Completion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 0% of its units are booked.

Punawale, Pune 411033 · by Aurigaa Realtors

DeliveryExtended 4 moPromised Dec 2029 · now due Apr 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 359 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2030

  • This projectRegistered 19 Jun 2025, completion promised 31 Dec 2029, revised to 30 Apr 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100080612
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210008061219 Jun 202531 Dec 202930 Apr 2030Aurigaa RealtorsProject page
Documents137

1 document held by Deedo, 136 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 25 Apr 2025Source

Legal

  • Legal Title reportTITLE REPORT.pdf · uploaded 25 Apr 2025Source
  • Declaration Form BFORM B PROMOTER.pdf · uploaded 25 Apr 2025Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 25 Apr 2025Source
  • 1 Copy of the legal title reportTITLE REPORT.pdf · uploaded 25 Apr 2025Source
  • 1 a Details of encumbrances concerned to FinanceENCUMBERENCE DETAILS.pdf · uploaded 25 Apr 2025Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN.pdf · uploaded 25 Apr 2025Source
Show all 137 documentsShow fewer documents

Migrated

  • 1 Proforma of Allotment letterALLOTTMENT LETTER NEW.pdf · uploaded 25 Apr 2025Source
  • 1 Declaration in FORM BFORM B PROMOTER.pdf · uploaded 25 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 25 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 25 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 25 Apr 2025Source
  • 1 Commencement Certificates / NA Order for plotted development1 Commencement Certificates _ NA Order for plotted development-1-4.pdf · uploaded 25 Apr 2025Source
  • 17 Building Plan Approval / NA Order for plotted developmentPLAN 17.pdf · uploaded 25 Apr 2025Source
  • 16 Building Plan Approval / NA Order for plotted developmentPLAN 16.pdf · uploaded 25 Apr 2025Source
  • 15 Building Plan Approval / NA Order for plotted developmentPLAN 15.pdf · uploaded 25 Apr 2025Source
  • 14 Building Plan Approval / NA Order for plotted developmentPLAN 14.pdf · uploaded 25 Apr 2025Source
  • 13 Building Plan Approval / NA Order for plotted developmentPLAN 13.pdf · uploaded 25 Apr 2025Source
  • 12 Building Plan Approval / NA Order for plotted developmentPLAN 12.pdf · uploaded 25 Apr 2025Source
  • 11 Building Plan Approval / NA Order for plotted developmentPLAN 11.pdf · uploaded 25 Apr 2025Source
  • 10 Building Plan Approval / NA Order for plotted developmentPLAN 10.pdf · uploaded 25 Apr 2025Source
  • 8 Building Plan Approval / NA Order for plotted developmentPLAN 8.pdf · uploaded 25 Apr 2025Source
  • 7 Building Plan Approval / NA Order for plotted developmentPLAN 7.pdf · uploaded 25 Apr 2025Source
  • 6 Building Plan Approval / NA Order for plotted developmentPLAN 6.pdf · uploaded 25 Apr 2025Source
  • 5 Building Plan Approval / NA Order for plotted developmentPLAN 5.pdf · uploaded 25 Apr 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentPLAN 4.pdf · uploaded 25 Apr 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentPLAN 3.pdf · uploaded 25 Apr 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentPLAN 2.pdf · uploaded 25 Apr 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentPLAN 1.pdf · uploaded 25 Apr 2025Source
  • 9 Building Plan Approval / NA Order for plotted developmentPLAN 9.pdf · uploaded 25 Apr 2025Source
  • 1 Declaration about Commencement CertificateCC DECLARATION.pdf · uploaded 25 Apr 2025Source
  • 1 CERSAI detailsCERSAI DETAILS.pdf · uploaded 25 Apr 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A FINAL.pdf · uploaded 25 Apr 2025Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION REPORT.pdf · uploaded 25 Apr 2025Source
  • 1 b Details of encumbrances concerned to LegalENCUMBERENCE DETAILS.pdf · uploaded 25 Apr 2025Source
  • 1 Other – TechnicalANNEXURE A.pdf · uploaded 25 Apr 2025Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT OF AN AGREEMENT.pdf · uploaded 25 Apr 2025Source
  • 1 Proforma of Agreement for saleAGREEMENT TO SELL FINAL.pdf · uploaded 25 Apr 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST.pdf · uploaded 25 Apr 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)FORMAT B NEW.pdf · uploaded 25 Apr 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure-Aria_compressed.pdf · uploaded 25 Apr 2025Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 16 Aug 2025Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 16 Aug 2025Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 16 Aug 2025Source
  • Withdrawal Update Form 1Aria Form 1.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 2Aria Form 2.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 3Aria Form 3.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 1Form 1 Aria.pdf · uploaded 14 Jan 2026Source
  • Withdrawal Update Form 2Form 2 Aria.pdf · uploaded 14 Jan 2026Source
  • Withdrawal Update Form 3Form 3 Aria.pdf · uploaded 14 Jan 2026Source
  • Withdrawal Update Form 1Aria Form 1.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2Form 2 Aria.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3Form 3 Aria.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1Form 1 Aria.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Aria.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3Form 3 Aria.pdf · uploaded 20 Jul 2026Source
  • Form 2A (FY 2025-2026)Form 2 A Aria.pdf · uploaded 6 Aug 2026Source
  • Form 5 (FY 2025-2026)Form 5 both signed Aria.pdf · uploaded 14 Aug 2026Source
  • Withdrawal Update Form 1Q2 Form 1 Aria.pdf · uploaded 9 Oct 2026Source
  • Withdrawal Update Form 2Q2 Form 2 Aria.pdf · uploaded 9 Oct 2026Source
  • Withdrawal Update Form 3Form 3 Aria.pdf · uploaded 9 Oct 2026Source

Technical

  • DocumentLAYOUT PLAN.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 1.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 2.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 3.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 4.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 5.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 6.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 7.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 8.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 9.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 10.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 11.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 12.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 13.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 14.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 15.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 16.pdf · uploaded 25 Apr 2025Source
  • DocumentPLAN 17.pdf · uploaded 25 Apr 2025Source
  • Other – TechnicalANNEXURE A.pdf · uploaded 25 Apr 2025Source
  • DocumentLayout.pdf · uploaded 23 Aug 2025Source
  • DocumentC 2.pdf · uploaded 25 Aug 2025Source
  • DocumentC3.pdf · uploaded 25 Aug 2025Source
  • DocumentC4.pdf · uploaded 25 Aug 2025Source
  • DocumentC5.pdf · uploaded 25 Aug 2025Source
  • DocumentC6.pdf · uploaded 25 Aug 2025Source
  • DocumentC7.pdf · uploaded 25 Aug 2025Source
  • DocumentC8.pdf · uploaded 25 Aug 2025Source
  • DocumentC9.pdf · uploaded 25 Aug 2025Source
  • DocumentC10.pdf · uploaded 25 Aug 2025Source
  • DocumentC11.pdf · uploaded 25 Aug 2025Source
  • DocumentC12.pdf · uploaded 25 Aug 2025Source
  • DocumentC13.pdf · uploaded 25 Aug 2025Source
  • DocumentC14.pdf · uploaded 25 Aug 2025Source
  • DocumentC15.pdf · uploaded 25 Aug 2025Source
  • DocumentC16.pdf · uploaded 25 Aug 2025Source
  • DocumentC17.pdf · uploaded 25 Aug 2025Source
  • DocumentC18.pdf · uploaded 25 Aug 2025Source
  • DocumentPlan 1.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 2.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 3.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 4.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 5.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 6.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 7.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 8.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 9.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 10.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 11.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 12.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 13.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 14.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 15.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 16.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 17.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 18.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 1.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 2.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 3.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 4.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 5.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 6.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 7.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 8.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 9.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 10.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 11.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 12.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 13.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 14.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 15.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 16.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 17.pdf · uploaded 3 Apr 2026Source
  • DocumentPlan 18.pdf · uploaded 3 Apr 2026Source

Technical (Architect)

  • DocumentQ2 Form 1 Aria.pdf · uploaded 6 Oct 2026Source

Technical (Engineer)

  • DocumentQ2 Form 2 Aria.pdf · uploaded 6 Oct 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 10/1C (PT)+10/1D/2 (PT), 10/2 (PT)

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Shop, 2BHK, 3BHK359 units in all
Address
Survey No. 10 (Pt), Hissa No. 10/1a+10/1b, 10/1c (Pt)+10/1d/2 (Pt), 10/2 (Pt), Plot No. A, Punawale, PunawalePIN 411033
Village
Punawale, Mulshi taluka
Land area for this project
10,537 sq m (1,13,421 sq ft)
Permissible built-up area
41,778 sq m (4,49,695 sq ft)
Sanctioned built-up area
41,768 sq m (4,49,585 sq ft)
Recreational open space
1,054 sq m (11,347 sq ft)
Designated bank account
220
Developed in phases
Yes

Survey, CTS, gat or plot numbers

10/1C (PT)+10/1D/2 (PT)10/2 (PT)HISSA NO. 10/1A+10/1BSURVEY NO. 10 (PT)

Land as published on MahaRERA's project page

SURVEY NO. 10 (PT), HISSA NO. 10/1A+10/1B, 10/1C (PT)+10/1D/2 (PT), 10/2 (PT), PLOT NO. A

Boundaries

North
SURVEY NO 10 Part
South
18 Mtr Dp Road
East
Project Of Aurigaa Realtors
West
Project Of Paras Multispace LLP

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking359 units

0 of 359 units booked (0%), as the promoter reported to MahaRERA

1BHK · 132 unitsShop · 2 units2BHK · 221 units3BHK · 4 units
BuildingTypeCarpet areaUnitsBooked
A Building1BHK43.33 sq m · 466 sq ft20
A Building1BHK43.68 sq m · 470 sq ft10
A Building1BHK44.93 sq m · 484 sq ft10
A Building1BHK46.35 sq m · 499 sq ft190
A Building1BHK46.36 sq m · 499 sq ft300
A Building1BHK46.37 sq m · 499 sq ft130
A Building1BHK47.39 sq m · 510 sq ft10
A Building1BHK47.63 sq m · 513 sq ft160
Show all 40 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A Building1BHK47.92 sq m · 516 sq ft160
A Building1BHK48.1 sq m · 518 sq ft330
A BuildingShop121.27 sq m · 1,305 sq ft10
A BuildingShop175.48 sq m · 1,889 sq ft10
B Building2BHK51.98 sq m · 560 sq ft20
B Building2BHK52.1 sq m · 561 sq ft30
B Building2BHK52.13 sq m · 561 sq ft10
B Building2BHK52.16 sq m · 561 sq ft30
B Building2BHK52.17 sq m · 562 sq ft10
B Building2BHK52.25 sq m · 562 sq ft20
B Building2BHK59.96 sq m · 645 sq ft150
B Building2BHK59.98 sq m · 646 sq ft150
B Building2BHK60.1 sq m · 647 sq ft820
B Building2BHK60.11 sq m · 647 sq ft150
B Building2BHK60.16 sq m · 648 sq ft150
B Building2BHK60.2 sq m · 648 sq ft150
B Building2BHK60.27 sq m · 649 sq ft150
B Building2BHK86.34 sq m · 929 sq ft40
C Building2BHK59.66 sq m · 642 sq ft20
C Building2BHK59.8 sq m · 644 sq ft30
C Building2BHK59.85 sq m · 644 sq ft30
C Building2BHK59.98 sq m · 646 sq ft20
C Building2BHK60.05 sq m · 646 sq ft20
C Building2BHK60.09 sq m · 647 sq ft30
C Building2BHK60.1 sq m · 647 sq ft30
C Building2BHK60.15 sq m · 647 sq ft30
C Building2BHK60.19 sq m · 648 sq ft30
C Building2BHK60.22 sq m · 648 sq ft30
C Building2BHK60.31 sq m · 649 sq ft60
D Building3BHK88.56 sq m · 953 sq ft20
D Building3BHK88.57 sq m · 953 sq ft10
D Building3BHK88.66 sq m · 954 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectManoj Tatooskar—
Chartered accountantAzam Mulani And Associates—
EngineerRohinee Badgujar—
EngineerShriram Lomate—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology