131 MahaRERA projects in Kolhapur are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 3 of 3.

ProjectLocalityPromisedRevisedDelivery
Veduta ResidencyIndo BuildconIchalkaranji (M Cl)Jun 2025Jun 20251 yr 5 mo late
Grand ResidencyDestiny Builders And DevelopersKolhapur (M Corp.)Jun 2025Jun 20251 yr 5 mo late
GrandstandRandive Builders and DevelopersKolhapur (M Corp.)Jun 2025Jun 20251 yr 5 mo late
Shree HeightsExcon Builders and DevelopersKolhapur (M Corp.)Jun 2025Jun 20251 yr 5 mo late
TustiRamsina Constructions Pvt. LtdKolhapur (M Corp.)Jun 2025Jun 20251 yr 5 mo late
NiwaraKulkarni Lohia DevelopersKolhapur (M Corp.)Aug 2025Aug 20251 yr 3 mo late
Jayashree ResidencyNilesh Shankar NikamKolhapur (M Corp.)Nov 2025Nov 20251 yr late
Gargi EleganceRohit DesaiKolhapur (M Corp.)Dec 2025Dec 202511 mo late
Sanjay Ghodawat Industrial ParkGhodawat Eduserve Limited Liability PartnershipMajaleDec 2025Dec 202511 mo late
Shri Narayan BhavanHanmant Dhondappa GuravIchalkaranji (M Cl)Dec 2025Dec 202511 mo late
Balaji HeightsBalaji AssociateKarvirDec 2025Dec 202511 mo late
City AvenueShriraam BuildersKolhapur (M Corp.)Dec 2025Dec 202511 mo late
Joshi Sabnis SankulCskcon Private LimitedGadhinglajDec 2025Dec 202511 mo late
Pratham ResidencyPratham DevelopersKolhapur (M Corp.)Dec 2025Dec 202511 mo late
Sai Basav SankulShrikant Pandurang VadgaonkarGadhinglajDec 2025Dec 202511 mo late
Sidhivinayak CornerPrasad Madhukar KhairnarHatkanangleDec 2025Dec 202511 mo late
Tawdes Govind ExcellencyCpl AssociatesKolhapur (M Corp.)Dec 2025Dec 202511 mo late
The Grand CasaSairaj Builders And DevelopersKolhapur (M Corp.)Dec 2025Dec 202511 mo late
Navkar HightsOssiya DevelopersIchalkaranji (M Cl)Jan 2026Jan 202610 mo late
Kwality Fortune SapphireFortune DevelopersYadravJan 2026Jan 202610 mo late
Shiv-ShrushtiManohar Baburao GaikwadGadhinglaj (M Cl)Mar 2026Jul 20268 mo late
Abhishek ResidencyBhaskar Ramgonda PatilGadhinglaj (M Cl)Mar 2026Jul 20268 mo late
AravaliBedekar Lifespaces LLPPachgaon (Ct)Mar 2026Jul 20268 mo late
Choundeshwari PlanetVijay Virupaksha GalgaleIchalkaranji (M Cl)Apr 2026Aug 20267 mo late
Shri Ganesh ResidencyTanaji Vithoba KokitkarGadhinglajApr 2026Aug 20267 mo late
Rdm Elite - KissanAbi BuildersKarvirMay 2026Sep 20266 mo late
Shravan SquareS R Builders And DevelopersKolhapur (M Corp.)May 2026Sep 20266 mo late
Dwarka Heights Phase IIJ.K. InfrastructureKolhapur (M Corp.)Jun 2026Oct 20265 mo late
Gm PrideGm Builders And DevelopersKarvirJun 2026Jun 20265 mo late
Pawanraj ResidencyShree Samarth InfrastructureKagal (M Cl)Jun 2026Oct 20265 mo late
Powar ComplexPrakash Tatoba PowarKagal (M Cl)Jun 2026Oct 20265 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology