Deedo IDDP-NGP-DW1VMahaRERA shows it completed, after its date was pushed back 5 years and 2 months; no MahaRERA orders on record; 100% of its units are booked.
Pipla, Nagpur 440034 · by Luxora Infrastructure Private Limited · 46% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 5 years and 2 months
- This projectRegistered 31 Aug 2017, completion promised 31 Dec 2019, revised to 18 Feb 2025.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP50500010660
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50500010660 | 31 Aug 2017 | 31 Dec 2019 | 18 Feb 2025 | Luxora Infrastructure Private Limited | Project page |
Documents143
36 documents held by Deedo, 107 filings listed on MahaRERA's project page
Show all 143 documentsShow fewer documents
Form 1 (10)
Form 2 (9)
Commencement certificate (2)
Other (9)
Document library
- Copy of Layout Approval (in case of layout)PRIMO_112_2.pdf · uploaded 29 Jul 2017Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Primo 112.pdf · uploaded 31 Jul 2017View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate Primo 112.pdf · uploaded 31 Jul 2017Source
- Proforma of Allotment letterPrimo 11220170729172451.pdf · uploaded 31 Jul 2017Source
- Details of encumbrancesencumbrances Primo 112.pdf · uploaded 31 Jul 2017Source
- Copy of the legal title reportTitle Certificate Primo 112.pdf · uploaded 31 Jul 2017Source
- Building Plan Approval (IOD)IOD Primo 112.pdf · uploaded 31 Jul 2017View
- Copy of the legal title reportTitle Certificate Primo 112.pdf · uploaded 31 Jul 2017Source
- Declaration in FORM BDeclaration Form Primo 112.pdf · uploaded 31 Jul 2017View
- Otherprimo 11220170731172553.pdf · uploaded 31 Jul 2017Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)02_RP-14A Architects Certificate_Primo112.pdf · uploaded 18 Jan 2019View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)02_RP-14A Engineers Cetificate_Primo-112.pdf · uploaded 18 Jan 2019Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)PRIMO112 ( ARCH )20181228120915.pdf · uploaded 21 Jan 2019View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)PRIMO112 ( ENG )20181228120744.pdf · uploaded 21 Jan 2019Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Cert-Primo-112.pdf · uploaded 4 Jul 2019View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Cert-Primo-112.pdf · uploaded 4 Jul 2019Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Eng-Cert-Primo-112.pdf · uploaded 5 Jul 2019Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch-Cert-Primo-112.pdf · uploaded 5 Jul 2019View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Eng-Cert-Primo-112.pdf · uploaded 4 Sep 2019Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo112_Dec_18.pdf · uploaded 5 Sep 2019View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Primo- 112.pdf · uploaded 5 Sep 2019View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Cert_Primo112_Mar_19.pdf · uploaded 5 Sep 2019Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Cert_Primo_112_Mar_19.pdf · uploaded 6 Sep 2019Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_cert_Primo_112_Jun_19.pdf · uploaded 6 Sep 2019Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Primo_112_30_Jun_19.pdf · uploaded 6 Sep 2019Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo112_Sep_19.pdf · uploaded 8 Jan 2020Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Primo-112_compressed.pdf · uploaded 18 Sep 2020View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Cert_Primo 112_Sep_19.pdf · uploaded 18 Sep 2020Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Primo-112_compressed.pdf · uploaded 18 Sep 2020View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Cert_MARCH -21_Primo 112_compressed.pdf · uploaded 4 Aug 2021View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert__Mar 21_Primo 112_compressed.pdf · uploaded 4 Aug 2021Source
- Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A_Primo112_Sep_2019_compressed.pdf · uploaded 16 Aug 2021Source
- Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A_Primo112_Mar_2020_compressed.pdf · uploaded 16 Aug 2021Source
- Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A_Primo112_Sep_2020_compressed.pdf · uploaded 16 Aug 2021Source
- Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A_Primo112_Mar 2021_compressed.pdf · uploaded 16 Aug 2021Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch cert Sep 21 Primo-112_compressed.pdf · uploaded 11 Nov 2021Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Cert Primo 112 Sep 21_compressed.pdf · uploaded 16 Nov 2021Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Primo-112_compressed.pdf · uploaded 23 Nov 2021View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Cert_Primo 112_Dec 21_compressed.pdf · uploaded 15 Mar 2022Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Cert_park Primo 112_Dec 21_Final_compressed.pdf · uploaded 15 Mar 2022View
- Disclosure of sold/ booked inventoryDisclosure of Sold_Booked_Primo112.pdf · uploaded 15 Mar 2022Source
- CERSAI detailsCERSAI_Report_Primo 112.pdf · uploaded 16 Mar 2022Source
- Declaration about Commencement CertificateDeclaration For Commencement Cert Rera Primo112.pdf · uploaded 23 Mar 2022View
- Commencement Certificates / NA Order for plotted developmentCommencement_Cert_Primo112.pdf · uploaded 23 Mar 2022View
- Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5_PRIMO-112 ( 2018-19)_compressed.pdf · uploaded 25 Mar 2022Source
- Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5_PRIMO 112 (19-20)_compressed.pdf · uploaded 25 Mar 2022Source
- Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5_PRIMO-112 ( 2020-2021)_compressed.pdf · uploaded 25 Mar 2022Source
- Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form 5_PRIMO-112 (2017-18)_compressed.pdf · uploaded 25 Mar 2022Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo 112_Mar_22_compressed.pdf · uploaded 9 Nov 2022Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo_112_Sep_22.pdf · uploaded 9 Nov 2022Source
- Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)QA_Cert_Primo112_Mar_22.pdf · uploaded 23 Feb 2023Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Primo-112_compressed.pdf · uploaded 27 Mar 2023View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Primo-112_compressed.pdf · uploaded 27 Mar 2023View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect's Certificate_Primo112.pdf · uploaded 27 Mar 2023Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo-112_Jun_2021_compressed.pdf · uploaded 27 Mar 2023Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Primo-112_compressed.pdf · uploaded 27 Mar 2023View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate_Dec -20_Primo 112.pdf · uploaded 27 Mar 2023View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Cert_Primo-112_Jun_2021_compressed.pdf · uploaded 27 Mar 2023View
- Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)QA_Cert_Primo 112_Mar_23.pdf · uploaded 20 Jun 2023Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARC Primo-112_Mar_23.pdf · uploaded 21 Jun 2023Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_PRIMO 112_Jun_23.pdf · uploaded 6 Oct 2023Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo 112_Sep_23.pdf · uploaded 18 Dec 2023Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Cert_PRIMO 112_Dec_23.pdf · uploaded 23 Feb 2024Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Primo 112_Dec_23.pdf · uploaded 23 Feb 2024View
- Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Primo-FY 21-22.pdf · uploaded 16 Mar 2024Source
- Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Primo-FY 21-22.pdf · uploaded 16 Mar 2024Source
- Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Primo FY 22-23.pdf · uploaded 16 Mar 2024Source
- Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)QA_Cert_Primo112_Mar_24.pdf · uploaded 15 May 2024Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo 112_Mar_24.pdf · uploaded 15 May 2024Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Cert_Primo 112_Mar_24.pdf · uploaded 27 May 2024View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo 112_Jun_24.pdf · uploaded 6 Aug 2024Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Cert_Primo 112_Jun_24.pdf · uploaded 6 Aug 2024View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Cert_Primo 112_Sep_24.pdf · uploaded 31 Oct 2024Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo 112_Sep_24.pdf · uploaded 31 Oct 2024Source
- Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Primo 112_Form 5 ( FY 23-24).pdf · uploaded 29 Nov 2024Source
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo 112_Dec_24.pdf · uploaded 7 Feb 2025Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Cert_Primo 112_Dec_24.pdf · uploaded 7 Feb 2025Source
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPrimo OC.pdf · uploaded 24 Feb 2025Source
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPrimo OC.pdf · uploaded 25 Feb 2025Source
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 27 Mar 2025View
- Declaration in FORM BForm B Primo.pdf · uploaded 29 Mar 2025Source
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Cert_Primo 112_Mar_25.pdf · uploaded 15 Apr 2025View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo 112_Mar_2025.pdf · uploaded 15 Apr 2025View
- Declaration in FORM BForm B Primo 112.pdf · uploaded 16 Apr 2025View
- Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)QA_Cert_Primo112_Mar_25.pdf · uploaded 10 Jul 2025View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch_Cert_Primo 112_Jun_25_Signed.pdf · uploaded 18 Jul 2025View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_Cert_Primo 112_Jun_25_Signed.pdf · uploaded 18 Jul 2025View
Promoter documents
- Legal Title reportTitle Certificate Primo 112.pdf · uploaded 31 Jul 2017Source
- Legal Title reportTitle Certificate Primo 112.pdf · uploaded 31 Jul 2017Source
- Declaration Form BDeclaration Form Primo 112.pdf · uploaded 31 Jul 2017View
- Declaration Form BForm B Primo.pdf · uploaded 29 Mar 2025Source
- Declaration Form BForm B Primo 112.pdf · uploaded 16 Apr 2025View
Other legal documents
- Otherprimo 11220170731172553.pdfSource
Proforma allotment letter
- Proforma allotment letterPrimo 11220170729172451.pdfSource
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel KH No 90/1 pt 90/2 pt 91 pt 108/1 pt 108/2 pt 108/3 pt · Joint Director Town Planning/Collectors Office Nagpur
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Completed
- Unit types
- 1BHK90 units in all
- Address
- KH No 90/1 pt 90/2 pt 91 pt 108/1 pt 108/2 pt 108/3 pt, Kharsoli Road, MauzaPIN 440034
- Village
- Pipla, Nagpur (Rural) taluka
- Location
- 21.08020, 79.12028
- Land area for this project
- 2,602 sq m (28,011 sq ft)
- Permissible built-up area
- 4,922 sq m (52,980 sq ft)
- Sanctioned built-up area
- 4,922 sq m (52,980 sq ft)
- Planning authority
- Joint Director Town Planning/Collectors Office Nagpur
- Designated bank account
- Bank Of Baroda
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
KH No 90/1 pt 90/2 pt 91 pt 108/1 pt 108/2 pt 108/3 pt
Boundaries
- North
- Kh No 109 2
- South
- Kh No 90 pt
- East
- Proposed Primo 113
- West
- 12 mt wide internal road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking90 units · 31 parking spaces
90 units registered
| Type | Carpet area | Units |
|---|---|---|
| 1BHK | 38.61 sq m · 416 sq ft | 30 |
| 1BHK | 38.9 sq m · 419 sq ft | 60 |
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 10 |
| Open Space | 0 | 0 | 0 | 0 | 21 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress2 buildings and areas
Work completed, as the promoter reported it to MahaRERA (Form 1)
Primo 112
Show all 11 activitiesShow fewer activities
Common areas and amenities
Show all 15 activitiesShow fewer activities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.