1 project under 1 MahaRERA registration, registered 2019–2019. 100% have a completion date extended beyond the one promised.

1RERA projects
1Registrations
0Completion still due1 past their completion date
9 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20191

Projects in Malewadi

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Aangan Phase IIGalaxy AssociatesP5210001991513 Mar 201930 Dec 202230 Sep 2023Extended 9 mo0

Other localities in Mawal

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Galaxy Associates1 project