Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 6% of its units are booked.

Mahim, Palghar 401404 · by Srushti Developers

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales6% booked5 of 86 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 3 Nov 2021, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000031683
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P990000316833 Nov 202131 Dec 202630 Apr 2027Srushti DevelopersProject page
Documents76

1 document held by Deedo, 75 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardSRUSHTI DEVELOPERS PAN.pdf · uploaded 14 Aug 2021Source

Legal

  • OtherBLDG NO - 7 RERA CERTIFICATE.pdf · uploaded 14 Aug 2021Source
  • Declaration Form BPROMOTER BUILDING NO -7_compressed.pdf · uploaded 14 Aug 2021Source
  • Otherformat D bldg no 7 27-Oct-2021 11-43-16.pdf · uploaded 28 Oct 2021Source
  • Legal Title reportnew title report 2021 20-Oct-2021 13-22-13_compressed (1).pdf · uploaded 28 Oct 2021Source

Migrated

  • 1 PAN CardSRUSHTI DEVELOPERS PAN.pdf · uploaded 14 Aug 2021Source
  • 1 Details of encumbrancesDeclaration - No Encumbarances.pdf · uploaded 14 Aug 2021Source
Show all 76 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)layout plan.pdf · uploaded 14 Aug 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentbldg7 sheet 6_compressed.pdf · uploaded 14 Aug 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentbldg 7 sheet 7_compressed.pdf · uploaded 14 Aug 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificates _ NA Order for plotted development.pdf · uploaded 14 Aug 2021Source
  • 1 Declaration about Commencement CertificateCommencement Certificates _ NA Order for plotted development.pdf · uploaded 14 Aug 2021Source
  • 1 Declaration in FORM BPROMOTER BUILDING NO -7_compressed.pdf · uploaded 14 Aug 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)BLDG NO - 7 ARCHITECT CERTIFICATE_compressed.pdf · uploaded 14 Aug 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)BLDG NO - 7 ENGINEERS CERTIFICATE_compressed.pdf · uploaded 14 Aug 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)ca Srushti_Bldg7.pdf · uploaded 14 Aug 2021Source
  • 1 Proforma of Allotment letterDECLARATION.pdf · uploaded 14 Aug 2021Source
  • 1 Status of ConveyanceCO - PROMOTER HIRALAL BUILDING NO - 7_compressed.pdf · uploaded 14 Aug 2021Source
  • 2 Status of ConveyanceCO - PROMOTER NARESH BUILDING NO - 7_compressed.pdf · uploaded 14 Aug 2021Source
  • 3 Status of ConveyanceCO - PROMOTER NATHULAL BUILDING NO - 7_compressed.pdf · uploaded 14 Aug 2021Source
  • 4 Status of ConveyanceCO - PROMOTER PREMJI BUILDING NO - 7_compressed.pdf · uploaded 14 Aug 2021Source
  • 1 OtherBLDG NO - 7 RERA CERTIFICATE.pdf · uploaded 14 Aug 2021Source
  • 1 Copy of the legal title reportnew title report 2021 20-Oct-2021 13-22-13_compressed (1).pdf · uploaded 28 Oct 2021Source
  • 2 Otherformat D bldg no 7 27-Oct-2021 11-43-16.pdf · uploaded 28 Oct 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1_compressed.pdf · uploaded 2 Mar 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2_compressed.pdf · uploaded 2 Mar 2024Source
  • 1 Disclosure of sold/ booked inventorysold unsold rajendra srushti bldg no-7.pdf · uploaded 2 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form-5 fy21-22.pdf · uploaded 2 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form-5 fy 22-23 Rajendra srushti bldg no 7.pdf · uploaded 16 Apr 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 rajendra srushti bldg no-7.pdf · uploaded 24 Apr 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 rajendra srushti bldg no-7.pdf · uploaded 24 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 31032024.pdf · uploaded 13 Dec 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 30062024.pdf · uploaded 13 Dec 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 31032024.pdf · uploaded 13 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 30060204.pdf · uploaded 13 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 March.pdf · uploaded 19 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 June_compressed.pdf · uploaded 19 Dec 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)fORM-1 bUIL;DING nO-7.pdf · uploaded 20 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)fORM-3 bUILDING nO-7.pdf · uploaded 20 Dec 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)fORM-2 bUILDING nO-7.pdf · uploaded 20 Dec 2024Source
  • 1 Disclosure of sold/ booked inventorySU AS ON MARCH 2024.pdf · uploaded 28 Dec 2024Source
  • 2 Disclosure of sold/ booked inventorySU AS ON JUNE 2024.pdf · uploaded 28 Dec 2024Source
  • 3 Disclosure of sold/ booked inventorySU AS ON SEP 2024.pdf · uploaded 28 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form-5 rajendra srushti building no7.pdf · uploaded 9 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 19 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_compressed (1).pdf · uploaded 19 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 19 Mar 2025Source
  • 1 Disclosure of sold/ booked inventorySrushti Developer Building No 7.pdf · uploaded 19 Mar 2025Source
  • Form 1Form-1.pdf · uploaded 25 Jun 2025Source
  • Form 2Form-2.pdf · uploaded 25 Jun 2025Source
  • Form 3Form-3.pdf · uploaded 25 Jun 2025Source
  • Disclosure of Sold and Booked InventorySold Booked Inventory.pdf · uploaded 25 Jun 2025Source
  • Withdrawal Update Form 1Form-1.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 2Form-2.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 3Form-3.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 1Form-1 Dec 2025.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 2Form-2 Dec 2025.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 3Form-3 Dec 2025.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 1Form-1 march 2026 (2) (1)_compressed.pdf · uploaded 18 Jun 2026Source
  • Withdrawal Update Form 2Form-2 March 2026 (2) (1)_compressed.pdf · uploaded 18 Jun 2026Source
  • Withdrawal Update Form 3Form-3 March 2026 (2) (1).pdf · uploaded 18 Jun 2026Source
  • Form 5 (FY 2024-2025)form 5.pdf · uploaded 22 Jun 2026Source

Technical

  • Documentlayout plan.pdf · uploaded 14 Aug 2021Source
  • Documentbldg7 sheet 6_compressed.pdf · uploaded 14 Aug 2021Source
  • Documentbldg 7 sheet 7_compressed.pdf · uploaded 14 Aug 2021Source

Technical (Architect)

  • DocumentForm-1 31032024.pdf · uploaded 13 Dec 2024Source
  • DocumentForm-1 30062024.pdf · uploaded 13 Dec 2024Source
  • DocumentfORM-1 bUIL;DING nO-7.pdf · uploaded 20 Dec 2024Source
  • DocumentForm-1.pdf · uploaded 19 Mar 2025Source
  • DocumentForm-1 march 2026 (2) (1)_compressed.pdf · uploaded 18 Jun 2026Source

Technical (Engineer)

  • DocumentForm-2 31032024.pdf · uploaded 13 Dec 2024Source
  • DocumentForm-2 30060204.pdf · uploaded 13 Dec 2024Source
  • DocumentfORM-2 bUILDING nO-7.pdf · uploaded 20 Dec 2024Source
  • DocumentForm-2.pdf · uploaded 19 Mar 2025Source
  • DocumentForm-2 March 2026 (2) (1)_compressed.pdf · uploaded 18 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 4105 4112678 83110

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 2BHK, Shop86 units in all
Address
410/5 411/2/6/7/8 831/10, Mahim Road, PalgharPIN 401404
Village
Mahim, Palghar taluka
Land area for this project
2,600 sq m (27,986 sq ft)
Permissible built-up area
3,525 sq m (37,943 sq ft)
Sanctioned built-up area
3,525 sq m (37,943 sq ft)
Recreational open space
915 sq m (9,844 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

4105 4112678 83110

Land as published on MahaRERA's project page

410/5 411/2/6/7/8 831/10

Boundaries

North
19 40 47 75 N 72 45 11 70 E
South
19 40 46 51 N 72 45 11 71 E
East
19 40 47 17 N 72 45 12 16 E
West
19 40 47 11 N 72 45 11 14 E

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking86 units

5 of 86 units booked (6%), as the promoter reported to MahaRERA

1BHK · 39 units1RK · 8 units2BHK · 20 unitsShop · 19 units
TypeCarpet areaUnitsBooked
1BHK32.3 sq m · 348 sq ft10
1BHK32.56 sq m · 350 sq ft40
1BHK32.98 sq m · 355 sq ft10
1BHK33.03 sq m · 356 sq ft10
1BHK33.42 sq m · 360 sq ft80
1BHK34.16 sq m · 368 sq ft10
1BHK34.61 sq m · 373 sq ft41
1BHK34.61 sq m · 373 sq ft40
Show all 40 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1BHK34.69 sq m · 373 sq ft40
1BHK34.97 sq m · 376 sq ft10
1BHK35.42 sq m · 381 sq ft40
1BHK37.72 sq m · 406 sq ft10
1BHK38.17 sq m · 411 sq ft40
1BHK43.32 sq m · 466 sq ft10
1RK23.24 sq m · 250 sq ft10
1RK24.7 sq m · 266 sq ft10
1RK25.51 sq m · 275 sq ft10
1RK25.69 sq m · 277 sq ft10
1RK25.78 sq m · 277 sq ft41
2BHK43.77 sq m · 471 sq ft40
2BHK45 sq m · 484 sq ft40
2BHK46.97 sq m · 506 sq ft42
2BHK48.5 sq m · 522 sq ft41
2BHK48.54 sq m · 522 sq ft40
Shop10.85 sq m · 117 sq ft10
Shop11.58 sq m · 125 sq ft10
Shop11.72 sq m · 126 sq ft10
Shop11.95 sq m · 129 sq ft10
Shop12.59 sq m · 136 sq ft10
Shop12.87 sq m · 139 sq ft10
Shop13.1 sq m · 141 sq ft10
Shop13.71 sq m · 148 sq ft40
Shop13.99 sq m · 151 sq ft10
Shop13.99 sq m · 151 sq ft10
Shop14.29 sq m · 154 sq ft10
Shop14.35 sq m · 154 sq ft10
Shop14.66 sq m · 158 sq ft10
Shop14.99 sq m · 161 sq ft10
Shop15.39 sq m · 166 sq ft10
Shop15.67 sq m · 169 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Architectchirag mistry—
Chartered accountantKb Mistry And Associates—
EngineerMeshram And Thukral—
OtherThakur Enterprises—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Mahim

All 115 projects in Mahim · Compare Srushti Developers Build No 7 with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology