Company or firm · first RERA registration 2017

Luxora Infrastructure Private Limited

Deedo IDDD-JV02

Of 13 registrations whose promised date has arrived, 6 kept it (46%). The rest ran a median 14 mo late.

Projects2223 RERA registrations
Kept RERA date46%Maharashtra: 73%
Median delay14 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases5no insolvency

Delivery record

14 of 23 registrations with dates moved or missed their RERA date · months late against the original promise

Show all 23 registrations

23 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Treeline 5P50500002936PiplaCertificate Signed31 Dec 201930 Dec 2021+24 mo
Vista 3BP50500003509PiplaActive30 Dec 2021—+59 mo*
Park Mansion 48P50500004854PiplaCertificate Signed31 Dec 202830 Apr 2029+4 mo
Vista 3CP50500007884PiplaCertificate Signed31 Dec 201930 Jun 2024+54 mo
Park House TranquilP50500009028PiplaCertificate Signed31 Dec 202630 Apr 2027+4 mo
Park Mansion 54P50500010626PiplaActive31 Dec 2026—On date
Primo 112P50500010660PiplaCompleted31 Dec 201918 Feb 2025+62 mo
Park House HolisticP50500011398PiplaCertificate Signed30 Dec 202630 Apr 2027+4 mo
Treeline 6P50500011412PiplaCertificate Signed31 Dec 203130 Apr 2032+4 mo
The MeadowsP50500013138PiplaCertificate Signed30 Sep 201930 Sep 2019On date
SpringfieldP50500013193PiplaCertificate Signed31 Mar 202631 Mar 2026On date
The WillowsP50500014261PiplaCertificate Signed30 Sep 201930 Sep 2019On date
The Willows 2P50500014787PiplaCertificate Signed30 Sep 202030 Sep 2020On date
Springfield 3P50500018570PiplaActive30 Jun 2021—On date
Springfield 2P50500018825PiplaCertificate Signed31 Jan 202731 Jan 2027On date
Park Mansion 52P50500019484PiplaCertificate Signed31 Dec 202631 Dec 2026On date
Park House TranquilP50500021749PiplaCertificate Signed30 Jun 202230 Nov 2025+53 mo*
AspenP50500026092PiplaCertificate Signed30 Mar 202430 Mar 2024On date
BirchP50500026118PiplaCertificate Signed30 Mar 202431 Dec 2026+33 mo
DiamondleafP50500027741PiplaCertificate Signed31 Dec 202630 Apr 2027+4 mo
Vista 3AP50500032662PiplaCertificate Signed31 Dec 202231 Dec 2025+47 mo*
EbonyP50500053556PiplaCertificate Signed31 Dec 202630 Apr 2027+4 mo
Phoenix ParkP50500078104BesaCertificate Signed31 Jul 202730 Nov 2027+4 mo
Show all 23 registrationsShow fewer

Luxora Infrastructure Private Limited, in questions

Does Luxora Infrastructure Private Limited finish projects on time?

Of 13 MahaRERA registrations whose promised completion date has arrived, 6 kept it (46%). The rest ran a median 14 mo late. Across Maharashtra, 73% kept their date.

How many projects has Luxora Infrastructure Private Limited registered with MahaRERA?

22 projects under 23 MahaRERA registrations; 9 completed on MahaRERA.

Does Luxora Infrastructure Private Limited have MahaRERA regulatory cases?

5 regulatory cases name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology