Pipla, Nagpur

4 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects84
Registrations89some projects hold several
Completion still due4148 past their date
Median extension4 months42% of registrations extended
Regulatory cases10on 8 projects
Pipla market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

8 in 10 registrations run late here

89 MahaRERA registrations in Pipla

8 completed13 not yet due28 extended, not yet due40 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Pipla

84 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Sai Krishana EmpireRradiance InfraaDue Dec 2032——
JalsaNeevstone DevelopersDue Dec 2030——
Golden LegacyGolden Megastructures LLPDue Apr 2030, extended 4 mo——
Modern NakshatraModern Arch Builders and DevelopersDue Apr 2030, extended 4 mo——
Sai Nagri - 12Sudhakar Vitthalrao Kohale Gopal J Chandak and Chandrapal Hanumansing GaherwarDue Apr 2031, extended 4 mo——
Sky 140 WinterSkyjoy Builders Private LimitedDue Apr 2030, extended 4 mo——
Lake Shore Oasis-Twin DuplexRsl Realities LLPDue Apr 2029, extended 4 mo——
Golden SignatureShree Amarnath DevelopersDue Jan 2029, extended 4 mo——
Sai Nagri - 11Sudhakar Vitthalrao Kohale Gopal J Chandak and Chandrapal Hanumansing GaherwarDue Jul 2030, extended 4 mo——
Ved Vidhi VenturesVed Vidhi VenturesDue Apr 2030, extended 4 mo—0%
Shri Govardhan Bhakti ParkUnicorn EstatesDue Apr 2029, extended 4 mo——
Pyramid AmaraSwami Builders And DevelopersDue Dec 2032——
Mauli-29 Unicorn PropertiesUnicorn PropertiesDue Apr 2029, extended 4 mo——
Gulmohar GreensLush Properties-1Due Dec 2029——
Mauli-22 Unicorn EstatesUnicorn EstatesDue Dec 2028——
Shree Gajanan Vihar IVShri Gajanan Builder & Developers7 mo late——
Golden AvenueGolden Homes Infrastructures1 yr 7 mo late——
Central HeightsNirmaan InfraDue Apr 2029, extended 4 mo—11%
EbonyLuxora Infrastructure Private LimitedDue Apr 2027, extended 4 mo——
Vrindavan Estate Phase IIBvn Constro Ventures LLPDue Feb 2029, extended 4 mo——
Shyam Nagri 2Shyam Kashiprasad BoreleDue Apr 2029, extended 4 mo——
Atharva Nagari VIIIAtharva InfrastructuresDue Dec 2028——
Shyam Nagri 1M/S Bhaiji Infra Projects Private LimitedDue Dec 2028——
Shyam Nagri 3M/S Bhaiji Infra Projects Private LimitedDue Apr 2029, extended 4 mo——
Shree Gajanan Vihar IIIShri Gajanan Builder & DevelopersCompleted——

Most active promoters

  1. Luxora Infrastructure Private Limited21 projects
  2. Atharva Infrastructures8 projects
  3. Pyramid Ventures India Pvt Ltd3 projects
  4. Rachana Developers3 projects
  5. Shri Gajanan Builder & Developers3 projects
  6. Golden Homes Infrastructures2 projects
  7. Leverage Spaces LLP2 projects
  8. M/S Bhaiji Infra Projects Private Limited2 projects
  9. Nirmaan Infra2 projects
  10. Radiance Infraventure2 projects
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology