Umbarde, Thane

10 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects2
Registrations2
Completion still due20 past their date
Median extension4 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists
Umbarde market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Projects in Umbarde

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Kalyan OrchidS K PropertiesPM133000260083817 Jun 202630 Jun 203130 Oct 2031Extended 4 mo0
Seasons AuraShree Muhurt DevelopersPM133000250142710 Nov 202531 Dec 203030 Apr 2031Extended 4 mo0

Most active promoters

  1. Shree Muhurt Developers1 project
  2. S K Properties1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology