Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 0% of its units are booked.

Mahim, Palghar 401404 · by Fia Developers Pvt. Ltd

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 5 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 19 May 2025, completion promised 31 Dec 2027, revised to 30 Apr 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000080307
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900008030719 May 202531 Dec 202730 Apr 2028Fia Developers Pvt. Ltd.Project page
Documents69

1 document held by Deedo, 68 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Card1 PAN Card.pdf · uploaded 18 Feb 2025Source

Legal

  • Declaration Form BForm-B Aum on 500 rs.pdf · uploaded 18 Mar 2025Source
  • Other – LegalAltered AOA.pdf · uploaded 25 Mar 2025Source
  • Other – LegalAltered MOA.pdf · uploaded 25 Mar 2025Source
  • Other – LegalKharedikhat 5937 - 2024 AUM_compressed-1-12.pdf · uploaded 3 Apr 2025Source
  • Other – LegalKharedikhat 5937 - 2024 AUM_compressed-13-24.pdf · uploaded 3 Apr 2025Source
  • Other – LegalKharedikhat 5937 - 2024 AUM_compressed-25-36.pdf · uploaded 3 Apr 2025Source
Show all 69 documentsShow fewer documents

Legal

  • Other – LegalKharedikhat 5937 - 2024 AUM_compressed-37-48.pdf · uploaded 3 Apr 2025Source
  • Other – LegalKharedikhat 5937 - 2024 AUM_compressed-49-60.pdf · uploaded 3 Apr 2025Source
  • Other – LegalKharedikhat 5937 - 2024 AUM_compressed-61-74.pdf · uploaded 3 Apr 2025Source
  • Legal Title reportTitle Aum residences.pdf · uploaded 8 Apr 2025Source

Migrated

  • 1 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 22 Jan 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC - Collector Office.pdf · uploaded 22 Jan 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan.pdf · uploaded 22 Jan 2025Source
  • 1 PAN Card1 PAN Card.pdf · uploaded 18 Feb 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B AUM.pdf · uploaded 18 Feb 2025Source
  • 1 Declaration in FORM BForm-B Aum on 500 rs.pdf · uploaded 18 Mar 2025Source
  • 1 a Details of encumbrances concerned to FinanceDeclaration Legal encumbrances.pdf · uploaded 24 Mar 2025Source
  • 2 a Details of encumbrances concerned to FinanceDeclaration Finance encumbrances.pdf · uploaded 24 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - 270225.pdf · uploaded 24 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Aum residences_compressed.pdf · uploaded 24 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - 170325.pdf · uploaded 24 Mar 2025Source
  • 1 CERSAI detailsDeclaration Cersai.pdf · uploaded 24 Mar 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format-A (1).pdf · uploaded 24 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterDeclaration allotment deviation report.pdf · uploaded 24 Mar 2025Source
  • 2 b Details of encumbrances concerned to LegalDeclaration Finance encumbrances.pdf · uploaded 24 Mar 2025Source
  • 1 b Details of encumbrances concerned to LegalDeclaration Legal encumbrances.pdf · uploaded 24 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementDeclaration agreement deviation report.pdf · uploaded 24 Mar 2025Source
  • 1 Proforma of Agreement for saleAFS DRAFT_FINAL.pdf · uploaded 24 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsNP.pdf · uploaded 24 Mar 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsSP.pdf · uploaded 24 Mar 2025Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDS.pdf · uploaded 24 Mar 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclousre of secured unsecured funds new draft.pdf · uploaded 24 Mar 2025Source
  • 2 Other – LegalAltered MOA.pdf · uploaded 25 Mar 2025Source
  • 1 Other – LegalAltered AOA.pdf · uploaded 25 Mar 2025Source
  • 1 Declaration about Commencement CertificateDeclaration CC Aum.pdf · uploaded 25 Mar 2025Source
  • 1 Other – TechnicalANNEXURE-A -Aum Residences.pdf · uploaded 25 Mar 2025Source
  • 8 Other – LegalKharedikhat 5937 - 2024 AUM_compressed-61-74.pdf · uploaded 3 Apr 2025Source
  • 7 Other – LegalKharedikhat 5937 - 2024 AUM_compressed-49-60.pdf · uploaded 3 Apr 2025Source
  • 6 Other – LegalKharedikhat 5937 - 2024 AUM_compressed-37-48.pdf · uploaded 3 Apr 2025Source
  • 5 Other – LegalKharedikhat 5937 - 2024 AUM_compressed-25-36.pdf · uploaded 3 Apr 2025Source
  • 3 Other – LegalKharedikhat 5937 - 2024 AUM_compressed-1-12.pdf · uploaded 3 Apr 2025Source
  • 4 Other – LegalKharedikhat 5937 - 2024 AUM_compressed-13-24.pdf · uploaded 3 Apr 2025Source
  • 1 Proforma of Allotment letterAUM_compressed.pdf · uploaded 7 Apr 2025Source
  • 1 Copy of the legal title reportTitle Aum residences.pdf · uploaded 8 Apr 2025Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC verification mail screenshotGmail - CC Issued by collector Palghar on BPMS system at village Mahim Gut No 923 plot no 2 order date 15 Jan 2025.pdf · uploaded 8 May 2025Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC Issued by collector Palghar on BPMS system at village Mahim Gut No 923 plot no 2 order date 15 Jan 2025.pdf · uploaded 8 May 2025Source
  • 2 Other – TechnicalVolunatrarily Declaration.pdf · uploaded 15 May 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 24 Oct 2025Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 24 Oct 2025Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 24 Oct 2025Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1FORM 1 - March 2026.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 2From 2 - March 2026.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 3Form 3 march 2026.pdf · uploaded 21 Apr 2026Source
  • Form 2A (FY 2025-2026)Form_2A - 25-26 AUM RESIDENCES.pdf · uploaded 25 Jun 2026Source
  • Withdrawal Update Form 1FORM 1 june 2026.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 june 2026.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 JUNE 2026.pdf · uploaded 20 Jul 2026Source
  • Form 5 (FY 2025-2026)Form 5- AUM FY 25-26-sing.pdf · uploaded 29 Sep 2026Source

Technical

  • DocumentLayout Plan.pdf · uploaded 22 Jan 2025Source
  • DocumentBuilding Plan.pdf · uploaded 22 Jan 2025Source
  • Other – TechnicalANNEXURE-A -Aum Residences.pdf · uploaded 25 Mar 2025Source
  • Other – TechnicalVolunatrarily Declaration.pdf · uploaded 15 May 2025Source

Technical (Architect)

  • DocumentFORM 1 june 2026.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentFORM 2 june 2026.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel FINAL PLOT NO. 2, S.NO 923

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
3BHK5 units in all
Address
S.no -923, Final Plot No. 2, Mahim Road, Palghar WestPIN 401404
Village
Mahim, Palghar taluka
Land area for this project
400 sq m (4,306 sq ft)
Permissible built-up area
610 sq m (6,561 sq ft)
Sanctioned built-up area
610 sq m (6,561 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

FINAL PLOT NO. 2S.NO 923

Land as published on MahaRERA's project page

S.NO -923, FINAL PLOT NO. 2

Boundaries

North
Allayali Shiv
South
9 Mtr Wide Road
East
Adj Plot No 01
West
Adj 6 Mtr Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking5 units

0 of 5 units booked (0%), as the promoter reported to MahaRERA

3BHK · 5 units
TypeCarpet areaUnitsBooked
3BHK89.79 sq m · 966 sq ft50

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVastu Shilp—
Chartered accountantMukesh V Patil & Company—
EngineerBharat Damji Vaja—
EngineerDarsh Consult—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Mahim

All 115 projects in Mahim · Compare Aum Residences with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology