8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects88
Registrations93some projects hold several
Completion still due4548 past their date
Median extension4 months43% of registrations extended
Regulatory cases11on 9 projects

8 in 10 registrations run late here

93 MahaRERA registrations in Pipla

8 completed14 not yet due31 extended, not yet due40 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Pipla

88 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Shyam Nagri 3Bhaiji Infra Projects Private LimitedDue Apr 2029, extended 4 mo——
Vrindavan EstateBvn Constro Ventures LLPDue Dec 2028, extended 4 mo——
Shree Gajanan Vihar IIIShri Gajanan Builder & DevelopersCompleted——
Pyramid GloriaPyramid Tajshree LLPDue Mar 2028——
Leverage Green Woods Unity-C GrandLeverage Spaces LLPDue Oct 2029, extended 4 mo—35%
Vista 3ASamsara Fund Advisors Pvt. Ltd.5 mo late——
Central Heights 1Nirmaan InfraDue Dec 2028——
Dream OasisShree G InfraDue Dec 2026, extended 2 yrs——
Golden VistaGolden Homes InfrastructuresCompleted, extended 1 yr——
Sai Krishna Residency Wing BRadiance InfraventureCompleted—100%
Shubhparth NagariR B InfraDue Apr 2027, extended 4 mo——
Ryka OrchidRyka Infracon11 mo late——
Shree Nagari-1Shree Infrastructures AopDue Apr 2028, extended 4 mo—20%
Super City IIIKanjibhai Sodavadia And Suresh Patel Pipla1 yr 11 mo late——
Garden Homes Atharva Nagari VIIAtharva InfrastructuresDue Mar 2028, extended 4 mo——
Pyramid GoldGolden Home InfraventuresDue Dec 2026—85%
Central AnnexBlackrock Buildcon Private LimitedDue Jun 2028, extended 4 mo——
Vista 3ALuxora Infrastructure Private Limited3 yrs 11 mo late——
Leverage Greenwoods - UnityLeverage Infrastructures Private Limited11 mo late——
Shree Laxmi PrideShree Laxmi Venture Pvt LtdCompleted——
Atharva EliteAtharva InfrastructuresCompleted——
Shree Gajanan Vihar IIShri Gajanan Builder & DevelopersCompleted——
Vijaya MauliThe Squarefeet CompanyCompleted——
DiamondleafLuxora Infrastructure Private LimitedDue Apr 2027, extended 4 mo——
Rachana Mithila IIIRachana DevelopersCompleted——
Pipla market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Luxora Infrastructure Private Limited21 projects
  2. Atharva Infrastructures9 projects
  3. Luxora Infrastructure Private Limited4 projects
  4. Rachana Developers3 projects
  5. Shri Gajanan Builder & Developers3 projects
  6. Bhaiji Infra Projects Private Limited2 projects
  7. Bvn Constro Ventures Llp2 projects
  8. Golden Homes Infrastructures2 projects
  9. Leverage Spaces Llp2 projects
  10. Nirmaan Infra2 projects

Pipla, in questions

How many projects in Pipla run late?

8 in 10 MahaRERA registrations (71 of 93): their completion date was extended or has passed, data through 5 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Pipla by Deedo. Medians on fewer than 3 deeds are not shown.

Data through5 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology