Residential / Group Housing · 14 buildings · 378 unitsRERA P52100000066 +1

Forest Trails Highland

Deedo IDDP-PUN-1PK6

MahaRERA shows it completed, after its date was pushed back 2 years; 16 listings and orders with MahaRERA on record; 74% of its units are booked.

Bhugaon, Pune 412115 · Property rates in Bhugaon · by Paranjape Schemes (Construction) Ltd · 38% of its projects kept the RERA date

DeliveryCompletedAs MahaRERA shows · after a 2 yrs extensionRegulatory16 listings and ordersLatest: Regulatory order, 2023Sales74% booked278 of 378 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 2 years

  • P52100000066Registered 22 Jun 2017, completion promised 31 Mar 2018.
  • P52100000067Registered 22 Jun 2017, completion promised 30 Dec 2022, revised to 30 Dec 2024.

1 extension certificate on record.

2 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

14 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory record16

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Show all 16 listings and ordersShow fewer listings and orders

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations2
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000006622 Jun 201731 Mar 2018—Paranjape Schemes (Construction) LimitedProject page
P5210000006722 Jun 201730 Dec 202230 Dec 2024Paranjape Schemes (Construction) LimitedProject page
Documents184

55 documents held by Deedo, 129 filings listed on MahaRERA's project page

Commencement certificate (3)

  • Commencement certificateP52100000066 · 15 Jun 2017ViewSource
  • Commencement certificateP52100000067 · 5 Aug 2017ViewSource
  • Commencement certificateP52100000067 · 26 May 2023ViewSource

Title report

Layout plan (2)

Form B (2)

Show all 184 documentsShow fewer documents

Building plan

Form 1 (7)

Registration certificate (2)

  • Registration certificateP52100000066 · 22 Jun 2017ViewSource
  • Registration certificateP52100000067 · 9 Sep 2021ViewSource

Allotment letter (2)

Form 4 (2)

Form 2A (5)

Other (17)

Form 5 (3)

Form 2 (6)

Encumbrance details

  • Encumbrance detailsP52100000067 · 26 May 2023ViewSource

Extension certificate

  • Extension certificateP52100000067 · 21 Nov 2023ViewSource

Document library

  • Commencement Certificates / NA Order for plotted developmentP52100000066 · forest trails 7 8 cc page1.pdf · uploaded 15 Jun 2017View
  • Commencement Certificates / NA Order for plotted developmentP52100000066 · Sanction Layout Page 2.pdf · uploaded 15 Jun 2017View
  • Copy of the legal title reportP52100000067 · Title Certificate_MDPL Highland 9,10,11.pdf · uploaded 19 Jun 2017View
  • Details of encumbrancesP52100000067 · Encumbrance Certificate_MDPL Highland 9,10, 11.pdf · uploaded 19 Jun 2017View
  • Proforma of Allotment letterP52100000067 · Proforma_Allotment Ltr AND Agreement_MDPL 9,10,11.pdf · uploaded 19 Jun 2017View
  • Copy of Layout Approval (in case of layout)P52100000067 · sancion layout 9 10 11.pdf · uploaded 19 Jun 2017View
  • Copy of the legal title reportP52100000066 · Title Certificate_MDPL Highland 7,8.pdf · uploaded 19 Jun 2017View
  • Details of encumbrancesP52100000066 · Encumbrance Certificate_MDPL Highland 7,8.pdf · uploaded 19 Jun 2017View
  • Proforma of Allotment letterP52100000066 · Proforma_Allotment Ltr and Agreement_MDPL Highland 7, 8.pdf · uploaded 19 Jun 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000066 · FORM 1 Forest Trails 7 8.pdf · uploaded 19 Jun 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · Form 1 Forest Trails 9 10 11.pdf · uploaded 19 Jun 2017View
  • Building Plan Approval (IOD)P52100000067 · sancion layout 9 10 11.pdf · uploaded 19 Jun 2017View
  • Commencement Certificates / NA Order for plotted developmentP52100000067 · CC 9 10 11.pdf · uploaded 19 Jun 2017View
  • Declaration in FORM BP52100000066 · Form B_MDPL Highland 7, 8.pdf · uploaded 19 Jun 2017View
  • Declaration in FORM BP52100000067 · Form B Forest Trails 9 10 11.pdf · uploaded 19 Jun 2017View
  • Copy of Layout Approval (in case of layout)P52100000066 · Tower 7 and 8 Layout plan.pdf · uploaded 20 Jun 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000066 · Form 2 Forest Trials 7 and 8.pdf · uploaded 20 Jun 2017View
  • Building Plan Approval (IOD)P52100000066 · Tower 7 and 8 Layout plan.pdf · uploaded 20 Jun 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · Forest trails T-9,10,11 Engineers certificate.pdf · uploaded 20 Jun 2017View
  • Commencement Certificates / NA Order for plotted developmentP52100000067 · Revised CC_Forest Trails Highland Tower 9 10 and 11.pdf · uploaded 5 Aug 2017View
  • Copy of Layout Approval (in case of layout)P52100000067 · Revised Sanction Layout _FOREST TRAILS HIGHLANDTOWER 9 10 11.pdf · uploaded 5 Aug 2017View
  • Building Plan Approval (IOD)P52100000067 · Revised Sanction Layout _FOREST TRAILS HIGHLANDTOWER 9 10 11.pdf · uploaded 5 Aug 2017View
  • Proforma of Allotment letterP52100000066 · Forest Trails-T7 and 8 - Proforma_Allotment Ltr and Agreement_MDPL Highland 7, 8.pdf · uploaded 29 Sep 2017View
  • Proforma of Allotment letterP52100000067 · Forest Trails- T9, 10, 11 - Proforma_Allotment Ltr and Agreement_MDPL 9,10,11.pdf · uploaded 29 Sep 2017View
  • Certificates of Architect (Form 4)P52100000066 · Highland Tower 7 8 Form 4 and OC.pdf · uploaded 2 Apr 2018View
  • Declaration in FORM BP52100000067 · FT 9 10 11 FORM B Promoter.pdf · uploaded 28 Nov 2018View
  • Certificates of CA (Form 5)P52100000067 · Highland 9,10,11.pdf · uploaded 18 Dec 2018View
  • Certificates of CA (Form 5)P52100000066 · FT - 7,8.pdf · uploaded 18 Dec 2018View
  • Status of ConveyanceP52100000066 · Society Certificate_Highlands 7, 8.pdf · uploaded 28 Feb 2019View
  • Status of Formation of Legal Entity (Society/Co Op etc.)P52100000066 · Society Certificate_Highlands 7, 8.pdf · uploaded 28 Feb 2019View
  • Certificates of Architect (Form 4)P52100000066 · Completion Certificate T7 T8 Forest Trails uploaded 18 Oct 209.pdf · uploaded 18 Oct 2019View
  • Copy of the legal title reportP52100000066 · Title Certificate MDPL Highland 7,8 post merger uploaded 18 oct2019.pdf · uploaded 18 Oct 2019View
  • Proforma of Allotment letterP52100000066 · Agreement to Sell Highlands 7 and 8 Ready Possession Post Merger FINAL uploaded 18 oct 2019.pdf · uploaded 18 Oct 2019View
  • Certificates of CA (Form 5)P52100000067 · Forest Trails T9,10,11_Form 5_18-19.pdf · uploaded 19 Oct 2019View
  • Copy of the legal title reportP52100000067 · Forest Trails Highland Tower 9 10 11 Title Certificate Post Merger28Aug2019.pdf · uploaded 11 Nov 2019View
  • Proforma of Allotment letterP52100000067 · FT Highland Tower 9,10 11 Proforma Allotment Letter ATS Post Merger 11 nov 2019.pdf · uploaded 11 Nov 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100000067 · 10 RERA FT 9 10 11 compressed.pdf · uploaded 1 Apr 2021View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100000067 · Form 5 FT Highlands 9,10,11-min_compressed.pdf · uploaded 13 Jul 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100000067 · Form 5 FT Highlands 9,10,11-min_compressed.pdf · uploaded 14 Jul 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100000067 · 2 1JUNE SEPT 2019.pdf · uploaded 14 Jul 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100000067 · 2 2 DEC2019 MARCH 2020.pdf · uploaded 14 Jul 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100000067 · 3 2FT 9 10 11 DEC 2020 MARCH 2021.pdf · uploaded 14 Jul 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100000067 · 4 2 DEC 2021 MARCH 2022.pdf · uploaded 14 Jul 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100000067 · 5 FT 9 10 11 FORM2A upto June2022.pdf · uploaded 14 Jul 2022View
  • Declaration about Commencement CertificateP52100000067 · Format D Declration about commencement.pdf · uploaded 14 Jul 2022View
  • CERSAI detailsP52100000067 · CERSAI Report HDFC.pdf · uploaded 15 Jul 2022View
  • CERSAI detailsP52100000067 · CERSAI Report IDBI Trusteeship.pdf · uploaded 15 Jul 2022View
  • CERSAI detailsP52100000067 · CERSAI Report IDBI TShip.pdf · uploaded 15 Jul 2022View
  • Disclosure of sold/ booked inventoryP52100000067 · Disclosure Report June 2022.pdf · uploaded 18 Jul 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P52100000067 · Forest Trails T9 10 11 Form 5 18-19.pdf · uploaded 20 Jul 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100000067 · Highlands T9 10 11 Qurter ending Sept 2022.pdf · uploaded 28 Sep 2022View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · 1 FT 9 10 11- FORM 2-Sept 17 to mar 18-merged -compressed.pdf · uploaded 23 Jan 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · 2 FT 9 10 11 -FORM 2-June 18 to Mar 19-merged and compressed.pdf · uploaded 23 Jan 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · 3 FT 9 1011 -FORM 2-June 19 to mar 21-merged and compressed.pdf · uploaded 23 Jan 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · 4 Ft 9 10 11 -FORM 2-June 21 to Dec21-merged and compressed.pdf · uploaded 23 Jan 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · 5 FT 9 10 11-FORM2 -T91011-Mar 22-uploaded.pdf · uploaded 23 Jan 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · 6 FT 9 10 11 FORM2 --Sep 22-uploaded.pdf · uploaded 23 Jan 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · 7 Ft 9 10 11 -FORM2 -Dec 22-uplaoded.pdf · uploaded 23 Jan 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · 20180326 FT 9,10,11 FORM-1 FOR RERA.pdf · uploaded 25 Jan 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · 1 FT 9 10 11 Form 1-June 18 to Mar 18 Compressed merged-uploaded.pdf · uploaded 25 Jan 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · 2 FT 9 1011 -FORM 1-Jne 19 Dec 19 merged and compressed-uploaded.pdf · uploaded 25 Jan 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · 2021-04-29 Highlands T9 10 11-RERA Form1.pdf · uploaded 25 Jan 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · FT Athashri-B2 RERA Form-1-Sept 2022.pdf · uploaded 25 Jan 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · Highlands T 91011 - 2017 -2021.pdf · uploaded 1 Feb 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · Highlands T 91011 -March 2022.pdf · uploaded 1 Feb 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · Highlands T 91011-June 2022.pdf · uploaded 1 Feb 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · Highlands T 91011-Dec-2022.pdf · uploaded 1 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100000067 · FT T91011-FORM 5-FY 21-22-uploded 03 Feb2023.pdf · uploaded 3 Feb 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · 5 Highlands T91011-RERA Form-1-Mar 23-uploaded.pdf · uploaded 8 Apr 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · 19 FORM 2-Forest Trails the Highland Tower 91011-Mar 23.pdf · uploaded 19 May 2023View
  • Details of encumbrancesP52100000067 · Encumbrances Letter-Financial Dues- FT 9,10,11.pdf · uploaded 26 May 2023View
  • Declaration about Commencement CertificateP52100000067 · FORMAT D Highland T 9 10 11.pdf · uploaded 26 May 2023View
  • Declaration in FORM BP52100000067 · FORM B -Affidavit-FT T 9,10,11.pdf · uploaded 26 May 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100000067 · FORM 2A -FT T 9,10,11.pdf · uploaded 26 May 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · Highlands T-9 10 11.pdf · uploaded 3 Jun 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100000067 · FORM 2A FT91011 June 23.pdf · uploaded 7 Jul 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · FORM 2-Highland Tower 91011-June'23.pdf · uploaded 7 Jul 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · FORM 1-Highlands T- 9,10, 11-uplaoded.pdf · uploaded 11 Jul 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100000067 · 2 A SEPT 23 T91011-Uploaded.pdf · uploaded 3 Oct 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · FORM 1-Highlands T-91011-Sept'23.pdf · uploaded 5 Oct 2023View
  • Disclosure of sold/ booked inventoryP52100000067 · Inventory data-Forest Trails Highland T91011-Sept'23-uploaded.pdf · uploaded 10 Oct 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · FORM 2-Forest Trails The Highland T-91011-Sept'23-uploaded.pdf · uploaded 11 Oct 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100000067 · FORM 5- FT Highland Tower 91011-Fy'22-23.pdf · uploaded 11 Oct 2023View
  • Disclosure of sold/ booked inventoryP52100000067 · tower 9 10 11 Circular 29 (1).pdf · uploaded 12 Oct 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · FORM 2-Highland Tower 91011-Dec'23-uplaoded.pdf · uploaded 10 Jan 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100000067 · FORM 2 A DEC 2023 T91011-uplaoded.pdf · uploaded 10 Jan 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · FORM 1-FTHighlands T-91011-Dec'23-uplaoded.pdf · uploaded 10 Jan 2024View
  • Disclosure of sold/ booked inventoryP52100000067 · 8 FT T-910 11-Disclosure-Dec'23-uploaded.pdf · uploaded 11 Jan 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100000067 · FORM 2A-Highlands T91011-Mar'24-uploaded.pdf · uploaded 1 Apr 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · FORM 2-FT HIGHLAND TOWER 91011-Mar'24-uploaded.pdf · uploaded 4 Apr 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · Form 1-FT 91011-Mar'24-uploaded.pdf · uploaded 6 Apr 2024View
  • Disclosure of sold/ booked inventoryP52100000067 · Inventory Report-Highland T-91011-Mar'24-uploaded.pdf · uploaded 17 Apr 2024View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · 10 FT Highlands T-91011-FORM 1-June'24-uploaded.pdf · uploaded 4 Jul 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · 3 FT Highland T-91011-FORM 2A-June'24-uploaded.pdf · uploaded 4 Jul 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · 23FORM 2- FT Highland T-91011-June'24-uploaded.pdf · uploaded 8 Jul 2024View
  • Copy of Layout Approval (in case of layout)P52100000067 · Layout Plan-June'24-compressed-uplaoded.pdf · uploaded 9 Jul 2024View
  • Building Plan Approval (IOD)P52100000067 · Building Plan Approval-FT 91011-compressed-June'24-uploaded.pdf · uploaded 9 Jul 2024View
  • Commencement Certificates / NA Order for plotted developmentP52100000067 · Commencement FT 91011-21June'24-uploaded.pdf · uploaded 9 Jul 2024View
  • Declaration about Commencement CertificateP52100000067 · FORMAT D-Declarn about Commencement-uploaded.pdf · uploaded 9 Jul 2024View
  • Disclosure of sold/ booked inventoryP52100000067 · Disclosure-sod-unsold FTHighland T-91011-June'24-uploaded.pdf · uploaded 20 Jul 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100000067 · FORM 5-FT91011-FY '23-24-uploaded.pdf · uploaded 7 Oct 2024Source
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · FORM 1-Highlands T-91011-Sept'24-uploaded.pdf · uploaded 17 Oct 2024View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · FORM 2-FTHighland T-91011-Sept'24-uploaded.pdf · uploaded 17 Oct 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100000067 · FT T9 COMPLETION-27SEP'24.pdf · uploaded 23 Dec 2024Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100000067 · FT T10 Completion-16Dec'24.pdf · uploaded 23 Dec 2024Source
  • Architect’s Certificate on Completion of Project (Form 4)P52100000067 · Form 4 Highlands T91011-uploaded.pdf · uploaded 8 Jan 2025View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100000067 · T11 - Completion - 31Dec 24-uploaded.pdf · uploaded 8 Jan 2025View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · Form 1-Highland T-9 10-11-Dec'24-uplaoded.pdf · uploaded 15 Jan 2025View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000067 · Form 2 -FT The Highland T91011-Dec'24-uploaded.pdf · uploaded 24 Jan 2025View
  • Architect’s Certificate on Completion of Project (Form 4)P52100000067 · Form 4 Highlands T91011- recd uploaded on 07 Jan'25.pdf · uploaded 28 Jan 2025View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000067 · FORM 1-FT T-91011-MAR'25-uploaded.pdf · uploaded 8 Apr 2025View

Promoter documents

  • Legal Title reportP52100000067 · Title Certificate_MDPL Highland 9,10,11.pdf · uploaded 19 Jun 2017View
  • Legal Title reportP52100000066 · Title Certificate_MDPL Highland 7,8.pdf · uploaded 19 Jun 2017View
  • Declaration Form BP52100000066 · Form B_MDPL Highland 7, 8.pdf · uploaded 19 Jun 2017View
  • Declaration Form BP52100000067 · Form B Forest Trails 9 10 11.pdf · uploaded 19 Jun 2017View
  • Declaration Form BP52100000067 · FT 9 10 11 FORM B Promoter.pdf · uploaded 28 Nov 2018View
  • Legal Title reportP52100000066 · Title Certificate MDPL Highland 7,8 post merger uploaded 18 oct2019.pdf · uploaded 18 Oct 2019View
  • Legal Title reportP52100000067 · Forest Trails Highland Tower 9 10 11 Title Certificate Post Merger28Aug2019.pdf · uploaded 11 Nov 2019View
  • Declaration Form BP52100000067 · FORM B -Affidavit-FT T 9,10,11.pdf · uploaded 26 May 2023View

Technical documents

  • Building Plan ApprovalP52100000066 · Tower 7 and 8 Layout plan.pdfView
  • Layout ApprovalP52100000066 · Tower 7 and 8 Layout plan.pdfView
  • Building Plan ApprovalP52100000067 · sancion layout 9 10 11.pdfView
  • Layout ApprovalP52100000067 · sancion layout 9 10 11.pdfView
  • Layout ApprovalP52100000067 · Revised Sanction Layout _FOREST TRAILS HIGHLANDTOWER 9 10 11.pdfView
  • Building Plan ApprovalP52100000067 · Revised Sanction Layout _FOREST TRAILS HIGHLANDTOWER 9 10 11.pdfView
  • Layout ApprovalP52100000067 · Layout Plan-June'24-compressed-uplaoded.pdfView
  • Building Plan ApprovalP52100000067 · Building Plan Approval-FT 91011-compressed-June'24-uploaded.pdfView

Proforma allotment letter

  • Proforma allotment letterP52100000066 · Proforma_Allotment Ltr and Agreement_MDPL Highland 7, 8.pdfView
  • Proforma allotment letterP52100000067 · Proforma_Allotment Ltr AND Agreement_MDPL 9,10,11.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsSurvey 16/1, Sector No.R12B

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Phases
2
Address
Sector No.R-12 Part, Survey No. 16/1 and others, Matalwadi Road, Bhugaon Road, BhugaonPIN 412115
Village
Bhugaon, Mulshi taluka
Land area for this project
6,735 sq m (72,495 sq ft)
Permissible built-up area
14,377 sq m (1,54,751 sq ft)
Sanctioned built-up area
14,377 sq m (1,54,751 sq ft)
Recreational open space
3,853 sq m (41,478 sq ft)
Designated bank account
Hdfc Bank
Litigation declared by promoter
Yes
Financial encumbrance declared
None declared
Also registered as
Forest Trails Highland Tower 7 and 8, Forest Trails Highland Tower 9, 10 and 11

Survey, CTS, gat or plot numbers

16/1Sector No.R12BSector No.R12 PartSurvey No. 16/1

Land as published on MahaRERA's project page

Sector No.R-12 Part, Survey No. 16/1 and others, Matalwadi Road

Boundaries

North
Sector R12 Part
South
18 Mtr Township Road And Sector No G40a Part
East
Sector No G40a
West
Sector No R12b And Os7

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking565 parking spaces

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Tower 10Closed/Covered0000170
Tower 10Open Space00000
Tower 11Closed/Covered0000115
Tower 11Open Space00000
Tower 7Closed/Covered000081
Tower 7Open Space00000
Tower 8Closed/Covered000084
Tower 8Open Space00000
Tower 9Closed/Covered0000115
Tower 9Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress6 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Tower 10

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
  • Sanitary Fittings within the flats / premises85%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Tower 11

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
  • Sanitary Fittings within the flats / premises42%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Tower 7

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Show all 6 buildings and common areasShow fewer buildings and common areas

Tower 8

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Tower 9

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsFoot Paths only65%
  • Water Supply85%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Project Specific STP95%
  • Storm Water Drains90%
  • Landscaping & Tree Planting80%
  • Street Lighting90%
Show all 36 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterProject Specific STP95%
  • Solid Waste Management And Disposal10%
  • Water conservation /Rain water harvesting0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirements40%
  • Electrical meter room, sub-station, receiving station15%
  • Aggregate area of recreational Open Spacework done for aggregate open space of township50%
  • Open ParkingNot applicable
  • CLUB HOUSE0%
  • MULTI PUROPSE HALL0%
  • SWIMMING POOL0%
  • Internal Roads & Footpathsfoot paths only82%
  • Water Supply92%
  • Sewerage (Chamber, Lines, Septic Tank , STP)STP of sector R12 (part) of township90%
  • Storm Water Drains92%
  • Landscaping & Tree Planting81%
  • Street Lighting91%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage Water90%
  • Solid Waste Management And DisposalSTP of sector R12 (part) of township90%
  • Water conservation /Rain water harvesting80%
  • Energy managemcnt0%
  • Fire protection and fire safety requirements95%
  • Electrical meter room, sub-station, receiving station90%
  • Aggregate area of recreational Open Spacework done for aggregate open space of township80%
  • Open ParkingNot applicable
  • SWIMMING POOL95%
  • MULTI PURPOSE HALL100%
  • CLUB HOUSE95%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals12

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectAniruddha Aniruddha Vaidya & Associates—P52100000066
EngineerJ + W Consultants—P52100000066
OtherBjr Construction Pvt Ltd—P52100000066
OtherMegh Civil Constuction—P52100000066
OtherM N Furniture—P52100000066
OtherN B Enterprises—P52100000066
OtherNoor Enterprises—P52100000066
OtherPatil Enterprises—P52100000066
Show all 12 professionalsShow fewer professionals
RoleNameRegistration no.RERA
OtherReva Electrical—P52100000066
OtherSheenath Plumbing Works—P52100000066
OtherShivkumar Sharma—P52100000066
OtherSs Enterprises—P52100000066

Source: MahaRERA project page. Contact details are not shown.

Data through12 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Report a problemMethodology