Aquagem
Certificate SignedKhadakale (Ct), Pune 410405 |Promoter: Namrata Realty
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- 55 PART 56 61/11 61/16 62/7 62/8 68/1 68/2 69 70, kamshet Nane Road, Mauli NagarPIN 410405
- Designated bank account
- 171
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Jun 2025
The latest completion date on record passed 1 year and 4 months ago.
- Registered
- 22 Jun 2022
- Promised
- 30 Jun 2025
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100046392 | 22 Jun 2022 | 30 Jun 2025 | 30 Jun 2025 | Namrata Realty | Project page |
Documents
1 document held by Deedo, 63 filings listed on MahaRERA's project page
Finance
- PAN Card1 PAN Card.pdf · uploaded 17 Jun 2022Source
Legal
- Legal Title report1 Copy of the legal title report.pdf · uploaded 17 Jun 2022Source
- Declaration Form B1 Declaration in FORM B.pdf · uploaded 17 Jun 2022Source
- Legal Title reportLegal Title Report _compressed.pdf · uploaded 17 Jun 2022Source
- Legal Title reportCountry song suppliment_2022.pdf · uploaded 17 Jun 2022Source
- Legal Title reportcorrigendum to tiltle report Adv Kiran kotadia.pdf · uploaded 17 Jun 2022Source
- Legal Title reportSuppliment_2021.pdf · uploaded 17 Jun 2022Source
Show all 64 documentsShow fewer documents
Migrated
- 1 PAN Card1 PAN Card.pdf · uploaded 17 Jun 2022Source
- 1 Copy of the legal title report1 Copy of the legal title report.pdf · uploaded 17 Jun 2022Source
- 2 Copy of the legal title reportLegal Title Report _compressed.pdf · uploaded 17 Jun 2022Source
- 3 Copy of the legal title reportCountry song suppliment_2022.pdf · uploaded 17 Jun 2022Source
- 4 Copy of the legal title reportcorrigendum to tiltle report Adv Kiran kotadia.pdf · uploaded 17 Jun 2022Source
- 5 Copy of the legal title reportSuppliment_2021.pdf · uploaded 17 Jun 2022Source
- 1 Details of encumbrances1 Details of encumbrances.pdf · uploaded 17 Jun 2022Source
- 1 Copy of Layout Approval (in case of layout)1 Copy of Layout Approval (in case of layout).pdf · uploaded 17 Jun 2022Source
- 1 Building Plan Approval / NA Order for plotted development1 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 17 Jun 2022Source
- 1 Commencement Certificates / NA Order for plotted development1 Commencement Certificates _ NA Order for plotted development.pdf · uploaded 17 Jun 2022Source
- 1 Declaration about Commencement Certificate1 Declaration about Commencement Certificate.pdf · uploaded 17 Jun 2022Source
- 1 Declaration in FORM B1 Declaration in FORM B.pdf · uploaded 17 Jun 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 17 Jun 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 17 Jun 2022Source
- 1 CERSAI details1 CERSAI details.pdf · uploaded 17 Jun 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf · uploaded 17 Jun 2022Source
- 1 Proforma of Allotment letter1 Proforma of the allotment letter and agreement for sale.pdf · uploaded 17 Jun 2022Source
- 2 Proforma of Allotment letter2 Proforma of the allotment letter and agreement for sale.pdf · uploaded 17 Jun 2022Source
- 2 Copy of Layout Approval (in case of layout)Country Song Revised Sanction_Plan 1.pdf · uploaded 11 Jan 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentCountry Song Revised Sanction_Plan 1.pdf · uploaded 11 Jan 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentCountry Song Revised Sanction_Plan 2.pdf · uploaded 11 Jan 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentCountry Song_Commencement Certificate_09112023.pdf · uploaded 11 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Aquagem CA Certificate_Dec 2023_organized.pdf · uploaded 7 Feb 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Aquagem_Engg Certificate_DEc 2023.pdf · uploaded 20 Feb 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Aquagem Form 2A_MArch 2023.pdf · uploaded 5 Apr 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Aquagem Form 2A_MArch 2024.pdf · uploaded 5 Apr 2024Source
- 1 Other – TechnicalAquagem_ANNEXURE A_Declaration cum undertaking.pdf · uploaded 5 Apr 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Aquagem_RERA Form 1_March 2024.pdf · uploaded 10 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5_Aquagem_FY 2022_23_Signed.pdf · uploaded 19 Apr 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Aquagem_Engg Certificate_MArch 2024.pdf · uploaded 24 Apr 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Aquagem_CA Certificate_MArch 2024.pdf · uploaded 24 Apr 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Aquagem_Form1_June 2024_Signed.pdf · uploaded 5 Jul 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Namrata Realty_Form 2_Signed_30062024.pdf · uploaded 22 Jul 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Namrata Realty_Form 3_Signed_30062024.pdf · uploaded 22 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Aquagem_Form1_Signed_30092024.pdf · uploaded 18 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Aquagem_Form3_Signed_30092024.pdf · uploaded 18 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Aquagem_Form 2_Signed_30092024.pdf · uploaded 18 Oct 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentfinal Commencement cum completion certificate_compressed.pdf · uploaded 5 Dec 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentfinal Sanction Plan_compressed.pdf · uploaded 5 Dec 2024Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentfinal Commencement cum completion certificate_compressed.pdf · uploaded 5 Dec 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5_Namrata Realty.pdf · uploaded 5 Dec 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentfinal Sanction Plan_compressed.pdf · uploaded 10 Dec 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Aquagem _Form 4_07122024.pdf · uploaded 20 Dec 2024Source
- 2 Architect’s Certificate on Completion of Project (Form 4)Aquagem _Form 4_07122024.pdf · uploaded 25 Dec 2024Source
- 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentAquagem_Declaration regarding final sanction and request for approval of Form 4.pdf · uploaded 25 Dec 2024Source
Technical
- Document1 Copy of Layout Approval (in case of layout).pdf · uploaded 17 Jun 2022Source
- Document1 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 17 Jun 2022Source
- DocumentCountry Song Revised Sanction_Plan 1.pdf · uploaded 11 Jan 2024Source
- DocumentCountry Song Revised Sanction_Plan 1.pdf · uploaded 11 Jan 2024Source
- DocumentCountry Song Revised Sanction_Plan 2.pdf · uploaded 11 Jan 2024Source
- Other – TechnicalAquagem_ANNEXURE A_Declaration cum undertaking.pdf · uploaded 5 Apr 2024Source
- Documentfinal Sanction Plan_compressed.pdf · uploaded 10 Dec 2024Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Khadakale (CT), Mawal taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- 61 part and 62 part
- South
- HP Pipe Line
- East
- Nala
- West
- Amenity Space 1 and 2
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Subha Architects | — |
| Chartered accountant | SSAP & Associates LLP | — |
| Engineer | Nikhil Patil | — |
Source: MahaRERA project page. Contact details are not shown.