Vista 3A
Deedo IDDP-NGP-MTMJCompletion was pushed back 3 years to Dec 2025, and that date has passed too; MahaRERA lists it: deregistered; 100% of its units are booked.
Pipla, Nagpur 440034 · by Luxora Infrastructure Private Limited · 46% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 3 years to Dec 2025, and that date has passed too
- This projectRegistered 17 Jan 2022, completion promised 31 Dec 2022, revised to 31 Dec 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory record1
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- DeregisteredMatched by RERA number
Deregistered: Luxora Infrastructure Private Limited
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP50500032662
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50500032662 | 17 Jan 2022 | 31 Dec 2022 | 31 Dec 2025 | Luxora Infrastructure Private Limited | Project page |
Documents147
65 documents held by Deedo, 82 filings listed on MahaRERA's project page
Show all 147 documentsShow fewer documents
Other (16)
Commencement certificate (3)
Form 1 (27)
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
Encumbrance details
- Encumbrance detailsDate not statedView
Layout plan (8)
Building plan
- Building planDate not statedView
Legal
Migrated
- 1 PAN CardLIPL PAN.pdf · uploaded 1 Dec 2021View
- 1 Details of encumbrancesEncumbrance_Vista 3A.pdf · uploaded 1 Dec 2021View
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_Vista 3A_Highlighted.pdf · uploaded 1 Dec 2021View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate_Vista 3A _compressed.pdf · uploaded 1 Dec 2021View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Certificate_Vista 3A_compressed.pdf · uploaded 1 Dec 2021View
- 1 CERSAI detailsCERSAI 97 (BOB)-merged.pdf · uploaded 7 Dec 2021View
- 1 Copy of the legal title reportVista 3A_Title 1_compressed.pdf · uploaded 14 Dec 2021View
- 2 Copy of the legal title reportVista 3A_Title 2_compressed.pdf · uploaded 23 Dec 2021View
- 1 Building Plan Approval / NA Order for plotted developmentCommencement Certificate_Vista 3A.pdf · uploaded 23 Dec 2021View
- 2 Building Plan Approval / NA Order for plotted developmentVista 3A_IOD.pdf · uploaded 23 Dec 2021View
- 3 Building Plan Approval / NA Order for plotted developmentEMP_Vista 3A IOD_Updated.pdf · uploaded 23 Dec 2021View
- 1 Proforma of Allotment letterProforma of agreement for sale.pdf · uploaded 24 Dec 2021View
- 2 Proforma of Allotment letterAllotment Letter_Vista 3A_Generic.pdf · uploaded 24 Dec 2021View
- 1 Declaration in FORM BForm B_Vista_3A_with Date.pdf · uploaded 26 Dec 2021View
- 1 Copy of Layout Approval (in case of layout)Vista 3A Layout 2 New.pdf · uploaded 7 Jan 2022View
- 2 Copy of Layout Approval (in case of layout)Vista 3A 1 Layout_New.pdf · uploaded 7 Jan 2022View
- 3 Copy of Layout Approval (in case of layout)Vista 3A Layout 3_New.pdf · uploaded 7 Jan 2022View
- 4 Copy of Layout Approval (in case of layout)EMP_Vista 3A IOD_Updated.pdf · uploaded 7 Jan 2022View
- 1 Declaration about Commencement CertificateDeclaration About Commencement Certificate_with stamp.pdf · uploaded 7 Jan 2022View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch_Cert_Vista 3A_Mar_22.pdf · uploaded 18 May 2022View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Vista 3A_QA_Cert_Form 2A.pdf · uploaded 6 Dec 2022Source
- 1 Proforma of Agreement for saleProforma of Agreement for Sale.pdf · uploaded 15 Feb 2023View
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC Vista 3A _Jun_22.pdf · uploaded 21 Jun 2023View
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC Vista 3A 2_Sep_22.pdf · uploaded 21 Jun 2023View
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Vista 3A.pdf · uploaded 5 Jul 2023View
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg_Cert_Vista 3A_Jun_22.pdf · uploaded 5 Jul 2023View
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg_Cert_Vista 3A_Sep_22.pdf · uploaded 5 Jul 2023View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)VISTA 3A FY 22-23.pdf · uploaded 16 Mar 2024View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)QA_Cert_Vista 3A_Mar_24.pdf · uploaded 15 May 2024View
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch_Cert_Vista 3A_Mar_24.pdf · uploaded 5 Aug 2024View
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch_Cert_Vista 3A_Jun_24.pdf · uploaded 5 Aug 2024View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Vista 3A_2(FY 23-24).pdf · uploaded 29 Nov 2024View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch_Cert_Vista 3A_Dec_24.pdf · uploaded 7 Feb 2025View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg_Cert_Vista 3A_Dec_24.pdf · uploaded 7 Feb 2025View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch_Cert_Vista 3A_Mar_2025.pdf · uploaded 15 Apr 2025View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg_Cert_Vista 3A_March_2025.pdf · uploaded 21 Apr 2025View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Mar_22.pdf · uploaded 23 Apr 2025View
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Sep_22.pdf · uploaded 23 Apr 2025View
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Jun_22.pdf · uploaded 23 Apr 2025View
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Dec_22.pdf · uploaded 23 Apr 2025View
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Mar_23.pdf · uploaded 23 Apr 2025View
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Jun_23.pdf · uploaded 23 Apr 2025View
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Sep_23.pdf · uploaded 23 Apr 2025View
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3ADec_23.pdf · uploaded 23 Apr 2025View
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Mar_24.pdf · uploaded 23 Apr 2025View
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Jun_24.pdf · uploaded 23 Apr 2025View
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Sep_24.pdf · uploaded 23 Apr 2025View
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Dec_24.pdf · uploaded 23 Apr 2025View
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Cert_Vista 3A_Mar_25.pdf · uploaded 23 Apr 2025View
- 1 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Jun_22.pdf · uploaded 1 May 2025View
- 2 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Sep_22.pdf · uploaded 1 May 2025View
- 3 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Dec_22.pdf · uploaded 1 May 2025View
- 4 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Mar_23.pdf · uploaded 1 May 2025View
- 5 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Jun_23.pdf · uploaded 1 May 2025View
- 6 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Sep_23.pdf · uploaded 1 May 2025View
- 7 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Dec_23.pdf · uploaded 1 May 2025View
- 8 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Mar_24.pdf · uploaded 1 May 2025View
- 9 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Jun_24.pdf · uploaded 1 May 2025View
- 10 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Sep_24.pdf · uploaded 1 May 2025View
- 11 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Dec_24.pdf · uploaded 1 May 2025View
- 12 Disclosure of sold/ booked inventorySold Unsold Inventory_Vista 3A_Mar_25.pdf · uploaded 1 May 2025View
- 1 Declaration in FORM BRera Form B.pdf · uploaded 7 Jun 2025View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form-2A.pdf · uploaded 7 Jun 2025View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)Form 5.pdf · uploaded 7 Jun 2025View
- Form 5 (FY 2024-2025)Form 5_Upload_Vista 3A_FY24_25.pdf · uploaded 7 Jan 2026Source
Technical
- DocumentCommencement Certificate_Vista 3A.pdf · uploaded 23 Dec 2021View
- DocumentVista 3A_IOD.pdf · uploaded 23 Dec 2021View
- DocumentEMP_Vista 3A IOD_Updated.pdf · uploaded 23 Dec 2021View
- DocumentVista 3A Layout 2 New.pdf · uploaded 7 Jan 2022View
- DocumentVista 3A 1 Layout_New.pdf · uploaded 7 Jan 2022View
- DocumentVista 3A Layout 3_New.pdf · uploaded 7 Jan 2022View
- DocumentEMP_Vista 3A IOD_Updated.pdf · uploaded 7 Jan 2022View
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Khasra No 97/1/2/3/4/ pt
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- Khasra No 97/1/2/3/4/ pt, Besa Pipla Road, MouzaPIN 440034
- Village
- Pipla, Nagpur (Rural) taluka
- Land area for this project
- 4,934 sq m (53,106 sq ft)
- Permissible built-up area
- 7,693 sq m (82,804 sq ft)
- Sanctioned built-up area
- 7,693 sq m (82,804 sq ft)
- Designated bank account
- 21
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Khasra No 97/1/2/3/4/ pt
Boundaries
- North
- Kh No 99 1 2
- South
- Kh No 81 pt
- East
- Vista 3B
- West
- Proposed Vista 2
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Chartered accountant | Neha Joshi | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Pipla
- Sai Krishana EmpireRERA PR1190002602417
- JalsaRERA PR1190002601674
- Golden LegacyRERA PR1190002600930
- Modern NakshatraRERA PM1190002600499
- Sai Nagri - 12RERA PP1190002501898
- Sky 140 WinterRERA PR1191012501662
- Lake Shore Oasis-Twin DuplexRERA PM1193032500920
- Golden SignatureRERA PR1190002500694
All 88 projects in Pipla · Compare Vista 3A with another project