Luxora Infrastructure Private Limited
Company or firm · 22 projects · 23 MahaRERA registrations · 1 reported completed
22Projects23 RERA registrations
1Completedas reported on MahaRERA project pages
54%Kept RERA date7 of 13 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 13 extended
4Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Treeline 5P50500002936 | Pipla | 2017 | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 months |
| Vista 3BP50500003509 | Pipla | 2017 | Active | 30 Dec 2021 | — | On date |
| Park Mansion 48P50500004854 | Pipla | 2017 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Vista 3CP50500007884 | Pipla | 2017 | Certificate Signed | 31 Dec 2019 | 30 Jun 2024 | +54 months |
| Park House TranquilP50500009028 | Pipla | 2017 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Park Mansion 54P50500010626 | Pipla | 2017 | Active | 31 Dec 2026 | — | On date |
| Primo 112P50500010660 | Pipla | 2017 | Completed | 31 Dec 2019 | 18 Feb 2025 | +62 months |
| Park House HolisticP50500011398 | Pipla | 2017 | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 months |
| Treeline 6P50500011412 | Pipla | 2017 | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 months |
| The MeadowsP50500013138 | Pipla | 2017 | Certificate Signed | 30 Sep 2019 | 30 Sep 2019 | On date |
| SpringfieldP50500013193 | Pipla | 2017 | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| The WillowsP50500014261 | Pipla | 2017 | Certificate Signed | 30 Sep 2019 | 30 Sep 2019 | On date |
| The Willows 2P50500014787 | Pipla | 2018 | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | On date |
| Springfield 3P50500018570 | Pipla | 2018 | Active | 30 Jun 2021 | — | On date |
| Springfield 2P50500018825 | Pipla | 2018 | Certificate Signed | 31 Jan 2027 | 31 Jan 2027 | On date |
| Park Mansion 52P50500019484 | Pipla | 2019 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Park House TranquilP50500021749 | Pipla | 2019 | Certificate Signed | 30 Jun 2022 | 30 Nov 2025 | +41 months |
| AspenP50500026092 | Pipla | 2020 | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | On date |
| BirchP50500026118 | Pipla | 2020 | Certificate Signed | 30 Mar 2024 | 31 Dec 2026 | +33 months |
| DiamondleafP50500027741 | Pipla | 2021 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Vista 3AP50500032662 | Pipla | 2022 | Certificate Signed | 31 Dec 2022 | 31 Dec 2025 | +36 months |
| EbonyP50500053556 | Pipla | 2023 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Phoenix ParkP50500078104 | Besa | 2024 | Certificate Signed | 31 Jul 2027 | 30 Nov 2027 | +4 months |
Show all 23 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 23 registrations
Track record notes
- 7 of 13 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 62 months, for Primo 112 (P50500010660).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: DIAMOND LEAF (Regulatory Case No. 407 OF 2025) dated 15 Sept, 2025. · Diamondleaf · P50500027741 · 15 Sep 2025
- Regulatory orderRegulatory order: PROJECT NAME:VISTA 3C (Regulatory Case No.89 of 2023) dated 7 November 2023. · Vista 3C · P50500007884 · 7 Nov 2023
- complaintComplaint CC004000000010024 · Vista 3B · P50500003509
- appealAppeal AT004000000031625/19 · Vista 3B · P50500003509
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology