Mahim, Palghar
Deedo IDDL-PAL-MAHIM9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects115
Registrations127some projects hold several
Completion still due4681 past their date
Median extension12 months53% of registrations extended
Regulatory cases6on 2 projects
9 in 10 registrations run late here
127 MahaRERA registrations in Mahim
13 not yet due33 extended, not yet due81 past even the latest date
Extended registrations moved their completion date by a median of 12 months.
Projects in Mahim
115 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Matru DarshanVikram Palabhai Chhuchhar | 1 yr 11 mo late | — | — |
| Matru DeepKuver Jagmal Khodbhaya | 8 mo late | — | — |
| Paramount Enclave Building No 6Kavita Realty | 11 mo late | — | — |
| AmbrosiaPawan Abhimanyu Singh, Pawan Abhimanyu Singh | Due May 2029, extended 4 mo | — | 11% |
| Ambrosia 13Thdc Nagri LLP | Due Apr 2028, extended 4 mo | — | 64% |
| Royal Plaza 1Royal Builder And Developers | Due Dec 2026, extended 3 yrs | — | — |
| Sakina Residencyvision developers | Due Oct 2027, extended 4 mo | — | 13% |
| Paramount Enclave Phase -1Kavita Realty Housing LLP | Due Nov 2026, extended 2 yrs | — | 45% |
| Srushti Developers Build No 7Srushti Developers | Due Apr 2027, extended 4 mo | — | 6% |
| Fia Construction Company A/C Fia EnclaveNimish Laxmichand Pasad | Completed | — | — |
| Fia Construction Company A/C Fia EnigmaNimish Laxmichand Pasad | Completed | — | 50% |
| Paramount Enclave Phase 02Gajanan Builders & Developers | Due Apr 2027, extended 4 mo | — | 44% |
| Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-CBrajbhoomi Developers | Due Oct 2027, extended 4 mo | — | 30% |
| Paramount Enclave Phase 02Om Sai Construction | Due Dec 2027 | — | 31% |
| Akruti Prime SquareAshish Anil Patil | Due Dec 2026, extended 3 yrs 6 mo | — | 20% |
| Nitya DarpanShree Riddhi Siddhi Construction | Completed | — | — |
| Paramount Enclave Phase - 2Taranchal Infraprojects Private Limited | Due Mar 2028 | — | 15% |
| Paramount Enclave Building No 2 Type D A WingSkyline Developers | Due Dec 2027, extended 4 yrs 6 mo | — | 84% |
| Sai Aashirwad ComplexAashirwad Developer | Due Apr 2027, extended 4 mo | — | 27% |
| Virat DarshanVirat Infra | 4 yrs 5 mo late | — | 16% |
| Parashakti ApartmentHiralal Arjunlal Chaudhary | Completed, extended 3 yrs 1 mo | — | 7% |
| Paramount Enclave Phase 2Kavita Realty | 4 yrs 5 mo late | — | 60% |
| Adinath EmpireGhanshyam Akhileshwar Roy | 2 yrs 5 mo late | — | 1% |
| Adinath GalaxyAdinath Developers | Completed | — | — |
| Adinath GloryGhanshyam Akhileshwar Roy | Completed | — | — |
Nearby: other villages in Palghar
Most active promoters
- Nimish Laxmichand Pasad7 projects
- Fia Developers Pvt. Ltd5 projects
- Amit Harshavadan Agaskar4 projects
- Ghanshyam Akhileshwar Roy2 projects
- Housing Development And Infrastructure Ltd2 projects
- Kavita Realty2 projects
- Pawan Abhimanyu Singh2 projects
- Shree Riddhi Siddhi Construction2 projects
- Srushti Developers2 projects
- Vikram Palabhai Chhuchhar2 projects
Mahim, in questions
How many projects in Mahim run late?
9 in 10 MahaRERA registrations (114 of 127): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Mahim by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology