders on record; 0% of its units are booked.

Ayre, Thane 421201 · by Bluebird Infrastructure & Developers

DeliveryDue Jul 2028No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 16 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

It is due for completion in Jul 2028, with no extension on record

  • This projectRegistered 1 Oct 2026, completion promised 31 Jul 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1330002602109
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR13300026021091 Oct 202631 Jul 202831 Jul 2028Bluebird Infrastructure & DevelopersProject page
Documents26

1 document held by Deedo, 25 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardbbi pan.pdf · uploaded 25 May 2026Source
  • OthersCERSAI_Search_Report_SWAMI ELITE-BBI.pdf · uploaded 7 Jun 2026Source
  • GSTIN DocumentGST CERTIFICATE-BID.pdf · uploaded 7 Jun 2026Source
  • Othersbbi declaration .pdf · uploaded 8 Sep 2026Source
  • Othersdeclaration cum undertaking notarized bbi.pdf · uploaded 11 Sep 2026Source
  • Othersdeclaration bluebird infra updated as required.pdf · uploaded 28 Sep 2026Source

Legal

  • OthersIndex II Development rights.pdf · uploaded 6 May 2026Source
Show all 26 documentsShow fewer documents

Legal

  • OthersDevelopment rights.pdf · uploaded 25 May 2026Source
  • Declaration Form Baffidavit cum declaration bbi rera.pdf · uploaded 25 May 2026Source
  • OthersPower of Attorney.pdf · uploaded 7 Jun 2026Source
  • OthersNO Encumbrance - legal and financial - BBI.pdf · uploaded 7 Jun 2026Source
  • Declaration Form Bbb rera title updated.pdf · uploaded 2 Jul 2026Source
  • Othersbbi declaration .pdf · uploaded 8 Sep 2026Source
  • Othersdeclaration cum undertaking notarized bbi.pdf · uploaded 11 Sep 2026Source
  • Declaration Form Bdeclaration cum undertaking notarized bbi.pdf · uploaded 11 Sep 2026Source

Planning Authority

  • Document1759223705_KDMCC-25-25161_R0.html · uploaded 6 May 2026Source
  • DocumentpYwTBZ9wivSaat_Bara.pdf · uploaded 6 May 2026Source
  • DocumentpYwTBZ9wivSaat_Bara.pdf · uploaded 6 May 2026Source
  • DocumentCert_B_563510_446FPepmSign.pdf · uploaded 6 May 2026Source
  • Document1759223705_KDMCC-25-25161_R0.pdf_2_58DSE_Sign.pdfSign.pdf · uploaded 6 May 2026Source

Technical

  • DocumentPlan Copy.pdf · uploaded 6 May 2026Source
  • Documentannx a declaration cum understanding (bbi) rera.pdf · uploaded 25 May 2026Source
  • Othersform 1 architect certificate bbi rera.pdf · uploaded 25 May 2026Source
  • DocumentBuilding approval plan as per CC.pdf · uploaded 23 Jun 2026Source
  • DocumentCC plan with highlights.pdf · uploaded 30 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel C.T.S. NO. 3137 TO 3143

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—16 units in all
Address
Survey No. 2/1/10, Area 0-03-20, P.K. 0-00-10, , C.T.S. No. 3137 area about 16.50 Sq. Mtrs., C.T.S. No. 3138 area about 25.40 Sq. Mtrs., C.T.S. No. 3139 area about 25.40 Sq. Mtrs., C.T.S. No. 3140 area about 27 Sq. Mtrs., C.T.S. No. 3141 area about 27 Sq. Mtrs., C.T.S. No. 3142 area about 238 Sq. Mtrs., C.T.S. No. 3143 area about 10.60 Sq. Mtrs.PIN 421201
Village
Ayre, Kalyan taluka
Land area for this project
264 sq m (2,842 sq ft)
Permissible built-up area
845 sq m (9,092 sq ft)
Sanctioned built-up area
845 sq m (9,092 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

C.T.S. NO. 3137 TO 3143

Land as published on MahaRERA's project page

plot_no - city_survey_gut_no C.T.S.NO.3137 TO 3143 final_plot_no - sector_no - mauje AYRE road_street - society Thakur building

Boundaries

North
Chandrabhaga Building
South
Ananta Bhoir Chawl
East
Vijay Kunj Building
West
Naik Niwas Building

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units

16 units registered

— · 16 units
TypeCarpet areaUnits
——16

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPramod Shinde—
Chartered accountantHaresh Ahuja—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Ayre

All 7 projects in Ayre · Compare Swami Elite with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology