Forest Trails Highland
Completion date passedBhugaon, Pune 412115 |Promoter: Paranjape Schemes (Construction) Limited
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Mar 2018
P52100000066The latest completion date on record passed 8 years and 7 months ago.
- Registered
- 22 Jun 2017
- Promised
- 31 Mar 2018
Completion pushed back 2 years
P52100000067The latest completion date on record passed 1 year and 10 months ago.
- Registered
- 22 Jun 2017
- Promised
- 30 Dec 2022
- Revised
- 30 Dec 2024
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100000066 | 22 Jun 2017 | 31 Mar 2018 | — | Paranjape Schemes (Construction) Limited | Project page |
| P52100000067 | 22 Jun 2017 | 30 Dec 2022 | 30 Dec 2024 | Paranjape Schemes (Construction) Limited | Project page |
Documents
3 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- Regulatory order7 Nov 2023Matched by RERA number
Regulatory order: PROJECT NAME: FOREST TRAILS HIGHLAND TOWER 9 10 AND 1(Regulatory Case No.84 of 2023) dated 7 November 2023.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Bhugaon
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.