Company or firm · first RERA registration 2017
Srushti Developers
Deedo IDDD-Q7BGOf 2 registrations whose promised date has arrived, 2 kept it (100%).
Projects23 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shri Rajendra SrushtiP99000005173 | Mahim | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Shri Rajendra SrushtiP99000026892 | Mahim | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Srushti Developers Build No 7P99000031683 | Mahim | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology