Luxora Infrastructure Private Limited
Deedo IDDD-JV02Of 13 registrations whose promised date has arrived, 6 kept it (46%). The rest ran a median 14 mo late.
Delivery record
14 of 23 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 23 registrations
23 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | DiamondleafRegulatory order: PROJECT NAME: DIAMOND LEAF (Regulatory Case No. 407 OF 2025) dated 15 Sept, 2025. | 15 Sep 2025 |
| Regulatory order | Vista 3CRegulatory order: PROJECT NAME:VISTA 3C (Regulatory Case No.89 of 2023) dated 7 November 2023. | 7 Nov 2023 |
| complaint | Vista 3BComplaint CC004000000010024 | Not on record |
| appeal | Vista 3BAppeal AT004000000031625/19 | Not on record |
| Deregistered | Vista 3ADeregistered: Luxora Infrastructure Private Limited | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Treeline 5P50500002936 | Pipla | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
| Vista 3BP50500003509 | Pipla | Active | 30 Dec 2021 | — | +59 mo* |
| Park Mansion 48P50500004854 | Pipla | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Vista 3CP50500007884 | Pipla | Certificate Signed | 31 Dec 2019 | 30 Jun 2024 | +54 mo |
| Park House TranquilP50500009028 | Pipla | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Park Mansion 54P50500010626 | Pipla | Active | 31 Dec 2026 | — | On date |
| Primo 112P50500010660 | Pipla | Completed | 31 Dec 2019 | 18 Feb 2025 | +62 mo |
| Park House HolisticP50500011398 | Pipla | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 mo |
| Treeline 6P50500011412 | Pipla | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 mo |
| The MeadowsP50500013138 | Pipla | Certificate Signed | 30 Sep 2019 | 30 Sep 2019 | On date |
| SpringfieldP50500013193 | Pipla | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| The WillowsP50500014261 | Pipla | Certificate Signed | 30 Sep 2019 | 30 Sep 2019 | On date |
| The Willows 2P50500014787 | Pipla | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | On date |
| Springfield 3P50500018570 | Pipla | Active | 30 Jun 2021 | — | On date |
| Springfield 2P50500018825 | Pipla | Certificate Signed | 31 Jan 2027 | 31 Jan 2027 | On date |
| Park Mansion 52P50500019484 | Pipla | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Park House TranquilP50500021749 | Pipla | Certificate Signed | 30 Jun 2022 | 30 Nov 2025 | +53 mo* |
| AspenP50500026092 | Pipla | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | On date |
| BirchP50500026118 | Pipla | Certificate Signed | 30 Mar 2024 | 31 Dec 2026 | +33 mo |
| DiamondleafP50500027741 | Pipla | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Vista 3AP50500032662 | Pipla | Certificate Signed | 31 Dec 2022 | 31 Dec 2025 | +47 mo* |
| EbonyP50500053556 | Pipla | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Phoenix ParkP50500078104 | Besa | Certificate Signed | 31 Jul 2027 | 30 Nov 2027 | +4 mo |
Show all 23 registrationsShow fewer
Luxora Infrastructure Private Limited, in questions
Does Luxora Infrastructure Private Limited finish projects on time?
Of 13 MahaRERA registrations whose promised completion date has arrived, 6 kept it (46%). The rest ran a median 14 mo late. Across Maharashtra, 73% kept their date.
How many projects has Luxora Infrastructure Private Limited registered with MahaRERA?
22 projects under 23 MahaRERA registrations; 9 completed on MahaRERA.
Does Luxora Infrastructure Private Limited have MahaRERA regulatory cases?
5 regulatory cases name its registrations.