Golden Vista
CompletedPipla, Nagpur 440037 |Promoter: Golden Homes Infrastructures
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Completed
- Buildings
- 2
- Land area for this project
- 5,870 sq m (63,179 sq ft)
- Permissible built-up area
- 18,747 sq m (2,01,789 sq ft)
- Sanctioned built-up area
- 18,747 sq m (2,01,789 sq ft)
- Planning authority
- OFFICE OF THE NAGAR PANCHAYAT BESA-PIPLA
- Address
- Ph No.38, Kh No.136/2/A Of Mouja Pipla, Besa Pipla, PiplaPIN 440037
- Designated bank account
- State Bank Of India
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year
The latest completion date on record passed 7 months ago.
- Registered
- 6 Mar 2023
- Promised
- 31 Mar 2025
- Revised
- 31 Mar 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50500050049 | 6 Mar 2023 | 31 Mar 2025 | 31 Mar 2026 | Golden Homes Infrastructures | Project page |
2 buildings
Buildings and wings named in the registration
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 units registered
Parking
| Building | Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|---|
| Wing A | Closed/Covered | 0 | 1 | 0 | 0 | 1 |
| Wing A | Open Space | 0 | 0 | 0 | 0 | 0 |
| Wing B | Closed/Covered | 0 | 1 | 0 | 0 | 1 |
| Wing B | Open Space | 166 | 34 | 0 | 0 | 200 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Wing A
Wing B
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
74 documents held by Deedo, 113 filings listed on MahaRERA's project page
Encumbrances
Commencement certificates
Others
- Other7 Feb 2023ViewSource
- Other7 Feb 2023ViewSource
- Other7 Feb 2023ViewSource
- Other16 Feb 2023ViewSource
- Other23 Aug 2023ViewSource
- Other23 Aug 2023ViewSource
- Other22 Oct 2023ViewSource
- Other22 Oct 2023ViewSource
- Other6 Apr 2024ViewSource
- Other10 Apr 2024ViewSource
- Other5 Aug 2024ViewSource
- Other27 Jan 2025ViewSource
- Other29 Jan 2025ViewSource
- Other23 Apr 2025ViewSource
- Other19 May 2026ViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
Form 1s
- Form 131 Jan 2024ViewSource
- Form 14 Mar 2024ViewSource
- Form 14 Mar 2024ViewSource
- Form 14 Mar 2024ViewSource
- Form 15 Apr 2024ViewSource
- Form 16 Jul 2024ViewSource
- Form 127 Oct 2024ViewSource
- Form 121 Jan 2025ViewSource
- Form 15 May 2025ViewSource
- Form 120 Jan 2026ViewSource
- Form 17 Feb 2026ViewSource
- Form 119 Apr 2026ViewSource
Form 2s
Layout plans
Building plans
Document library
- a Details of encumbrances concerned to FinanceLegal Encumbrance.pdf · uploaded 7 Feb 2023View
- b Details of encumbrances concerned to LegalLegal Encumbrance.pdf · uploaded 7 Feb 2023View
- Copy of Layout Approval (in case of layout)Sheet 1-6_11zon.pdf · uploaded 7 Feb 2023View
- Copy of Layout Approval (in case of layout)Sheet 2-6_11zon.pdf · uploaded 7 Feb 2023View
- Copy of Layout Approval (in case of layout)Sheet 3-6_11zon.pdf · uploaded 7 Feb 2023View
- Copy of Layout Approval (in case of layout)Sheet 4-6_11zon.pdf · uploaded 7 Feb 2023View
- Copy of Layout Approval (in case of layout)Sheet 5-6_11zon.pdf · uploaded 7 Feb 2023View
- Copy of Layout Approval (in case of layout)Sheet 6-6_11zon.pdf · uploaded 7 Feb 2023View
- Building Plan Approval / NA Order for plotted developmentSheet 1-6_11zon.pdf · uploaded 7 Feb 2023View
- Building Plan Approval / NA Order for plotted developmentSheet 2-6_11zon.pdf · uploaded 7 Feb 2023View
- Building Plan Approval / NA Order for plotted developmentSheet 3-6_11zon.pdf · uploaded 7 Feb 2023View
- Building Plan Approval / NA Order for plotted developmentSheet 4-6_11zon.pdf · uploaded 7 Feb 2023View
- Building Plan Approval / NA Order for plotted developmentSheet 5-6_11zon.pdf · uploaded 7 Feb 2023View
- Building Plan Approval / NA Order for plotted developmentSheet 6-6_11zon.pdf · uploaded 7 Feb 2023View
- Commencement Certificates / NA Order for plotted developmentCommencement Cert.pdf · uploaded 7 Feb 2023View
- Declaration about Commencement CertificateFORM D.pdf · uploaded 7 Feb 2023View
- Declaration in FORM BFORM B.pdf · uploaded 7 Feb 2023View
- CERSAI detailsCERSAI.pdf · uploaded 7 Feb 2023View
- Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 7 Feb 2023View
- Proforma of Allotment letterAllotment Letter.pdf · uploaded 7 Feb 2023View
- Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration About Separate Bank Account.pdf · uploaded 7 Feb 2023View
- Deviation Report with respect to Allotment letterDeviation in Allotment Letter.pdf · uploaded 7 Feb 2023View
- Deviation Report with respect to model copy of AgreementDeviation Report In Agreenment To Sale.pdf · uploaded 7 Feb 2023View
- Other – LegalSALE DEED.pdf · uploaded 7 Feb 2023View
- Copy of the legal title reportLEGAL TITLE REPORT.pdf · uploaded 16 Feb 2023View
- Proforma of Agreement for saleAGREEMENT FOR SALE.PDF · uploaded 16 Feb 2023View
- a Details of encumbrances concerned to FinanceFINANCIAL NO EN.PDF · uploaded 21 Feb 2023View
- a Details of encumbrances concerned to FinanceLEGAL NO EN.PDF · uploaded 21 Feb 2023View
- b Details of encumbrances concerned to LegalFINANCIAL NO EN.PDF · uploaded 21 Feb 2023View
- b Details of encumbrances concerned to LegalLEGAL NO EN.PDF · uploaded 21 Feb 2023View
- Other – FinanceSELF_DECLARATION_FIRST_Q_1_23_24.pdf · uploaded 23 Aug 2023View
- Disclosure of sold/ booked inventoryDisclosure_Of_Sold_Unsold_Inventory_Till_10_July_2023.pdf · uploaded 23 Aug 2023View
- Disclosure of sold/ booked inventoryDISCLOSURE GOLDEN VISTA MAR-202320102023194913.pdf · uploaded 22 Oct 2023View
- Disclosure of sold/ booked inventoryDISCLOSURE GOLDEN VISTA SEP-202320102023195000.pdf · uploaded 22 Oct 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 GOLDEN VISTA 2022-2023 25-08-202320102023193340.pdf · uploaded 22 Oct 2023View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Golden Vista_Form-1- Architect Certificate_Dec-23.pdf · uploaded 31 Jan 2024View
- Commencement Certificates / NA Order for plotted developmentPermit.pdf · uploaded 2 Mar 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_MAR-23.pdf · uploaded 4 Mar 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_JUNE-23.pdf · uploaded 4 Mar 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_SEP-23.pdf · uploaded 4 Mar 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_Dec-23.pdf · uploaded 4 Mar 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2-Engineers Certificate_Goden vista_Mar-23.pdf · uploaded 4 Mar 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2-Engineers Certificate_Goden vista_June-23.pdf · uploaded 4 Mar 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2-Engineers Certificate_Goden vista_Sept-23.pdf · uploaded 4 Mar 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2-Engineers Certificate_Goden vista_Dec-23.pdf · uploaded 4 Mar 2024View
- Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Golden Vista_RERA_Form 2A_MAR-23.pdf · uploaded 7 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentSheet no 05.pdf · uploaded 21 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentSheet no 04.pdf · uploaded 21 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentSheet no 03.pdf · uploaded 21 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentSheet no 02.pdf · uploaded 21 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentSheet no 01.pdf · uploaded 21 Mar 2024View
- Commencement Certificates / NA Order for plotted developmentOC_.pdf · uploaded 3 Apr 2024View
- Declaration about Commencement Certificateform dV1_Golden vista.pdf · uploaded 3 Apr 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Golden Vista_Form-1- Architect Certificate_Mar-24.pdf · uploaded 5 Apr 2024View
- Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Golden Vista_RERA_Form 2A_MAR-24.pdf · uploaded 5 Apr 2024View
- Other – TechnicalCC MAIL.pdf · uploaded 6 Apr 2024View
- Declaration about Commencement Certificateform dV1_Golden.pdf · uploaded 6 Apr 2024View
- Disclosure of sold/ booked inventorySOLD AND UNSOLD INVENTORY.pdf · uploaded 10 Apr 2024View
- Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A.pdf · uploaded 29 Jun 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_June-24_compressed.pdf · uploaded 6 Jul 2024View
- Disclosure of sold/ booked inventoryinventory Wing-A and B_compressed.pdf · uploaded 5 Aug 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)VISTA.pdf · uploaded 27 Oct 2024View
- Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Golden Vista.pdf · uploaded 5 Dec 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Golden Vista-Dec-2024_.pdf · uploaded 21 Jan 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 27 Jan 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 27 Jan 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 27 Jan 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Jan 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Jan 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Jan 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE(1).pdf · uploaded 27 Jan 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Jan 2025View
- Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameRera Declaration - Bank account- golden vista format a.pdf · uploaded 29 Jan 2025View
- Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)golden home infra format b.pdf · uploaded 29 Jan 2025View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 GHI.pdf · uploaded 23 Apr 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 GHI.pdf · uploaded 23 Apr 2025View
- Disclosure of sold/ booked inventorySold GHI.pdf · uploaded 23 Apr 2025View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate-Wig -A_compressed (1).pdf · uploaded 5 May 2025View
- Withdrawal Update Form 1FORM-1.pdf · uploaded 20 Jan 2026View
- Withdrawal Update Form 2FORM-2_GOLDEN VISTA_JUNE-2025.pdf · uploaded 20 Jan 2026View
- Withdrawal Update Form 1FORM-1.pdf · uploaded 20 Jan 2026View
- Withdrawal Update Form 2FORM-2_GOLDEN VISTA_JUNE-2025.pdf · uploaded 20 Jan 2026View
- Withdrawal Update Form 1FORM-1.pdf · uploaded 20 Jan 2026View
- Withdrawal Update Form 2FORM-2_GOLDEN VISTA_JUNE-2025.pdf · uploaded 20 Jan 2026View
- Withdrawal Update Form 1FORM-1 SEPT-25 GOLDEN VISTA.pdf · uploaded 7 Feb 2026View
- Withdrawal Update Form 2FORM-2_GOLDEN VISTA_SEP-25.pdf · uploaded 7 Feb 2026View
- Withdrawal Update Form 1Golden Vista_Form-1- Architect Certificate_Dec-25.pdf · uploaded 9 Feb 2026View
- Withdrawal Update Form 2Form-2-Engineers Certificate_Goden vista_ december 2025 upd.pdf · uploaded 9 Feb 2026View
- Withdrawal Update Form 1Golden Vista_Form-1- Architect Certificate_Dec-25.pdf · uploaded 19 Apr 2026View
- Withdrawal Update Form 2Form-2-Engineers Certificate_Goden vista_ december 2025 upd.pdf · uploaded 19 Apr 2026View
- Occupational CertificateOC MERGE WITH MAIL COMPPRESED.pdf · uploaded 19 May 2026View
Promoter documents
Technical documents
- Layout ApprovalSheet 1-6_11zon.pdfView
- Layout ApprovalSheet 2-6_11zon.pdfView
- Layout ApprovalSheet 3-6_11zon.pdfView
- Layout ApprovalSheet 4-6_11zon.pdfView
- Layout ApprovalSheet 5-6_11zon.pdfView
- Layout ApprovalSheet 6-6_11zon.pdfView
- Building Plan ApprovalSheet 1-6_11zon.pdfView
- Building Plan ApprovalSheet 2-6_11zon.pdfView
- Building Plan ApprovalSheet 3-6_11zon.pdfView
- Building Plan ApprovalSheet 4-6_11zon.pdfView
- Building Plan ApprovalSheet 5-6_11zon.pdfView
- Building Plan ApprovalSheet 6-6_11zon.pdfView
- Building Plan ApprovalSheet no 05.pdfView
- Building Plan ApprovalSheet no 04.pdfView
- Building Plan ApprovalSheet no 03.pdfView
- Building Plan ApprovalSheet no 02.pdfView
- Building Plan ApprovalSheet no 01.pdfView
Other legal documents
- Other – LegalSALE DEED.pdfView
Financial documents
- Other – FinanceSELF_DECLARATION_FIRST_Q_1_23_24.pdf · uploaded 23 Aug 2023View
Proforma allotment letter
- Proforma allotment letterAllotment Letter.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- complaintMatched by RERA number
Complaint CC12605405
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Pipla, Nagpur (Rural) taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
PH NO.38, KH NO.136/2/A OF MOUJA PIPLA
Boundaries
- North
- Khasra No 131
- South
- Khasra No 136
- East
- Khasra No 135
- West
- Khasra No 139
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Cd Giripunje | — |
| Chartered accountant | Ca Upendra Singh Thakur | — |
| Chartered accountant | G A D & Associates | — |
| Chartered accountant | MJM Associates | — |
| Chartered accountant | Sumit Santosh Agrawal & Associates | — |
| Engineer | Atul Talekar | — |
Source: MahaRERA project page. Contact details are not shown.