Pipla, Nagpur
4 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects84
Registrations89some projects hold several
Completion still due4148 past their date
Median extension4 months42% of registrations extended
Regulatory cases10on 8 projects
8 in 10 registrations run late here
89 MahaRERA registrations in Pipla
8 completed13 not yet due28 extended, not yet due40 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Pipla
84 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sai Krishana EmpireRradiance Infraa | Due Dec 2032 | — | — |
| JalsaNeevstone Developers | Due Dec 2030 | — | — |
| Golden LegacyGolden Megastructures LLP | Due Apr 2030, extended 4 mo | — | — |
| Modern NakshatraModern Arch Builders and Developers | Due Apr 2030, extended 4 mo | — | — |
| Sai Nagri - 12Sudhakar Vitthalrao Kohale Gopal J Chandak and Chandrapal Hanumansing Gaherwar | Due Apr 2031, extended 4 mo | — | — |
| Sky 140 WinterSkyjoy Builders Private Limited | Due Apr 2030, extended 4 mo | — | — |
| Lake Shore Oasis-Twin DuplexRsl Realities LLP | Due Apr 2029, extended 4 mo | — | — |
| Golden SignatureShree Amarnath Developers | Due Jan 2029, extended 4 mo | — | — |
| Sai Nagri - 11Sudhakar Vitthalrao Kohale Gopal J Chandak and Chandrapal Hanumansing Gaherwar | Due Jul 2030, extended 4 mo | — | — |
| Ved Vidhi VenturesVed Vidhi Ventures | Due Apr 2030, extended 4 mo | — | 0% |
| Shri Govardhan Bhakti ParkUnicorn Estates | Due Apr 2029, extended 4 mo | — | — |
| Pyramid AmaraSwami Builders And Developers | Due Dec 2032 | — | — |
| Mauli-29 Unicorn PropertiesUnicorn Properties | Due Apr 2029, extended 4 mo | — | — |
| Gulmohar GreensLush Properties-1 | Due Dec 2029 | — | — |
| Mauli-22 Unicorn EstatesUnicorn Estates | Due Dec 2028 | — | — |
| Shree Gajanan Vihar IVShri Gajanan Builder & Developers | 7 mo late | — | — |
| Golden AvenueGolden Homes Infrastructures | 1 yr 7 mo late | — | — |
| Central HeightsNirmaan Infra | Due Apr 2029, extended 4 mo | — | 11% |
| EbonyLuxora Infrastructure Private Limited | Due Apr 2027, extended 4 mo | — | — |
| Vrindavan Estate Phase IIBvn Constro Ventures LLP | Due Feb 2029, extended 4 mo | — | — |
| Shyam Nagri 2Shyam Kashiprasad Borele | Due Apr 2029, extended 4 mo | — | — |
| Atharva Nagari VIIIAtharva Infrastructures | Due Dec 2028 | — | — |
| Shyam Nagri 1M/S Bhaiji Infra Projects Private Limited | Due Dec 2028 | — | — |
| Shyam Nagri 3M/S Bhaiji Infra Projects Private Limited | Due Apr 2029, extended 4 mo | — | — |
| Shree Gajanan Vihar IIIShri Gajanan Builder & Developers | Completed | — | — |
Nearby: other localities in Nagpur (Rural)
Most active promoters
- Luxora Infrastructure Private Limited21 projects
- Atharva Infrastructures8 projects
- Pyramid Ventures India Pvt Ltd3 projects
- Rachana Developers3 projects
- Shri Gajanan Builder & Developers3 projects
- Golden Homes Infrastructures2 projects
- Leverage Spaces LLP2 projects
- M/S Bhaiji Infra Projects Private Limited2 projects
- Nirmaan Infra2 projects
- Radiance Infraventure2 projects
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology