10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects9
Registrations12some projects hold several
Completion still due39 past their date
Median extension4 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

12 MahaRERA registrations in Devkhop

3 extended, not yet due9 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Devkhop

9 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Vbhc Landscape 2Vbhc Mumbai Value Homes Private LimitedDue Mar 2027, extended 4 mo——
Vbhc LandscapeVbhc Mumbai Value Homes Private LimitedDue Mar 2027, extended 4 mo——
VBHC SpringwaterVbhc Mumbai Value Homes Private LimitedDue Aug 2027, extended 4 mo——
Vbhc 47 Rowland ParkVbhc Mumbai Value Homes Private Limited1 yr 8 mo late——
Greenwoods-2Anemones Hospitality And Hotels Private LimitedCompleted——
VBHC GreenwoodsVBHDC Bangalore Value Homes Private LimitedCompleted, extended 1 yr—74%
VBHC GreenwoodsVBHDC Bangalore Value Homes Private LimitedCompleted, extended 1 yr—84%
VBHC GreendewVbhc Mumbai Value Homes Private LimitedCompleted, extended 1 yr—41%
VBHC GreengladeVbhc Mumbai Value Homes Private LimitedCompleted, extended 3 yrs—29%
Devkhop market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Vbhc Mumbai Value Homes Private Limited4 projects
  2. Vbhc Mumbai Value Homes Private Limited2 projects
  3. Vbhdc Bangalore Value Homes Private Limited2 projects
  4. Anemones Hospitality And Hotels Private Limited1 project

Devkhop, in questions

How many projects in Devkhop run late?

10 in 10 MahaRERA registrations (12 of 12): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Devkhop by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology