RERA projects in Jamtha

93 projects under 96 MahaRERA registrations, registered 2017–2026. 17% have a completion date extended beyond the one promised.

Locality
93RERA projects
96Registrationssome projects hold several
32Completion still due64 past their completion date, 14 marked completed
4 monthsMedian extension beyond promised date17% of registrations extended
2Regulatory caseson 2 projects
128Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201715
20187
20197
20207
202116
202218
202312
20244
20257
20263

Projects in Jamtha

93 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Anandam 14Design DevelopersPP11900026014295 Aug 202631 Dec 202831 Dec 2028Not yet due0
Anandam 7Safeco Hygiene Films Private LimitedPP11900025019976 Jan 202631 Dec 203030 Apr 2031Extended 4 mo0
KS Shreeya HomesKS Shreeya Homes And Infrastructures Private LimitedPP119000250043730 Jul 202531 Mar 203031 Jul 2030Extended 4 mo0
Oasis 35Sandip Omprakash AgarwalP505000807663 Jul 202531 Dec 202731 Dec 2027Not yet due0
Moreshwar Park-11Prasanna InfraPP119000250014126 Jun 202531 Dec 203030 Apr 2031Extended 4 mo0
Wainganga LifecityWainganga LifestyleP5050007931228 Feb 202531 Jan 2030—Completed0
Mahalaxmi Nagar 42Ara BuildconP505000790593 Feb 202510 Feb 203010 Feb 2030Not yet due0
Kalash Vatika Phase 2Deepavali Construction Pvt LtdP505000787388 Jan 202531 May 202930 Sep 2029Extended 4 mo0
Moreshwar Park 8Nikhil Prakash ChapleP5050005524714 Mar 202431 Jan 202931 May 2029Extended 4 mo0
Sandesh Park View-3Ample Mercantile Private LimitedP5050005460331 Jan 202431 Dec 202631 Dec 2026Not yet due0
Sandesh Park ViewAmple Mercantile Private LimitedP50500054312, PP119000250306715 Jan 202431 Dec 202930 Apr 2030Extended 4 mo0
Krishna NagariRashmi Mahendra SardaP505000542123 Jan 202431 Dec 202831 Dec 2028Not yet due0
Highway Radiance-4Dilip Pralhadrai AgrawalP5050005414129 Dec 202331 Dec 202631 Dec 2026Not yet due0
Highway RadianceR Sandesh Infrastructures Private LimitedP50500054064, PP119000250156827 Dec 202331 Dec 202930 Apr 2030Extended 4 mo0
Royal CrestRoyal Fort Developers and Landmark RealitiesP5050005409127 Dec 202325 Aug 202825 Dec 2028Extended 4 mo0
Mahalaxmi Nagar 33 Sector - 2Ara Habitats LLPP5050005396218 Dec 202312 Dec 202812 Dec 2028Not yet due0
Mahalaxmi Nagar 33 Sector - 3Ara Habitats LLPP5050005395618 Dec 202327 Dec 202827 Dec 2028Not yet due0
Mahalaxmi Nagar 32Ara Habitats LLPP5050005378528 Nov 202325 Nov 202825 Nov 2028Not yet due0
Mahalaxmi Nagar 33 Sector - 1Ara Habitats LLPP5050005363721 Nov 202325 Nov 202825 Nov 2028Not yet due0
Sg Estate - 2Aska Real Estate Private LimitedP5050005315317 Oct 202331 Mar 202631 Mar 2026Promised date passed0
Moreshwar Park 7Prasanna DevelopersP5050005213124 Jul 202331 Dec 202831 Dec 2028Not yet due0
Moreshwar Park 5Prasanna Developers & Prasanna PlannersP5050005024227 Mar 202331 Dec 2028—Not yet due0
Mauli Nagar 15Mauli InfraP5050004974324 Feb 202331 Dec 202331 Dec 2023Promised date passed0
Rsg - West EndR Sandesh Infrastructures Private LimitedP505000492313 Feb 202331 Dec 202631 Dec 2026Not yet due0
Maruti park2Nikhil ChapleP5050004826622 Dec 20221 Oct 20241 Oct 2024Promised date passed0

Other localities in Nagpur (Rural)

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Sandesh Infrastructures Pvt Ltd8 projects
  2. Ara Habitats LLP7 projects
  3. K S Shreeya Infrastructure Pvt Ltd6 projects
  4. Ample Mercantile Private Limited3 projects
  5. Mahalaxmi Infra3 projects
  6. Sadesh Realty Builders LLP3 projects
  7. Aekom Devloper2 projects
  8. KS Shreeya Homes And Infrastructures Private Limited2 projects
  9. Luvkush Corporation Private Limited2 projects
  10. Mahalaxmi Buildcon2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology