P52100000067

Forest Trails Highland · Bhugaon, Pune · Paranjape Schemes (Construction) Ltd

Promised for 30 Dec 2022; MahaRERA reports the project completed.

The revised date is 2 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2022 to 30 Dec 2024 (1 extension certificate on record).
  • Caution: 15 other MahaRERA orders name this registration.
  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 45

Building plan19 Jun 2017View
Commencement certificate5 Aug 2017View
Allotment letter29 Sep 2017View
Form B28 Nov 2018View
Registration certificate9 Sep 2021View
Form 2A14 Jul 2022View
Form 2A14 Jul 2022View
Other18 Jul 2022View
Show all 45 documents
Form 520 Jul 2022View
Form 223 Jan 2023View
Form 223 Jan 2023View
Form 223 Jan 2023View
Form 125 Jan 2023View
Form 125 Jan 2023View
Form 11 Feb 2023View
Form 18 Apr 2023View
Encumbrance details26 May 2023View
Commencement certificate26 May 2023View
Form 27 Jul 2023View
Form 511 Oct 2023View
Extension certificate21 Nov 2023View
Form 110 Jan 2024View
Form 2A10 Jan 2024View
Other11 Jan 2024View
Form 2A1 Apr 2024View
Form 24 Apr 2024View
Form 2A8 Jul 2024View
Form 520 Jul 2024View
Form 417 Oct 2024View
Form 224 Jan 2025View
Form 18 Apr 2025View
OtherView
OtherView
OtherView
Layout planView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 15

Regulatory order

Regulatory order: PROJECT NAME: FOREST TRAILS HIGHLAND TOWER 9 10 AND 1(Regulatory Case No.84 of 2023) dated 7 November 2023.

7 Nov 2023 · matched by RERA number

View order →
Show all 15 orders and lists

Questions about P52100000067

Is Forest Trails Highland delayed?

MahaRERA reports it completed. Its promised completion date was 30 Dec 2022.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100000067. The completion date moved from 30 Dec 2022 to 30 Dec 2024.

Who is the promoter?

MahaRERA records Paranjape Schemes (Construction) Ltd as the promoter of P52100000067.

Is it on any MahaRERA regulatory list?

15 MahaRERA orders or lists name P52100000067.

Answers are generated from the record.

Data through23 Nov 2026, 01:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology