Sansari, Nashik
Deedo IDDL-NSK-SANSARI9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects24
Registrations24
Completion still due519 past their date
Median extension4 months17% of registrations extended
Regulatory cases1on 1 project
9 in 10 registrations run late here
24 MahaRERA registrations in Sansari
2 completed1 not yet due4 extended, not yet due17 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Sansari
24 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Anandam RowhomesShivay Buildecowell LLP | Due Mar 2029 | — | — |
| Vimal VishvaAnantadrishti Constructions | Due Jan 2027, extended 4 mo | — | 20% |
| Deolali Meadows D WingAtb Samarth LLP | 11 mo late | — | — |
| Regant PlazaRakhee Papneja | Completed | — | 11% |
| Samarth Paradise Phase IIIChandrakant Ramkrishna Godse | Completed | — | — |
| Panchmoti ResidencyDeepak Machhindranath Balkawade | Due Apr 2027, extended 4 mo | — | 8% |
| NakshatraStandard Realtors Private Limited | 1 yr 5 mo late | — | — |
| PancharatnaDeepak Machhindranath Balkawade | Due Apr 2027, extended 4 mo | — | — |
| Sai NiketanDevraj Builders And Land Developers | Completed | — | 56% |
| Shah S Rajlaxmi ParkShah Buildcon | Completed | — | 56% |
| Sahyadri ParkRakesh Baburao Palde | 3 yrs 5 mo late | — | — |
| Samarth ParadiseChandrakant Ramkrishna Godse | Completed | — | 38% |
| Oak WoodsS.v.enterprises | Completed | — | 88% |
| VINI Park - Phase IIIBindu Land Developers and Builders | Completed | — | — |
| Vaishnav ShrustiAnita Hemant Godse | 1 yr 11 mo late | — | — |
| Royal ResidencyParas Rajesh Rohra | Completed | — | — |
| SerenityNarayani Developers | Completed | — | — |
| Sai NisargDevraj Builders & Land Developers | 3 yrs 5 mo late | — | — |
| Shah S Sai Residency Phase IIShah Builders And Developers | Completed | — | — |
| Gayatridham Co-Op.housing Society LtdVedant Construwell | Completed, extended 5 yrs | — | 98% |
| Padmavati NagagRiddhi Siddhi Constructions | Completed | — | 27% |
| Shri Samarth Sai NiwasShri Sai Samartha Constructions | Completed | — | 72% |
| Shahs Parashram ApartmentShah Builders And Developers | Completed | — | 100% |
| Hari VatikaKbc Global Limited | Completed | — | — |
Nearby: other villages in Nashik
Most active promoters
- Chandrakant Ramkrishna Godse2 projects
- Deepak Machhindranath Balkawade2 projects
- Devraj Builders & Land Developers2 projects
- Shah Builders And Developers2 projects
- Anantadrishti Constructions1 project
- Anita Hemant Godse1 project
- Atb Samarth Llp1 project
- Bindu Land Developers And Builders1 project
- Karda Constructions Limited1 project
- Kbc Global Limited1 project
Sansari, in questions
How many projects in Sansari run late?
9 in 10 MahaRERA registrations (21 of 24): their completion date was extended or has passed, data through 28 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sansari by Deedo. Medians on fewer than 3 deeds are not shown.
Data through28 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology