RERA projects in Panjari Farm

24 projects under 25 MahaRERA registrations, registered 2017–2026. 40% have a completion date extended beyond the one promised.

Locality
24RERA projects
25Registrationssome projects hold several
12Completion still due13 past their completion date, 3 marked completed
4 monthsMedian extension beyond promised date40% of registrations extended
0Regulatory casesnone on MahaRERA's lists
24Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20180
20191
20206
20212
20225
20232
20244
20251
20262

Projects in Panjari Farm

24 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Keshavam City 23Vitthal Mahadeoji BarapatrePP119000260156014 Aug 202631 Mar 202931 Mar 2029Not yet due0
Dwarka Panjari 15Dwarka Panjari EstatesPP119000250210520 Jan 202631 Dec 202930 Apr 2030Extended 4 mo0
Shivam HeightsKb RealtyPR119000250079615 Sep 202531 Dec 202930 Apr 2030Extended 4 mo0
Sarswati Nagar 4Sarswati DevelopersP5050007765617 Oct 202412 Feb 202511 Feb 2026Extended 12 mo0
Mauli Town- 20Apw Realty LLPP5050005538622 Mar 202431 Dec 202731 Dec 2027Not yet due0
Mohini ParkBhikulal Jugalkishore BajajP5050005458431 Jan 20241 Nov 2028—Not yet due0
Silver Park 15Tirupati DevelopersP5050005443525 Jan 202430 Nov 2028—Completed0
Golden Glory-101Golden Land DevelopersP5050005400019 Dec 202331 Dec 202630 Apr 2027Extended 4 mo0
Aaditya Premium - 9Aaditya InfraP5050005298010 Oct 202321 Jul 202521 Jul 2025Promised date passed0
Kuhaasa ResidencyMahendra Manohar SardaP505000480357 Dec 202231 Dec 202731 Dec 2027Not yet due0
SG Estate -1 , Residential Layout Plan in Kh no 145/5, P.H No 42Navneet Shukul And 1 OtherP505000479722 Dec 202231 Mar 20249 Aug 2024Extended 5 mo0
Prestige ParkSakshi Karan DubeyP5050004678410 Sep 202215 Jun 202715 Jun 2027Not yet due0
Mai City Phase VIMy Assets InfraventureP5050004624120 Jun 202230 Apr 202730 Aug 2027Extended 4 mo0
Mangaldeep City IIIMangaldeep DevelopersP5050004520410 May 202231 Dec 202730 Apr 2028Extended 4 mo0
Shreenidhi Estate 4Shri Sai Builders And DevelopersP5050003026210 Aug 202131 Jul 202531 Jul 2025Promised date passed0
Anjaneya Nagar-IIShri Anjaneya Developers Pvt. Ltd.P5050002946429 May 202131 Mar 202531 Mar 2025Promised date passed0
Anandam ParkPankaj Chandrakant WaghmareP505000273948 Dec 202030 Jun 202331 Dec 2026Extended 42 mo0
Akash ViharAkash ViharP5050002666521 Oct 20201 Jul 20241 Jul 2024Promised date passed0
Shivam Empire 1Shivam Empire1P5050002520623 Mar 202030 Dec 202230 Dec 2022Promised date passed0
Shiv Brighton Phase IIIOm Shivam Buildcon Private LimitedP5050002427130 Jan 202030 Jan 202429 Jan 2025Extended 12 mo0
Mauli Nagar 2Mauli AssociatesP5050002421427 Jan 202030 Dec 202130 Dec 2021Promised date passed0
Shiv Brighton Phase IVOm Shivam Buildcon Private LimitedP5050002419324 Jan 202030 Jan 202429 Jan 2025Extended 12 mo0
Shivam EmpireMachhindra Kadam And Vijay BorundiyaP5050002045915 Apr 201930 Mar 202130 Mar 2021Promised date passed0
Shiv BrightonOm Shivam Buildcon Private LimitedP50500006203, P5050000629514 Aug 201731 Jan 2021—Completed0

Other localities in Nagpur (Rural)

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Om Shivam Buildcon Private Limited3 projects
  2. Aaditya Infra1 project
  3. Akash Vihar1 project
  4. Apw Realty LLP1 project
  5. Bhikulal Jugalkishore Bajaj1 project
  6. Dwarka Panjari Estates1 project
  7. Golden Land Developers1 project
  8. Kb Realty1 project
  9. Machhindra Kadam And Vijay Borundiya1 project
  10. Mahendra Manohar Sarda1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology