Paranjape Schemes (Construction) Ltd
Company or firm · 29 projects · 32 MahaRERA registrations
Also appears as PARANJAPE SCHEMES (CONSTRUCTION) LIMITED · Paranjape Schemes (Construction) Ltd.
Projects2932 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date58%14 of 24 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 10 extended
Regulatory cases4MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Forest Trails Athashri - B2P52100000029 | Bhugaon | 2017 | Not reported | 31 Jul 2022 | 31 Jul 2024 | +24 months |
| SwapnasamratP52100000035 | Pune (M Corp.) | 2017 | Not reported | 31 Mar 2019 | 30 Sep 2020 | +18 months |
| Blue Ridge Project C Land T18 and T19P52100000054 | Hinjavadi (Ct) | 2017 | Not reported | 31 Dec 2018 | — | On date |
| Blue Ridge - THE LOFTSP52100000060 | Hinjavadi (Ct) | 2017 | Not reported | 30 Dec 2022 | — | On date |
| Forest Trails HighlandP52100000066 | Bhugaon | 2017 | Not reported | 31 Mar 2018 | — | On date |
| Forest Trails HighlandP52100000067 | Bhugaon | 2017 | Not reported | 30 Dec 2022 | 30 Dec 2024 | +24 months |
| AzureP52100000241 | Tathwade | 2017 | Not reported | 30 Sep 2020 | — | On date |
| Happiness Hub - VarveP52100000303 | Varve Bk. | 2017 | Not reported | 31 Mar 2020 | 28 Mar 2025 | +60 months |
| 127 Upper EastP51800000454 | Andheri | 2017 | Not reported | 31 Oct 2022 | 30 Jun 2024 | +20 months |
| Paranjape Abhiruchi Parisar -T1,T2 ,T3, M1A, M1B and M2P52100000452 | Dhayari (Part) | 2017 | Not reported | 31 Dec 2020 | 28 Mar 2025 | +51 months |
| UjvalP51800000657 | Borivali | 2017 | Not reported | 31 Dec 2019 | 30 Sep 2022 | +33 months |
| Gloria GrandP52100001380 | Bavadhan Bk | 2017 | Not reported | 31 Dec 2026 | 31 Dec 2026 | On date |
| Athashri SynergyP52100001787 | Mahalunge | 2017 | Not reported | 31 Jul 2022 | — | On date |
| Athashri Baner CommercialP52100002667 | Baner | 2017 | Not reported | 31 Dec 2017 | 31 Dec 2018 | +12 months |
| TridentP52100004511 | Wakad | 2017 | Not reported | 31 Jul 2023 | 30 Jul 2024 | +12 months |
| TridentP52100015697 | Wakad | 2018 | Not reported | 30 Dec 2023 | 31 Dec 2025 | +24 months |
| AzureP52100016218 | Tathwade | 2018 | Not reported | 1 Jun 2022 | — | On date |
| Blue Ridge Project E Land T24 and T25P52100016328 | Hinjavadi (Ct) | 2018 | Not reported | 1 Jun 2024 | — | On date |
| Trident Commercial and MHADAP52100019023 | Wakad | 2018 | Not reported | 30 May 2023 | — | On date |
| Magnolia Business CentreP52100021866 | Pashan | 2019 | Not reported | 30 Dec 2024 | — | On date |
| Forest Trails Everglades H3 and H4P52100022655 | Bhugaon | 2019 | Not reported | 30 Dec 2025 | — | On date |
| Madhukosh A 1P52100024073 | Haveli | 2020 | Not reported | 28 Feb 2026 | — | On date |
| Azure Aster G and HP52100024186 | Tathwade | 2020 | Not reported | 28 Feb 2026 | — | On date |
| Trident Business ParkP52100025946 | Wakad | 2020 | Not reported | 30 Jun 2026 | — | On date |
| Madhukosh EP52100026405 | Wadgaon Bk | 2020 | Not reported | 28 Feb 2026 | — | On date |
| Trident E FP52100029377 | Wakad | 2021 | Not reported | 31 Dec 2027 | — | On date |
| The Rivolo Residences at Forest TrailsP52100031560 | Bhugaon | 2021 | Not reported | 31 Dec 2027 | — | On date |
| Cliff ResidencesP52100049098 | Bhugaon | 2023 | Not reported | 1 Jan 2028 | — | On date |
| Abhiruchi MHADA 3P52100051322 | Dhayari (Part) | 2023 | Not reported | 1 May 2028 | — | On date |
| Samara HillsP52100052065 | Varve Kh. | 2023 | Not reported | 1 Jun 2028 | — | On date |
| Swaniketan At Forest TrailsP52100052124 | Bhugaon | 2023 | Not reported | 1 Jun 2028 | — | On date |
| The Orchard ResidencesP52100055710 | Bhugaon | 2024 | Not reported | 31 Mar 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 14 of 24 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 60 months, for Happiness Hub - Varve (P52100000303).
- MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: FOREST TRAILS ATHASHRI - B2 (Regulatory Case No.85 of 2023) dated 7 November 2023. · Forest Trails Athashri - B2 · P52100000029 · 7 Nov 2023
- Regulatory orderRegulatory order: PROJECT NAME: FOREST TRAILS HIGHLAND TOWER 9 10 AND 1(Regulatory Case No.84 of 2023) dated 7 November 2023. · Forest Trails Highland · P52100000067 · 7 Nov 2023
- Regulatory orderRegulatory order: PROJECT NAME: 127 UPPER EAST(Regulatory Case No.83 of 2023) dated 7 November 2023. · 127 Upper East · P51800000454 · 7 Nov 2023
- DeregisteredDeregistered: CLIFF RESIDENCES · Cliff Residences · P52100049098
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology