Company or firm · 22 projects · 23 MahaRERA registrations · 1 reported completed

22Projects23 RERA registrations
1Completedas reported on MahaRERA project pages
54%Kept RERA date7 of 13 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 13 extended
4Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Treeline 5P50500002936Pipla2017Certificate Signed31 Dec 201930 Dec 2021+24 months
Vista 3BP50500003509Pipla2017Active30 Dec 2021—On date
Park Mansion 48P50500004854Pipla2017Certificate Signed31 Dec 202830 Apr 2029+4 months
Vista 3CP50500007884Pipla2017Certificate Signed31 Dec 201930 Jun 2024+54 months
Park House TranquilP50500009028Pipla2017Certificate Signed31 Dec 202630 Apr 2027+4 months
Park Mansion 54P50500010626Pipla2017Active31 Dec 2026—On date
Primo 112P50500010660Pipla2017Completed31 Dec 201918 Feb 2025+62 months
Park House HolisticP50500011398Pipla2017Certificate Signed30 Dec 202630 Apr 2027+4 months
Treeline 6P50500011412Pipla2017Certificate Signed31 Dec 203130 Apr 2032+4 months
The MeadowsP50500013138Pipla2017Certificate Signed30 Sep 201930 Sep 2019On date
SpringfieldP50500013193Pipla2017Certificate Signed31 Mar 202631 Mar 2026On date
The WillowsP50500014261Pipla2017Certificate Signed30 Sep 201930 Sep 2019On date
The Willows 2P50500014787Pipla2018Certificate Signed30 Sep 202030 Sep 2020On date
Springfield 3P50500018570Pipla2018Active30 Jun 2021—On date
Springfield 2P50500018825Pipla2018Certificate Signed31 Jan 202731 Jan 2027On date
Park Mansion 52P50500019484Pipla2019Certificate Signed31 Dec 202631 Dec 2026On date
Park House TranquilP50500021749Pipla2019Certificate Signed30 Jun 202230 Nov 2025+41 months
AspenP50500026092Pipla2020Certificate Signed30 Mar 202430 Mar 2024On date
BirchP50500026118Pipla2020Certificate Signed30 Mar 202431 Dec 2026+33 months
DiamondleafP50500027741Pipla2021Certificate Signed31 Dec 202630 Apr 2027+4 months
Vista 3AP50500032662Pipla2022Certificate Signed31 Dec 202231 Dec 2025+36 months
EbonyP50500053556Pipla2023Certificate Signed31 Dec 202630 Apr 2027+4 months
Phoenix ParkP50500078104Besa2024Certificate Signed31 Jul 202730 Nov 2027+4 months
Show all 23 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Treeline 5+24 mo
  • Vista 3BOn date
  • Park Mansion 48+4 mo
  • Vista 3C+54 mo
  • Park House Tranquil+4 mo
  • Park Mansion 54On date
  • Primo 112+62 mo
  • Park House Holistic+4 mo
  • Treeline 6+4 mo
  • The MeadowsOn date
Show all 23 registrations
  • SpringfieldOn date
  • The WillowsOn date
  • The Willows 2On date
  • Springfield 3On date
  • Springfield 2On date
  • Park Mansion 52On date
  • Park House Tranquil+41 mo
  • AspenOn date
  • Birch+33 mo
  • Diamondleaf+4 mo
  • Vista 3A+36 mo
  • Ebony+4 mo
  • Phoenix Park+4 mo

Track record notes

  • 7 of 13 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 62 months, for Primo 112 (P50500010660).