41 Zillenia Phase 2

Certificate Signed

Punawale, Pune 411033 |Promoter: Krisala Punawale LLP

Residential / Group HousingRERAP52100078925
21 Jan 2025Registered with MahaRERA
31 Aug 2027Promised completion
31 Dec 2027Revised completionPushed back 4 months
1Building
72Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK, Landowner Units sale72 units in all
Address
26/2, Gaikwad Wasti Road, PunawalePIN 411033
Designated bank account
85
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.53026, 73.84986
41 Zillenia Phase 2 is at latitude 18.53026, longitude 73.84986.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
21 Jan 2025
Promised
31 Aug 2027
Revised
31 Dec 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210007892521 Jan 202531 Aug 202731 Dec 2027Krisala Punawale LLPProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Tower C1472

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 72 units booked (0%), as the promoter reported to MahaRERA

2BHK · 60 unitsLandowner Units sale · 12 units
TypeCarpet areaUnitsBooked
2BHK57.13 sq m · 615 sq ft600
Landowner Units sale57.13 sq m · 615 sq ft120

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 148 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardKRISALA PUNAWALE PAN.pdf · uploaded 28 Nov 2024Source
  • Other – FinanceCERSAI REPORT.pdf · uploaded 23 Dec 2024Source
  • Other – FinanceDECLARATION AS TO SATISFATION OF MORTGAGE.pdf · uploaded 26 Dec 2024Source
  • Other – FinanceLANDOWNER'S DECLARATION - LAND COST.pdf · uploaded 18 Jan 2025Source
  • OthersSelf Declaration cost change.pdf · uploaded 18 Jul 2025Source
  • OthersEncumbrance with respect to finance 2.pdf · uploaded 17 Dec 2025Source

Legal

  • Other – Legal0 50 DECLARATION.pdf · uploaded 28 Nov 2024Source
Show all 149 documentsShow fewer documents

Legal

  • Declaration Form BFORM B - PROMOTER.pdf · uploaded 28 Nov 2024Source
  • Legal Title reportTSR - 41 ZILLENIA PHASE 2.pdf · uploaded 8 Dec 2024Source

Migrated

  • 1 PAN CardKRISALA PUNAWALE PAN.pdf · uploaded 28 Nov 2024Source
  • 1 Copy of Layout Approval (in case of layout)1 - 28 LAYOUT_compressed.pdf · uploaded 28 Nov 2024Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 28 Nov 2024Source
  • 1 Declaration in FORM BFORM B - PROMOTER.pdf · uploaded 28 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 28 Nov 2024Source
  • 12 Building Plan Approval / NA Order for plotted development25 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • 2 Building Plan Approval / NA Order for plotted development2 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • 3 Building Plan Approval / NA Order for plotted development3 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • 4 Building Plan Approval / NA Order for plotted development4 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • 5 Building Plan Approval / NA Order for plotted development18 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • 6 Building Plan Approval / NA Order for plotted development19 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • 7 Building Plan Approval / NA Order for plotted development20 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • 8 Building Plan Approval / NA Order for plotted development21 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • 9 Building Plan Approval / NA Order for plotted development22 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • 10 Building Plan Approval / NA Order for plotted development23 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • 11 Building Plan Approval / NA Order for plotted development24 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • 1 Other – Legal0 50 DECLARATION.pdf · uploaded 28 Nov 2024Source
  • 1 Declaration about Commencement CertificateCC DECLARATION.pdf · uploaded 28 Nov 2024Source
  • 1 CERSAI detailsCERSAI REPORT.pdf · uploaded 28 Nov 2024Source
  • 1 Deviation Report with respect to Allotment letterALLOTMENT LETTER - DEVIATION.pdf · uploaded 28 Nov 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsSAGAR - DISCLOSURE.pdf · uploaded 28 Nov 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsOMPRAKASH - DISCLOSURE.pdf · uploaded 28 Nov 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsVISHAL SIR - DISCLOSURE.pdf · uploaded 28 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - ZILLENIA PHASE 2.pdf · uploaded 29 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 29 Nov 2024Source
  • 2 Other – TechnicalBOARD RESOLUTION.pdf · uploaded 29 Nov 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION - AFS.pdf · uploaded 29 Nov 2024Source
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 29 Nov 2024Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsAAKASH SIR - DISCLOSURE.pdf · uploaded 29 Nov 2024Source
  • 5 Disclosure of Interest in Other Real Estate OrganizationsANUP MORE - DISCLOSURE.pdf · uploaded 29 Nov 2024Source
  • 1 a Details of encumbrances concerned to FinanceLEGAL ENCUMBRANCE.pdf · uploaded 5 Dec 2024Source
  • 1 b Details of encumbrances concerned to LegalLEGAL ENCUMBRANCE.pdf · uploaded 5 Dec 2024Source
  • 1 Copy of the legal title reportTSR - 41 ZILLENIA PHASE 2.pdf · uploaded 8 Dec 2024Source
  • 3 Other – TechnicalDECLARATION AS TO SURVEY NUMBER.pdf · uploaded 8 Dec 2024Source
  • 4 Other – TechnicalCC VERIFICATION EMAIL.pdf · uploaded 19 Dec 2024Source
  • 2 a Details of encumbrances concerned to FinanceFINANCE ENCUMBRANCE.pdf · uploaded 20 Dec 2024Source
  • 2 b Details of encumbrances concerned to LegalFINANCE ENCUMBRANCE.pdf · uploaded 20 Dec 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDISCLOSURE SECURED UNSECURED LOAN.pdf · uploaded 20 Dec 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)FORMAT B.pdf · uploaded 21 Dec 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A - SEPARATE BANK ACCOUNT.pdf · uploaded 23 Dec 2024Source
  • 2 Other – FinanceCERSAI REPORT.pdf · uploaded 23 Dec 2024Source
  • 3 Other – FinanceDECLARATION AS TO SATISFATION OF MORTGAGE.pdf · uploaded 26 Dec 2024Source
  • 1 Building Plan Approval / NA Order for plotted development20 -28.pdf · uploaded 3 Jan 2025Source
  • 1 Other – TechnicalDECLARATION AS TO PARKING - ZILLENIA 2.pdf · uploaded 3 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 08012025.pdf · uploaded 8 Jan 2025Source
  • 1 Other – FinanceLANDOWNER'S DECLARATION - LAND COST.pdf · uploaded 18 Jan 2025Source
  • 1 a Details of encumbrances concerned to Financezillenia Encumbrances signed.pdf · uploaded 20 Feb 2025Source
  • 1 b Details of encumbrances concerned to Legalzillenia Encumbrances signed.pdf · uploaded 20 Feb 2025Source
  • 1 a Details of encumbrances concerned to Financezillenia Encumbrances signed.pdf · uploaded 20 Feb 2025Source
  • 1 b Details of encumbrances concerned to Legalzillenia Encumbrances signed.pdf · uploaded 20 Feb 2025Source
  • 1 Proforma of Allotment letterallotment letter zillenia phase 2 rizz with new encumbrances_compressed.pdf · uploaded 21 Feb 2025Source
  • 1 Proforma of Allotment letterallotment letter zillenia phase 2 rizz with new encumbrances_compressed.pdf · uploaded 21 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Zillenia Phase 2.pdf · uploaded 3 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 zillenia phase 2 (1).pdf · uploaded 3 May 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Zillenia phase 2.pdf · uploaded 3 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 zillenia phase 2.pdf · uploaded 6 May 2025Source
  • Form 1form 1 zillenia phase 2.pdf · uploaded 15 Jul 2025Source
  • Form 2form 2 zillenia phase 2 (1).pdf · uploaded 15 Jul 2025Source
  • Form 3Form 03 March 2025.pdf · uploaded 15 Jul 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Zillenia phase 2.pdf · uploaded 15 Jul 2025Source
  • Withdrawal Update Form 1Form 1_.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 1Form 1_.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 1Form 1_.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 1Form 1_.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 2form 2 zllenia phase 2_.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 2form 2 zllenia phase 2_.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 2form 2 zllenia phase 2_.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 2form 2 zllenia phase 2_.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 3FORM 3 ZILLENIA PHASE II 30062025_.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 3FORM 3 ZILLENIA PHASE II 30062025_.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 3FORM 3 ZILLENIA PHASE II 30062025_.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 3FORM 3 ZILLENIA PHASE II 16072025.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 1Form 1_.pdf · uploaded 31 Jul 2025Source
  • Withdrawal Update Form 2form 2 zllenia phase 2_.pdf · uploaded 31 Jul 2025Source
  • Withdrawal Update Form 3FORM 3 ZILLENIA PHASE II 16072025.pdf · uploaded 31 Jul 2025Source
  • Withdrawal Update Form 1Form 1_.pdf · uploaded 24 Sep 2025Source
  • Withdrawal Update Form 1Form 1_.pdf · uploaded 24 Sep 2025Source
  • Withdrawal Update Form 2form 2 zllenia phase 2_.pdf · uploaded 24 Sep 2025Source
  • Withdrawal Update Form 2form 2 zllenia phase 2_.pdf · uploaded 24 Sep 2025Source
  • Withdrawal Update Form 3FORM 3 ZILLENIA PHASE II 16072025.pdf · uploaded 24 Sep 2025Source
  • Withdrawal Update Form 3FORM 3 ZILLENIA PHASE II 16072025.pdf · uploaded 24 Sep 2025Source
  • Form 5 (FY 2024-2025)Form 5 ZILLENIA PHASE 2- 2024-2025.pdf · uploaded 10 Oct 2025Source
  • Withdrawal Update Form 1FORM 1 ZILLENIA PHASE 2 -30092025.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 27 Oct 2025Source
  • Form 2A (FY 2024-2025)form2A ZILLENIA2 2425.pdf · uploaded 29 Oct 2025Source
  • Withdrawal Update Form 1FORM 1 ZILLENIA PH II.pdf · uploaded 24 Feb 2026Source
  • Withdrawal Update Form 2Form 2 signed.pdf · uploaded 24 Feb 2026Source
  • Withdrawal Update Form 3Form 3 Final_.pdf · uploaded 24 Feb 2026Source
  • Withdrawal Update Form 1Form-1- 41 ZILLENIA PH II_signed.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 2Form 2 - 41 Zillenia Phase 2_ Signed.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 3Form 3 41 Zillenia Phase II_ Signed.pdf · uploaded 7 May 2026Source
  • Form 5 (FY 2025-2026)Form 5.pdf · uploaded 9 Jun 2026Source
  • Form 2A (FY 2025-2026)Form 2A-Zillenia Ph 2.pdf · uploaded 6 Jul 2026Source
  • Withdrawal Update Form 1Form 1 Zillenia Phase II_Signed.pdf · uploaded 16 Jul 2026Source
  • Withdrawal Update Form 2Form 2 41 Zillenia Ph II June 26_Final.pdf · uploaded 16 Jul 2026Source
  • Withdrawal Update Form 3Form 3 June 26_Final.pdf · uploaded 16 Jul 2026Source

Technical

  • Document25 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • Document24 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • Document23 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • Document22 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • Document21 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • Document20 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • Document19 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • Document18 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • Document4 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • Document3 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • Document2 - 28_compressed.pdf · uploaded 28 Nov 2024Source
  • Document1 - 28 LAYOUT_compressed.pdf · uploaded 28 Nov 2024Source
  • Other – TechnicalBOARD RESOLUTION.pdf · uploaded 29 Nov 2024Source
  • Other – TechnicalDECLARATION AS TO SURVEY NUMBER.pdf · uploaded 8 Dec 2024Source
  • Other – TechnicalCC VERIFICATION EMAIL.pdf · uploaded 19 Dec 2024Source
  • Document20 -28.pdf · uploaded 3 Jan 2025Source
  • Other – TechnicalDECLARATION AS TO PARKING - ZILLENIA 2.pdf · uploaded 3 Jan 2025Source
  • Document01-29 Layout_11zon.pdf · uploaded 17 Jul 2025Source
  • Document18-29 Tower C.pdf · uploaded 17 Jul 2025Source
  • Document19-29 Tower C.pdf · uploaded 17 Jul 2025Source
  • Document20-29 Tower C.pdf · uploaded 17 Jul 2025Source
  • Document21-29 Tower C.pdf · uploaded 17 Jul 2025Source
  • Document22-29 Tower C.pdf · uploaded 17 Jul 2025Source
  • Document23-29 Tower C.pdf · uploaded 17 Jul 2025Source
  • Document24-29 Tower C.pdf · uploaded 17 Jul 2025Source
  • Document25-29 Tower C.pdf · uploaded 17 Jul 2025Source
  • Document26-29 Tower C.pdf · uploaded 17 Jul 2025Source
  • Document01-29 Layout_.pdf · uploaded 9 Dec 2025Source
  • Document18-29 Tower C.pdf · uploaded 9 Dec 2025Source
  • Document19-29 Tower C.pdf · uploaded 9 Dec 2025Source
  • Document20-29 Tower C.pdf · uploaded 9 Dec 2025Source
  • Document21-29 Tower C.pdf · uploaded 9 Dec 2025Source
  • Document22-29 Tower C.pdf · uploaded 9 Dec 2025Source
  • Document23-29 Tower C.pdf · uploaded 9 Dec 2025Source
  • Document24-29 Tower C.pdf · uploaded 9 Dec 2025Source
  • Document25-29 Tower C.pdf · uploaded 9 Dec 2025Source
  • Document26-29 Tower C.pdf · uploaded 9 Dec 2025Source
  • OthersDeclaration of CC.pdf · uploaded 9 Dec 2025Source

Technical (Architect)

  • Documentform 1 zillenia phase 2.pdf · uploaded 6 May 2025Source
  • DocumentForm 1 Zillenia Phase II_Signed.pdf · uploaded 16 Jul 2026Source

Technical (Engineer)

  • Documentform 2 zillenia phase 2 (1).pdf · uploaded 3 May 2025Source
  • DocumentForm 2 41 Zillenia Ph II June 26_Final.pdf · uploaded 16 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Punawale, Mulshi taluka

Survey, CTS, gat or plot numbers

26/2

Boundaries

North
Sr No 26-2
South
Sr No 26-2
East
Sr No 26-11
West
Jambe Gaon Shiv

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectHrishikesh Kulkarni—
EngineerPankaj Kolte—
EngineerRanjit Dalavi—
EngineerSadhu Pawar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology