Damat, Raigarh
Deedo IDDL-RAI-DAMAT6 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects10
Registrations12some projects hold several
Completion still due102 past their date
Median extension4 months58% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
12 MahaRERA registrations in Damat
4 not yet due6 extended, not yet due2 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Damat
10 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Diamond HeightsAl Safa Developers | Due Dec 2030 | — | — |
| Mecca AvenueSrs Burooj Construction LLP | Due Dec 2031 | — | — |
| Baug-E-ZainabSrs Burooj Construction LLP | Due Jun 2028 | — | — |
| Sun CityRajnir Enterprises Private Limited | Due Dec 2026 | — | 92% |
Nearby: other localities in Karjat
Most active promoters
- Rajnir Enterprises Private Limited2 projects
- Srs Burooj Construction LLP2 projects
- Al-Hamd Developers1 project
- Al Safa Developers1 project
- Khalif Siraj Shaikh1 project
- Palak Developers1 project
- Shree Mahavir Builders And Developers1 project
- Zam Zam Developers1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology