Paranjape Schemes (Construction) Ltd
Deedo IDDD-VDTVOf 24 registrations whose promised date has arrived, 9 kept it (38%). The rest ran a median 12 mo late.
Delivery record
20 of 32 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 32 registrations
32 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
Show all 44 casesShow fewer
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Forest Trails Athashri - B2P52100000029 | Bhugaon | Completed | 31 Jul 2022 | 31 Jul 2024 | +24 mo |
| SwapnasamratP52100000035 | Erandwana | Completed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| Blue Ridge Project C Land T18 and T19P52100000054 | Hinjavadi (Ct) | Completed | 31 Dec 2018 | — | On date |
| Blue Ridge - THE LOFTSP52100000060 | Hinjavadi (Ct) | Completed | 30 Dec 2022 | — | On date |
| Forest Trails HighlandP52100000066 | Bhugaon | Completed | 31 Mar 2018 | — | On date |
| Forest Trails HighlandP52100000067 | Bhugaon | Completed | 30 Dec 2022 | 30 Dec 2024 | +24 mo |
| AzureP52100000241 | Tathwade | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | On date |
| Happiness Hub - VarveP52100000303 | Varve Bk. | Certificate Signed | 31 Mar 2020 | 28 Mar 2025 | +60 mo |
| 127 Upper EastP51800000454 | Andheri | Certificate Signed | 31 Oct 2022 | 30 Jun 2024 | +20 mo |
| Paranjape Abhiruchi Parisar -T1, T2 , T3, M1A, M1B and M2P52100000452 | Dhayari | Certificate Signed | 31 Dec 2020 | 28 Mar 2025 | +51 mo |
| UjvalP51800000657 | Borivali | Certificate Signed | 31 Dec 2019 | 30 Sep 2022 | +33 mo |
| Gloria GrandP52100001380 | Bavadhan Bk | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Athashri SynergyP52100001787 | Mahalunge | Certificate Signed | 31 Jul 2022 | 31 Jul 2022 | On date |
| Athashri Baner CommercialP52100002667 | Baner | Certificate Signed | 31 Dec 2017 | 31 Dec 2018 | +12 mo |
| TridentP52100004511 | Wakad | Certificate Signed | 31 Jul 2023 | 30 Jul 2024 | +12 mo |
| TridentP52100015697 | Wakad | Certificate Signed | 30 Dec 2023 | 31 Dec 2025 | +35 mo* |
| AzureP52100016218 | Tathwade | Certificate Signed | 1 Jun 2022 | 1 Jun 2022 | On date |
| Blue Ridge Project E Land T24 and T25P52100016328 | Hinjavadi (Ct) | Certificate Signed | 1 Jun 2024 | 1 Jun 2024 | On date |
| Trident Commercial and MHADAP52100019023 | Wakad | Certificate Signed | 30 May 2023 | 30 May 2023 | On date |
| Magnolia Business CentreP52100021866 | Pashan | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Forest Trails Everglades H3 and H4P52100022655 | Bhugaon | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | +11 mo* |
| Madhukosh A 1P52100024073 | Haveli | Certificate Signed | 28 Feb 2026 | 28 Jun 2026 | +9 mo* |
| Azure Aster G and HP52100024186 | Tathwade | Certificate Signed | 28 Feb 2026 | 28 Jun 2026 | +9 mo* |
| Trident Business ParkP52100025946 | Wakad | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +5 mo* |
| Madhukosh EP52100026405 | Wadgaon Bk | Certificate Signed | 28 Feb 2026 | 28 Jun 2026 | +9 mo* |
| Trident E FP52100029377 | Wakad | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
| The Rivolo Residences at Forest TrailsP52100031560 | Bhugaon | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Cliff ResidencesP52100049098 | Bhugaon | Certificate Signed | 1 Jan 2028 | 1 Jan 2028 | On date |
| Abhiruchi MHADA 3P52100051322 | Dhayari | Certificate Signed | 1 May 2028 | 1 Sep 2028 | +4 mo |
| Samara HillsP52100052065 | Varve Kh. | Certificate Signed | 1 Jun 2028 | 1 Oct 2028 | +4 mo |
| Swaniketan At Forest TrailsP52100052124 | Bhugaon | Certificate Signed | 1 Jun 2028 | 1 Oct 2028 | +4 mo |
| The Orchard ResidencesP52100055710 | Bhugaon | Certificate Signed | 31 Mar 2029 | 31 Jul 2029 | +4 mo |
Show all 32 registrationsShow fewer
Paranjape Schemes (Construction) Ltd, in questions
Does Paranjape Schemes (Construction) Ltd finish projects on time?
Of 24 MahaRERA registrations whose promised completion date has arrived, 9 kept it (38%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Paranjape Schemes (Construction) Ltd registered with MahaRERA?
29 projects under 32 MahaRERA registrations; 18 completed on MahaRERA.
Does Paranjape Schemes (Construction) Ltd have MahaRERA regulatory cases?
44 regulatory cases name its registrations.