Aangan Phase II
Deedo IDDP-PUN-NXGWMahaRERA shows it completed, after its date was pushed back 9 months; no MahaRERA orders on record; 90% of its units are booked.
Malewadi, Pune 410507 · by Galaxy Associates
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 9 months
- This projectRegistered 13 Mar 2019, completion promised 30 Dec 2022, revised to 30 Sep 2023.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
12 buildings
Open a building to see every flat, floor by floor.
- 1bSize not on record100% booked
- 2bSize not on record100% booked
- 3bSize not on record100% booked
- 4bSize not on record100% booked
- 6bSize not on record100% booked
- 7bSize not on record100% booked
- B2Size not on record100% booked
- B3Size not on record100% booked
- B4Size not on record100% booked
- Building (P52100019915)Size not on record88% booked
- C9 floors · 84 units85% booked
- D9 floors · 42 units100% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100019915
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100019915 | 13 Mar 2019 | 30 Dec 2022 | 30 Sep 2023 | Galaxy Associates | Project page |
Documents44
3 documents held by Deedo, 41 filings listed on MahaRERA's project page
Show all 44 documentsShow fewer documents
Migrated
- 1 PAN CardPan.pdf · uploaded 27 Feb 2019Source
- 1 Copy of the legal title reporttitle report.PDF · uploaded 27 Feb 2019Source
- 1 Details of encumbrancesNew encumrance certificate.pdf · uploaded 27 Feb 2019Source
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 27 Feb 2019Source
- 1 Building Plan Approval (IOD)IOD.PDF · uploaded 27 Feb 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentComencement certificate.PDF · uploaded 27 Feb 2019Source
- 1 Declaration in FORM BForm B.pdf · uploaded 28 Feb 2019Source
- 1 Certificates of CA (Form 3)Certificate of CA.PDF · uploaded 28 Feb 2019Source
- 1 Proforma of Allotment letterFinal RERA draft.pdf · uploaded 6 Mar 2019Source
- 1 OtherForm 2A.pdf · uploaded 14 Feb 2020Source
- 2 Copy of the legal title reportTitle report.PDF · uploaded 17 Jun 2020Source
- 2 Proforma of Allotment letterdraft agreement.pdf · uploaded 17 Jun 2020Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold unsold.PDF · uploaded 1 Jun 2021Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPart completion D wing.PDF · uploaded 1 Jun 2021Source
- 2 Building Plan Approval (IOD)1363-145Rev-B IOD Layout Plan.pdf · uploaded 4 Aug 2021Source
- 2 Commencement Certificates / NA Order for plotted development210723 - CC-compressed_compressed (1).pdf · uploaded 4 Aug 2021Source
- 1 Declaration about Commencement CertificateFormat D - For RERA Date Extend_001.pdf · uploaded 23 Dec 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A (2).pdf · uploaded 23 Dec 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)CA FORM 5 GA 2019-20.pdf · uploaded 23 Dec 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)CA FORM 5 GA 2020-21.pdf · uploaded 23 Dec 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)CA FORM 5 GA 2021-22.pdf · uploaded 23 Dec 2022Source
- 2 Disclosure of sold/ booked inventoryGalaxy C D Wing Flat Sold - Un Sold List 24-12-2022_001_compressed.pdf · uploaded 24 Dec 2022Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Eng Certificate Form 2A_001 (1).pdf · uploaded 18 Feb 2023Source
- 3 Disclosure of sold/ booked inventorysold unsold.pdf · uploaded 18 Feb 2023Source
- 4 Disclosure of sold/ booked inventorySOLD UNSOLD CIRCULAR 29 - 20-02-2023_001_compressed.pdf · uploaded 20 Feb 2023Source
- 2 Certificates of CA (Form 3)Form 3.pdf · uploaded 23 Feb 2023Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPart Completion Certificate (D-Wing).pdf · uploaded 28 Feb 2023Source
- 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPart Completion Certificate for C Bldg (1).pdf · uploaded 28 Feb 2023Source
- 5 Architect’s Certificate on Completion of Project (Form 4)form 4 c wing.pdf · uploaded 1 Mar 2023Source
- 6 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 1 Mar 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Aangan Phase II Form 2.pdf · uploaded 2 Mar 2023Source
- 5 Disclosure of sold/ booked inventoryAangan Ph II Sold Unsold 29-9-2023_001 (1)_compressed.pdf · uploaded 29 Sep 2023View
Technical
Technical (Engineer)
- DocumentAangan Phase II Form 2.pdf · uploaded 2 Mar 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 3/3/2 p
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK126 units in all
- Address
- 3/3/2 p, 3, MawalPIN 410507
- Village
- Malewadi, Mawal taluka
- Location
- 18.52043, 73.85674
- Land area for this project
- 2,746 sq m (29,555 sq ft)
- Permissible built-up area
- 10,021 sq m (1,07,865 sq ft)
- Sanctioned built-up area
- 10,021 sq m (1,07,865 sq ft)
- Recreational open space
- 718 sq m (7,730 sq ft)
- Designated bank account
- 109
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
3/3/2 p
Boundaries
- North
- Sr No 4
- South
- Sr No 2
- East
- Sr No 13 -2 and 14
- West
- 36 M PWD road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking126 units
113 of 126 units booked (90%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| C | 1BHK | 41.25 sq m · 444 sq ft | 28 | 28 |
| C | 1BHK | 41.39 sq m · 446 sq ft | 28 | 25 |
| C | 2BHK | 55.6 sq m · 598 sq ft | 12 | 7 |
| C | 2BHK | 55.78 sq m · 600 sq ft | 16 | 11 |
| D | 1BHK | 40.03 sq m · 431 sq ft | 3 | 3 |
| D | 1BHK | 40.1 sq m · 432 sq ft | 3 | 3 |
| D | 1BHK | 40.97 sq m · 441 sq ft | 3 | 3 |
| D | 1BHK | 41.3 sq m · 445 sq ft | 5 | 5 |
Show all 15 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| D | 1BHK | 42.2 sq m · 454 sq ft | 1 | 1 |
| D | 1BHK | 44.43 sq m · 478 sq ft | 3 | 3 |
| D | 1BHK | 44.66 sq m · 481 sq ft | 4 | 4 |
| D | 1BHK | 44.7 sq m · 481 sq ft | 3 | 3 |
| D | 1BHK | 44.91 sq m · 483 sq ft | 1 | 1 |
| D | 1BHK | 44.93 sq m · 484 sq ft | 3 | 3 |
| D | 2BHK | 59.3 sq m · 638 sq ft | 13 | 13 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Hrishikesh V. Kulkarni | — |
Source: MahaRERA project page. Contact details are not shown.