Skip to content

Sai Krishna Residency Wing B

Certificate Signed

Pipla, Nagpur 440034 |Promoter: Radiance Infraventure

Residential / Group HousingRERAP50500047943
1 Dec 2022Registered with MahaRERA
31 Mar 2025Promised completion
1Building
46Units registered46 booked (100%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK, 3BHK, Shop46 units in all
Address
Kh No 189/1 A Mauza Pipla, Pipla, PiplaPIN 440034
Designated bank account
212
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.14580, 79.08815
Sai Krishna Residency Wing B is at latitude 21.14580, longitude 79.08815.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2025

The latest completion date on record passed 1 year and 7 months ago.

Registered
1 Dec 2022
Promised
31 Mar 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P505000479431 Dec 202231 Mar 202531 Mar 2025Radiance InfraventureProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Sai Krishna Residency Wing B046

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

46 of 46 units booked (100%), as the promoter reported to MahaRERA

2BHK · 18 units3BHK · 17 unitsShop · 11 units
TypeCarpet areaUnitsBooked
2BHK1,248.67 sq m · 13,441 sq ft1818
3BHK1,516.72 sq m · 16,326 sq ft1717
Shop262.71 sq m · 2,828 sq ft1111

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

48 documents held by Deedo, 64 filings listed on MahaRERA's project page

Registration certificate

Other (10)

  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
Show all 112 documentsShow fewer documents

Other (10)

  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView

Layout plan (5)

  • Layout planDate not statedView
  • Layout planDate not statedView
  • Layout planDate not statedView
  • Layout planDate not statedView
  • Layout planDate not statedView

Commencement certificate

  • Commencement certificateDate not statedView

Form 1 (23)

  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView

Allotment letter

  • Allotment letterDate not statedView

Title report

  • Title reportDate not statedView

Encumbrance details (3)

  • Encumbrance detailsDate not statedView
  • Encumbrance detailsDate not statedView
  • Encumbrance detailsDate not statedView

Form 2

  • Form 2Date not statedView

Building plan

  • Building planDate not statedView

Form B

  • Form BDate not statedView

Legal

  • Legal Title reportLEGAL TITLE.pdf · uploaded 29 Jul 2022View
  • Declaration Form BFORM B.pdf · uploaded 29 Jul 2022View
  • Other – LegalMODEL AGREMENT TO SALES.pdf · uploaded 11 Nov 2022View

Migrated

  • 1 PAN Card1 PAN Card.pdf · uploaded 28 Jul 2022View
  • 1 Copy of the legal title reportLEGAL TITLE.pdf · uploaded 29 Jul 2022View
  • 1 a Details of encumbrances concerned to Financeencumbrance.pdf · uploaded 29 Jul 2022View
  • 1 b Details of encumbrances concerned to LegalENCUMBRANCE CERTIFICATE.pdf · uploaded 29 Jul 2022View
  • 1 Copy of Layout Approval (in case of layout)LAYOUT APPROVAL.pdf · uploaded 29 Jul 2022View
  • 1 Building Plan Approval / NA Order for plotted developmentMAP_organized_compressed.pdf · uploaded 29 Jul 2022View
  • 1 Commencement Certificates / NA Order for plotted developmentNMRD.pdf · uploaded 29 Jul 2022View
  • 1 Declaration about Commencement Certificatedeclaration.pdf · uploaded 29 Jul 2022Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 29 Jul 2022View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 29 Jul 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 29 Jul 2022View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A.pdf · uploaded 29 Jul 2022View
  • 1 CERSAI detailsCERSAI.pdf · uploaded 29 Jul 2022View
  • 1 Proforma of Allotment letterPROFOMA SALE DEED_merged.pdf · uploaded 8 Aug 2022View
  • 1 Deviation Report with respect to Allotment letterprofoma new_merged.pdf · uploaded 8 Aug 2022View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 9 Sep 2022View
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK DETAILS.pdf · uploaded 22 Oct 2022View
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 11 Nov 2022View
  • 1 Other – LegalMODEL AGREMENT TO SALES.pdf · uploaded 11 Nov 2022View
  • 1 Deviation Report with respect to model copy of AgreementNEW DEVIATION REPORT.pdf · uploaded 12 Nov 2022View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1_page-0001.pdf · uploaded 4 Apr 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1_page-0001.pdf · uploaded 4 Apr 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2_page-0001.pdf · uploaded 4 Apr 2024View
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2_page-0001.pdf · uploaded 4 Apr 2024View
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q-3_page-0001.pdf · uploaded 4 Apr 2024View
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q-4_page-0001.pdf · uploaded 4 Apr 2024View
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5_page-0001.pdf · uploaded 4 Apr 2024View
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 22-23 q-3.pdf · uploaded 29 Jun 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 22-23 q-4.pdf · uploaded 29 Jun 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 23-24 q-1.pdf · uploaded 29 Jun 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 23-24 q-2.pdf · uploaded 29 Jun 2024View
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 23-24 q-3.pdf · uploaded 29 Jun 2024View
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 23-24 q-4.pdf · uploaded 29 Jun 2024View
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 22-23 Q-3.pdf · uploaded 29 Jun 2024View
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 22-23 Q-4.pdf · uploaded 29 Jun 2024View
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 23-24 Q-1.pdf · uploaded 29 Jun 2024View
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 23-24 Q-2.pdf · uploaded 29 Jun 2024View
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 23-24 Q-3.pdf · uploaded 29 Jun 2024View
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 23-24 Q-4.pdf · uploaded 29 Jun 2024View
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 22-23 Q-3.pdf · uploaded 29 Jun 2024View
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 22-23 Q-4.pdf · uploaded 29 Jun 2024View
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 23-24 Q-1.pdf · uploaded 29 Jun 2024View
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 23-24 Q-2.pdf · uploaded 29 Jun 2024View
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 23-24 Q-3.pdf · uploaded 29 Jun 2024View
  • 7 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 23-24 Q-4.pdf · uploaded 29 Jun 2024View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A 23-24 Q-4.pdf · uploaded 29 Jun 2024View
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A 23-24 Q-3.pdf · uploaded 29 Jun 2024View
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A 23-24 Q-2.pdf · uploaded 29 Jun 2024View
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A 23-24 Q-1.pdf · uploaded 29 Jun 2024View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A 22-23 Q-3.pdf · uploaded 29 Jun 2024View
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A 22-23 Q-3.pdf · uploaded 29 Jun 2024View
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 29 Jun 2024View
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 29 Jun 2024View
  • 1 Architect’s Certificate on Completion of Project (Form 4)form 4.pdf · uploaded 18 Jan 2025View
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentform OC.pdf · uploaded 18 Jan 2025View
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf · uploaded 18 Jan 2025View
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)RADIANCE INFR WING B.pdf · uploaded 28 Jan 2025View

Technical

  • DocumentLAYOUT APPROVAL.pdf · uploaded 29 Jul 2022View
  • DocumentMAP_organized_compressed.pdf · uploaded 29 Jul 2022View

Technical (Architect)

  • Documentform 1 23-24 q-4.pdf · uploaded 29 Jun 2024View

Technical (Engineer)

  • DocumentFORM 2 23-24 Q-4.pdf · uploaded 29 Jun 2024View

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pipla, Nagpur (Rural) taluka

Survey, CTS, gat or plot numbers

KH NO 189/1 A MAUZA PIPLA

Boundaries

North
Kh No 190 Mouza Pipla
South
Kh No Part Of Mouza Pipla
East
18 Mt Wide Road
West
Kh No 188

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrashant Satpute—
Chartered accountantDilip Lohiya—
Chartered accountantKapil Jaiswal—
EngineerVarsha Hinge—
OtherHarshal Shankarrao Katol—