4 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects20
Registrations23some projects hold several
Completion still due149 past their date
Median extension4 months35% of registrations extended
Regulatory cases3on 2 projects
7 in 10 registrations run late here
23 MahaRERA registrations in Mangaon
7 not yet due7 extended, not yet due9 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Mangaon
20 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Emerald A and BLodha Developers Limited | Due Dec 2028, extended 4 mo | — | 0% |
| Jasper C and DLodha Developers Limited | Due Dec 2028, extended 4 mo | — | 0% |
| Foresta ELodha Developers Limited | Due Aug 2028 | — | 0% |
| Vinayak PlatinaVinayak Construction | Due Apr 2027, extended 4 mo | — | 0% |
| Crown Dombivli 4Lodha Developers Limited | Due Jun 2028 | — | — |
| Crown Dombivli 3Lodha Developers Limited | Due Dec 2027, extended 4 mo | — | — |
| Crown Dombivli 2Lodha Developers Limited | Due Dec 2028 | — | — |
| Crown Dombivli 1Lodha Developers Limited | Due Dec 2028 | — | — |
| Kuber HeightsShreeji Infra Group | Due Apr 2027, extended 4 mo | — | 12% |
| JardinoMacrotech Developers Limited | Due Aug 2028 | — | — |
| LianaLodha Developers Limited | 1 mo late | — | 92% |
| Liana BMacrotech Developers Limited | 8 mo late | — | 92% |
| Foresta FMacrotech Developers Limited | 9 mo late | — | 92% |
| Liana AMacrotech Developers Limited | 8 mo late | — | 98% |
| Biroba DarshanJay Sadguru Biroba Maharaj Developers | Due Apr 2027, extended 4 mo | — | — |
| ForestaMacrotech Developers Limited | 6 mo late | — | 91% |
| La CentrumBhumi Homes | Due Apr 2032, extended 4 mo | — | 0% |
| Laxmi CastleArihant Enterprises | Due Dec 2028 | — | 0% |
| Advance LegacyRamesh Dungarshi Shah | 2 yrs 10 mo late | — | 42% |
| Foresta & FioraPalava Dwellers Private Limited | 3 yrs 2 mo late | — | — |
Nearby: other localities in Kalyan
Dombivli · 405 projectsKalyandombivali (M Corp.) · 206 projectsKalyan · 140 projectsChikanghar · 108 projectsTitwala · 89 projectsKalyan-Dombivali (M Corp.) · 85 projectsKhoni · 71 projectsKatemanevali · 55 projectsManda · 52 projectsTisgaon · 48 projectsGandhare · 44 projectsAdharwadi · 24 projects
Most active promoters
- Lodha Developers Limited8 projects
- Macrotech Developers Limited5 projects
- Arihant Enterprises1 project
- Bhumi Homes1 project
- Jay Sadguru Biroba Maharaj Developers1 project
- Palava Dwellers Private Limited1 project
- Ramesh Dungarshi Shah1 project
- Shreeji Infra Group1 project
- Vinayak Construction1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology