C · Aangan Phase II
Malewadi · RERA P52100019915
IDBLD_0313379 floorsExtended 9 mo
9Sanctioned habitable floorsregistration certificate
30 Sep 2023Revised completionpromised 30 Dec 2022
71 of 84Units bookedMahaRERA project page
Floors
9 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100019915 · registered 13 Mar 2019
- Promised completion
- 30 Dec 2022
- Revised completion
- 30 Sep 2023
- Sanctioned habitable floors
- 9
- ProjectId
- 23,966
- ProjectName
- Aangan Phase II
- TotalUnitCount
- 0
- ProjectBuildingId
- 54,691
- BuildingNameNumber
- C
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100019915
- ProjectBuildingWingsId
- 54,691
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- C
- NoOfBuildingWingFloorProposed
- 9
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 9
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 41.3 m² (444 sq.ft) | 28 | 28 |
| 1BHK | 41.4 m² (446 sq.ft) | 28 | 25 |
| 2BHK | 55.6 m² (598 sq.ft) | 12 | 7 |
| 2BHK | 55.8 m² (600 sq.ft) | 16 | 11 |
| Total | 84 | 71 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology