RERA projects in Punawale
183 projects under 212 MahaRERA registrations, registered 2017–2026. 17% have a completion date extended beyond the one promised.
Locality
183RERA projects
212Registrationssome projects hold several
96Completion still due116 past their completion date
18 monthsMedian extension beyond promised date17% of registrations extended
1Regulatory caseson 1 project
45Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 50 |
| 2018 | 9 |
| 2019 | 19 |
| 2020 | 19 |
| 2021 | 18 |
| 2022 | 18 |
| 2023 | 20 |
| 2024 | 17 |
| 2025 | 19 |
| 2026 | 23 |
Projects in Punawale
183 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Nb Evo HighstreetYashada Holdings | PR1261012501027 | 1 Oct 2025 | 30 Dec 2032 | — | Not yet due | 0 |
| Sky LavishSujit Group | PR1260002500793 | 15 Sep 2025 | 31 May 2028 | — | Not yet due | 0 |
| Nb Evo PlazaYashada Holdings | PC1261012500615 | 20 Aug 2025 | 30 Jun 2030 | — | Not yet due | 0 |
| AriaAurigaa Realtors | P52100080612 | 19 Jun 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| 108 AsteraAum Ventures | P52100080292, PR1260002501838 | 19 May 2025 | 31 Dec 2031 | — | Not yet due | 0 |
| Nexus WestiaNexus Properties | P52100080184 | 6 May 2025 | 30 Jun 2027 | — | Not yet due | 0 |
| Namrata ManifestaNamrata Developers | P52100080124 | 29 Apr 2025 | 30 Dec 2029 | — | Not yet due | 0 |
| 24Life AltaaKshitej Realtors Through Its Proprietor Kaustubh S Talekar | P52100078972 | 24 Jan 2025 | 31 Oct 2028 | — | Not yet due | 0 |
| 41 Zillenia Phase 2Krisala Punawale LLP | P52100078925 | 21 Jan 2025 | 31 Aug 2027 | — | Not yet due | 0 |
| Anika Piccadilly Phase 3Arun Pitamber Sheth | P52100078875 | 17 Jan 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| West WorldLandmark Realty | P52100078839 | 15 Jan 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| AA PrivilegeJ N Realty And Homes | P52100078775 | 13 Jan 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Infinity EvanaTulip Infra | P52100078470 | 12 Dec 2024 | 30 Jun 2029 | — | Not yet due | 0 |
| Legacy MilestoneInfinity Associates | P52100077968 | 14 Nov 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| GloryAtul Dilip Dhavale | P52100077028 | 16 Jul 2024 | 30 Jun 2027 | — | Not yet due | 0 |
| Evernest EmpressaEvernest Infracity LLP | P52100076897 | 3 Jul 2024 | 31 May 2027 | — | Not yet due | 0 |
| Millennium SamriddhiMillennium Strategic Promoters LLP | P52100076784 | 28 Jun 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| F PremiumEssen Landmarks | P52100056429 | 31 May 2024 | 21 Mar 2029 | — | Not yet due | 0 |
| Akshara GrandeurGarve Developers and Builders | P52100056316 | 29 May 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Vcc ViaraShubham Properties And Promoters | P52100055989 | 6 May 2024 | 30 Apr 2027 | — | Not yet due | 0 |
| Surya Skies A And A1 WingSurya Developer | P52100055868 | 23 Apr 2024 | 30 Dec 2027 | — | Not yet due | 0 |
| Kohinoor Uptown AvenueMoonstone Realinfra Private Limited | P52100055120 | 4 Mar 2024 | 30 Dec 2029 | — | Not yet due | 0 |
| Nexus SkydaleNexus Infrastructure | P52100055009 | 26 Feb 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Rudraksh VantageGurudatta Developers | P52100054830 | 15 Feb 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Shantais Divine VastuMahalaxmi Developers | P52100054227 | 9 Jan 2024 | 31 Dec 2026 | — | Not yet due | 0 |
Other localities in Mulshi
Most active promoters
By projects registered here, as named on MahaRERA.
- Benchmarrk Realty LLP5 projects
- Arun Pitamber Sheth4 projects
- Sai Samarttha Properties4 projects
- Samarttha Prisha Properties4 projects
- Essen Land Marks, Esvee Dream Homes LLP3 projects
- Samarth Chintamani Properties3 projects
- Shiv Constructions3 projects
- Tulip Developers3 projects
- Vinayak Kishor Garve3 projects
- Vinod Premchand Chandwani3 projects
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology