RERA projects in Borkhedi
13 projects under 13 MahaRERA registrations, registered 2017–2026. 77% have a completion date extended beyond the one promised.
Locality
13RERA projects
13Registrations
10Completion still due3 past their completion date
4 monthsMedian extension beyond promised date77% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 1 |
| 2020 | 0 |
| 2021 | 1 |
| 2022 | 0 |
| 2023 | 3 |
| 2024 | 4 |
| 2025 | 1 |
| 2026 | 2 |
Projects in Borkhedi
13 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mauli Niwasa-37Confidence Buildcon Private Limited | PP1190002600772 | 15 Jun 2026 | 31 Mar 2030 | 31 Jul 2030 | Extended 4 mo | 0 |
| Mauli Town-36Confidence Buildcon Private Limited | PP1190002502037 | 9 Jan 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Sai Nagri 10Saidham Builders And Associates | PP1190002500930 | 24 Sep 2025 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Unity ResidencyKeshav Husukale Huf | P50500077844 | 7 Nov 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Sai Nagri 9Saidham Builders And Associates | P50500077184 | 29 Jul 2024 | 31 Jul 2029 | 31 Jul 2029 | Not yet due | 0 |
| Ozen City IIOzen Buildcon | P50500055543 | 2 Apr 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Sahayog GoldSahayog Properties | P50500055112 | 4 Mar 2024 | 30 Sep 2026 | 30 Jan 2027 | Extended 4 mo | 0 |
| Anandam TenLush Properties | P50500051074 | 22 May 2023 | 31 Mar 2028 | 31 Jul 2028 | Extended 4 mo | 0 |
| Rsg TownR Sandesh Infrastructures Private Limited | P50500049658 | 22 Feb 2023 | 30 Jun 2027 | 30 Oct 2027 | Extended 4 mo | 0 |
| Ozen City - Residential Layout Plan in Kh. No 192/A And 192/BOzen Buildcon | P50500048993 | 24 Jan 2023 | 31 Mar 2027 | 31 Jul 2027 | Extended 4 mo | 0 |
| Bhakti Park 2Kahnoria Estates Pvt Ltd | P50500031602 | 31 Oct 2021 | 10 Oct 2026 | 10 Oct 2026 | Promised date passed | 0 |
| Kirti NagarRajkumar Ghanshyamdas Agrawal | P50500023463 | 16 Dec 2019 | 25 Mar 2024 | 25 Mar 2024 | Promised date passed | 0 |
| Vedaarya HomesAdditya Infrastructure | P50500003103 | 4 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Extended 12 mo | 0 |
Other localities in Nagpur (Rural)
Most active promoters
By projects registered here, as named on MahaRERA.
- Confidence Buildcon Private Limited2 projects
- Ozen Buildcon2 projects
- Saidham Builders And Associates2 projects
- Additya Infrastructure1 project
- Kahnoria Estates Pvt Ltd1 project
- Keshav Husukale Huf1 project
- Lush Properties1 project
- Rajkumar Ghanshyamdas Agrawal1 project
- R Sandesh Infrastructures Private Limited1 project
- Sahayog Properties1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology