Khadakale (Ct), Pune

2 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects5
Registrations6some projects hold several
Completion still due15 past their date
Median extension14 months17% of registrations extended
Regulatory cases0none on MahaRERA's lists

Projects in Khadakale (Ct)

5 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
AquagemNamrata RealtyP5210004639222 Jun 202230 Jun 202530 Jun 2025Promised date passed0
Cosmos ResidencyCosmos BuildconP5210001860822 Nov 201830 Dec 202530 Dec 2025Promised date passed0
Weekender Country SongsNamrata RealtyP5210001622324 Apr 20181 Dec 20211 Dec 2021Promised date passed0
Green CastleApurva DevelopersP5210001316115 Sep 201730 Dec 202415 Mar 2026Extended 15 mo0
Gagan NulifeGagan LifespaceP52100002941, P521000096424 Aug 201730 Jun 202730 Jun 2027Not yet due0

Most active promoters

  1. Namrata Realty2 projects
  2. Apurva Developers1 project
  3. Cosmos Buildcon1 project
  4. Gagan Lifespace1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology